Sec. 16-97. Design.

About this text

  • As published by Municode, current through 2020-02-10
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Detention designs. Detention designs may be rejected if they incorporate structures and facilities that will demand considerable maintenance or will be difficult to maintain or will utilize numerous small structures if other alternatives

are physically possible.

(b) Discharge velocities. Discharge velocities from detention facilities must be reduced to provide a nonerosive velocity flow from a structure, channel, or other control measure as set forth in the approved Georgia Stormwater Management Manual.

(c) Design storm. The drainage system being developed must have adequate capacity to accommodate the flow from all upstream areas

for a 100-year storm event.

(d) Drainage outfalls. The drainage system from a proposed development must discharge into an outfall that has adequate capacity to accommodate the runoff from the development.

If the connecting downstream system is not able to accommodate the allowable design flow from the site, then the design engineer must design on-site drainage facilities that result in no exacerbation of existing downstream conditions.

(e) Detention storage.

(1) The live detention storage to be provided must be calculated on the basis of the 100-year frequency rainfall as published in the Georgia Stormwater Management Manual. The detention system must be adequate for the runoff of a

100-year rainfall, for any and all durations from the post-development, with a release rate that does not exceed the

pre-development release rate during the same duration storm. Detention control structures and other drainage improvements must be located and designed to prevent erosion damage to adjacent property owners.

(2) Detention and sedimentation control facilities may not be placed in any of the following:

a. Transitional buffer zones as defined by the city zoning ordinance.

b. Floodplains.

c. Wetlands.

d. Stream buffer zones.

e. State buffer zones.

(3) Perforated standpipes or a French drain, in accordance with published design standards available from the community development department, or other methods which will achieve equal performance to prevent standing water and inadequate drainage, must be installed within all the detention and sedimentation control facilities.

(f) Combined detention. When the applicant requests and the community development director determines that development and construction projects are too small, or that engineering and economic factors make combined detention or other stormwater management facilities more practical, the city may authorize the joint

construction of these facilities to serve two or more properties by two or more applicants.

(g) Fencing.

(1) Permanent fencing at least four feet in height is required around all stormwater and sedimentation control facilities designed for temporary storage of stormwater if they have a water storage

depth of greater than four feet or they are designated by the city or board of health as a public health hazard.

(2) Required fencing must be designed, installed and maintained to allow the free flow of runoff and sediment into the facility. Fencing must be established on the outside edge of a facility. The fence

must include a gate of sufficient size to permit entrance of equipment necessary to allow periodic maintenance activities. The gate must be placed in a manner such that the gate does not obstruct reasonable access or become obstructive. The community development director may waive fencing in nonresidential areas where a pond is more than 500 feet from a residential zoning district

and in residential zoning districts when detention is provided in natural areas such as stream channels and fencing in the opinion of the community development director would damage the environment or affect stream flow.

(h) Special flood hazard area elevation contours. In residential districts, not less than 70 percent of the minimum lot area, as established

by applicable zoning district development standards, must be above the special flood hazard area elevation contours with the exception that

lots in the R-150 district must conform to requirements of the R-100 district.

(i) Street centerline elevations. The profile elevation of the centerline of all public streets must be constructed a minimum of one foot above special flood hazard area elevation contours. The community development director may grant exceptions to this provision in cases where

construction of the street elevation is within a special flood hazard area and elevation contours would improve drainage or reduce the effects of flooding.

History

The history line the source prints at the end of the section.

(Ord. No. 2020-11-21, § I, 11-30-2020)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:dunwoody/zoning/16-97@2020-02-10-418fbca6e2

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Dunwoody Zoning Ordinance, Sec. 16-97. Design | Georgia Commons