Sec. 16-62. Enforcement and penalties.

About this text

  • As published by Municode, current through 2020-02-10
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Enforcement.

(1) The community development department will periodically inspect the sites of land-disturbing activities for which permits have been issued to determine if the activities are being conducted in accordance with the plan and if the measures required in the plan are effective in controlling erosion, sedimentation and

pollution.

(2) The city must regulate both primary and secondary permittees as such terms are defined in the state general permit. Primary permittees are responsible for installation and maintenance of best management practices where the primary permittee is conducting land-disturbing

activities. Secondary and tertiary permittees are responsible for installation and maintenance of best management practices where the permittees are conducting land-disturbing activities. If, through inspection, it is deemed that a person

engaged in land-disturbing activities as defined herein has failed to comply with the approved plan, with permit conditions, or with the provisions of this division, a written notice to comply must be served upon that person by the community development director. The notice must set forth the measures necessary

to achieve compliance and must state the time within which such measures must be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, that

person will be deemed in violation of this division.

(3) The community development director has the power to conduct any investigations necessary to carry out duties as prescribed in this division, and for this purpose to enter at reasonable times upon any property, public or private, for the

purpose of investigation and inspecting the sites of land-disturbing activities.

(4) No person may refuse entry or access to any authorized representative or agent of the city, the soil and water conservation commission, or the soil and water conservation district who requests entry

for the purposes of inspection, and who presents appropriate credentials, nor may any person obstruct, hamper or interfere with any such representative while in the process of carrying out his official duties.

(5) The soil and water conservation district or the soil and water conservation commission or both may periodically review the actions of the city. The soil and water

conservation district or the soil and water conservation commission or both may provide technical assistance to the city

for the purpose of improving the effectiveness of the city's erosion, sedimentation and pollution control program. The soil and water conservation district or

the soil and water conservation commission must notify the EPD and request investigation by the EPD if the city's

program is found to be deficient or ineffective.

(6) The Georgia Board of Natural Resources may promulgate rules and regulations setting forth the requirements and standards for certification and the procedures for decertification of a Local issuing authority. The EPD may periodically review the actions of the city which has

been certified as a Local issuing authority pursuant to O.C.G.A. § 12-7-8(a).

Such review may include review of the administration and enforcement of the city's ordinances. If such review indicates that the city has not administered or enforced its ordinances or has not

conducted the program in accordance with any agreement entered into pursuant to O.C.G.A. § 12-7-7(e), the EPD must notify the city governing authority

in writing. Upon receipt of the notification, the governing authority has 90 days to take the necessary corrective action

to retain certification as a Local issuing authority. If the city does not take necessary action within 90 days after notification by the EPD, the EPD may revoke the certification of the city as a Local

issuing authority.

(b) Penalties.

(1) Failure to obtain a permit for land-disturbing activity. If any person commences any land-disturbing activity requiring a

land-disturbing permit as prescribed in this chapter without first obtaining the permit, the person is subject to revocation of their business license, work permit or other authorization for the conduct of a business and associated work activities within the city.

(2) Stop-work orders. Upon notice from the community development director or other city authorized representative, work on any project that is being done contrary to the provisions of this chapter or in a dangerous or unsafe manner, must be immediately stopped. Such notice must be in writing and must be given to the owner of the property, his authorized agent or the person in charge of the activity on the property, and must state the conditions under which work may be resumed. Where an emergency exists, no written notice is required.

a. For the first and second violations of the provisions of this division on a site, the community development director must issue a written notice of violation. The violator has five days to correct the violation. If the violation is not corrected within five days, the EPD or the Local issuing authority must issue a stop-work order requiring that land-disturbing activities be stopped until necessary corrective action or mitigation has occurred; provided that if the

violation presents an imminent threat to public health or waters of the state or if land-disturbing activities are conducted without obtaining the necessary permit, the EPD or the Local issuing authority must

issue an immediate stop-work order in lieu of a warning.

b. For a third and each subsequent violation on a site, the EPD or the Local issuing authority must issue an immediate stop-work order. All stop-work orders are effective immediately upon issuance and remain in effect until the necessary corrective action or mitigation has

occurred.

c. When a violation in the form of landdisturbance without a permit, failure to maintain a stream buffer, or significant amounts of sediment, as

determined by the Local issuing authority or by the EPD director or his designee, have been or are being

discharged into state waters and where best management practices have not been properly designed, installed, and maintained, a stopwork order must be issued by the Local issuing authority or by the

EPD director or his designee. All such stop-work orders are effective immediately upon issuance and remain in effect until the necessary corrective action or mitigation has

occurred. Stop-work orders apply to all land-disturbing activity on the site with the exception of the installation and maintenance of temporary or permanent erosion and sediment controls.

(3) Bond forfeiture. If, through inspection, it is determined that a person engaged in land-disturbing activities has failed to comply with the approved plan, a written notice to comply must be served by the community development director upon that person. The notice must set forth the measures necessary to achieve compliance with the plan and must state the time within which such measures must

be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, they will be deemed in violation of this chapter and,

in addition to other penalties, will be deemed to have forfeited his performance bond, if required to post one under the provisions of section 16-60. The community development director may call

the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the

land-disturbing activity and bring it into compliance.

(4) Monetary penalties. Any person who violates any provisions of this division, or any permit condition or limitation established pursuant to this division, or who negligently or intentionally fails or refuses to comply with any final or emergency order of the community development director issued as provided in this division, is liable for a civil penalty not to

exceed $2,500.00 per day. Notwithstanding any limitation of law as to penalties which can be assessed for violations of

city ordinances, the municipal court or any other court of competent jurisdiction trying cases brought under city ordinances approved under this division is authorized to impose penalties for such

violations, not to exceed $2,500.00 for each violation. Each day during which violation or failure or refusal to comply continues constitutes a separate violation.

(Ord. No. 2013-10-14, 1(Exh. A § 16-5.70), 10- 14-2013; Ord. No. 2015-01-04, § 1, 1-26-2015;

Ord. No. 2017-03-06, §§ 1, 2, 3-27-2017)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:dunwoody/zoning/16-62@2020-02-10-1b6a8b825e