Section 1304. Construction Progress

About this text

  • As posted on the city's website, retrieved 2026-11-25

If no substantial construction progress has been made within six (6) months of the date of issuance of the building permit, the permit becomes invalid. The permit may be re-issued only upon completion of the application procedure outlined in Sections 1301 and 1303 of this Resolution.