Cumming · Zoning Ordinance
Part II - CODE OF ORDINANCES / Part B - PLANNING, ZONING, DEVELOPMENT AND UTILITIES / Chapter 109 - SUBDIVISION AND LAND DEVELOPMENT REGULATIONS AND CONSTRUCTION SPECIFICATIONS / Article V - STORM DRAINAGE AND WATERSHED PROTECTION
Sec. 109-366. Same—Facility design criteria.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) All designs, calculations, and rationale must follow the principles set forth in the city stormwater manual.
(b) Stormwater runoff must be managed to control the velocity at the point of discharge so as to minimize accelerated erosion of the site and increased sedimentation of the streams. Soil erosion and sedimentation control measures, structures and devices shall be so planned, designed and constructed as to provide for a range of design
flows for flood control. These design flows should be demonstrated for the two-, ten-, and 25-year storm events using the procedures as outlined in the United States Department of Agriculture Soil Conservation Service's Technical Release 55 Urban Hydrology for Small Watersheds or other acceptable calculation procedures. All BMPs must
be designed for a 25-year storm. All stormwater management facilities must have outlet devices able to effectively route the 100-year storm. All disturbed land must drain to an approved BMP, and stormwater runoff must be managed for the entire drainage area above the detention system or BMP.
(c) Stormwater management facilities can only be located in perennial streams with strict adherence to United States Army Corps of Engineers permitting requirements. Such in-stream facilities do not include those for controlling erosion at land disturbing activities. Proper documentation
demonstrating compliance with corps requirements must be provided before the city will permit the in-stream stormwater management facility. Additionally, a dredging plan depicting how the facility will be cleaned of silt accumulations in
the future must be provided prior to permitting.
(d) During construction, all land disturbing activities (to include all land uses) must comply with sedimentation and erosion control procedures/ program as defined by General Permit (No.
GAR100000), and per the soil and sediment control ordinance in chapter 107.
(e) Applicants must demonstrate compliance with the stormwater control plan to the city prior to approval of any building or subdivision permit request.
(f) After construction, runoff from the first 1.0 inch of rainfall must be captured and released evenly over a 48-hour period. Facilities must maintain peak flows for the two-, ten-, and 25- year storm at the property boundaries equal to or less than flow under undeveloped conditions and be able to route a 100-year storm through the facility. The site must discharge no more than a calculated 65 pounds of suspended solids per acre per year. The suspended solids discharge rate is to be calculated using the city stormwater quality performance review form, and no water quality monitoring is required to verify compliance with this suspended solids requirement. Alternative best management practices and alternative modeling methods are allowed and encouraged provided the same theoretical level of stormwater quality and quantity is achieved. The city will
verify that best management practices deemed necessary by the city stormwater quality performance review form, or the approved alternative modeling method, are installed on site. The property owner may choose to designate additional undisturbed buffer areas to reach the targeted
suspended solids discharge rate. The proper installation and maintenance of BMPs, undisturbed upland areas, and stream buffers deemed necessary by the city stormwater quality performance review form, or alternative modeling method,
shall constitute a complete defense to any allegation of noncompliance with this subsection, regardless of the result of water quality monitoring.
The city stormwater quality performance review form uses the following BMP efficiencies and loading rates to calculate the discharge of suspended solids:
(1) BMP efficiencies.
BMP
TSS Removal (percent) Extended detention pond (wet/dry) 80 Dry detention pond 50 Constructed wetland 80 Vegetated filter strips 50 Sand filters 80 Infiltration trenches 80 Oil/grit separator 60
BMP
TSS Removal (percent) Grassed swales 15
(2) Total suspended solids (TSS) loading rates applied to land use categories.
Land Use Category TSS Loading Rate (lb/ac/yr) Undisturbed upland area (woods, preserves, etc.)
30 Undisturbed stream buffers 15 Disturbed pervious area (lawns, gardens, porous pavement, etc.)
65 Impervious area (driveways, rooftops, parking lots, etc.)
400
(g) Stormwater management facility fencing.
Fences and warning signs will be required on all detention ponds, constructed wetlands, retention ponds or similar devices where the sides of the device adjacent to the water are steeper than 3:1 and the depth of the water in the pond is greater than three feet. Fences shall be five-foot-high chain link or other approved material with a 12-foot-wide gate. The gate shall be locked with a master number one lock that is keyed as per the city, and two keys will be provided to the city.
Fences shall be located on the outside edge of the 20-foot perimeter easement when possible.
(h) A silt gauge will be installed on all detention ponds consisting of a durable, weatherresistant post. The post will be embedded a minimum of two feet and extend a minimum of five feet above the ground. Numbers and adjacent tick
marks must be on the post beginning with the number "1" at one foot above the ground elevation and thereafter a number and tick mark for each corresponding foot. Numbers and tick marks must be clear, readable, weather-resistant, and durable.
(i) A concrete survey marker shall be placed in the near vicinity of the stormwater management facility. The marker shall be a minimum of five inches by five inches in width and be embedded one foot into the ground. The marker shall have a "PK" nail embedded in the top. The marker must be placed above the high water elevation of the facility and within the drainage easement area.
Alternate survey markers are allowed with prior approval from the city.
(j) Outlet structures and piping for residential stormwater management facilities must be constructed of concrete to be eligible for acceptance into the city maintenance system.
(k) All stormwater inlets installed by the developer shall have a storm sewer stencil or insignia approved by the planning and zoning director.
History
(Ord. of 3-16-2004(02), § III(10.11))
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.