(a) Inspections to ensure compliance during construction. (1) Periodic inspections of the stormwater management system during construction must be conducted by the community development department or conducted and certified by a professional engineer approved by the community development director. Construction inspections must use the approved stormwater management plan for establishing compliance. All inspections must be documented with written reports that contain the following information: a. The date and location of the inspection; b. Whether the stormwater management system is in compliance with the approved stormwater management plan; c. Variations from the approved stormwater management plan; and d. Any other variations or violations of the conditions of the approved stormwater management plan. (2) If any violations are found, the applicant must be notified in writing of the nature of the violation and the required corrective actions. (b) Final inspections. (1) As-built drawings; Delivery of inspection and maintenance agreement. Upon completion of development, the applicant is responsible for: a. Certifying that the stormwater management system is functioning properly and was constructed in conformance with the approved stormwater management plan and associated hydrologic analysis. b. Submitting "as-built" drawings showing the final design specifications for all components of the stormwater management system as by a professional engineer. c. Certifying that the landscaping is established and installed in conformance with the BMP landscaping plan, and d. Delivering to the City of Dunwoody a signed inspection and maintenance agreement that has been recorded by the owner in the property record for all parcels that make up the site. 1. Specific certification requirements. In order to ensure each component is functioning as designed and built according to the design specifications in the approved stormwater management plan, a certification of volume, or other performance test applicable to the type of stormwater management system component, msut be performed by a qualified person. 2. Final inspection. The certification and required performance tests shall be submitted to the City of Dunwoody with the request of a final inspection. The City of Dunwoody shall perform a final inspection with the applicant to confirm applicant has fulfilled all applicable responsibilities. A final inspection by the city is required before the release of any performance bonds or financial guarantees. (c) Violations and enforcement.Any violation of the approved stormwater management plan during construction, failure to submit as-built drawings, failure to submit a final BMP landscaping plan, or failure of the final inspection shall constitute and be addressed as violations of, or failures to comply with, the underlying land disturbance permit pursuant to section 16-60 or the underlying building permit pursuant to section 16-29. To address a violation of this division, the City of Dunwoody shall have all the powers and remedies that are available to it for other violations of building and land disturbance permits, including, without limitation, the right to issue notices and orders to ensure compliance, stop work orders, and penalties as set forth in the applicable ordinances for such permits. (d) Long-term maintenance and inspections. (1) Stormwater management facilities and practices included in a stormwater manLAND DEVELOPMENT REGULATIONS § 16-98 agement plan which are subject to an inspection and maintenance agreement must undergo ongoing inspections to document maintenance and repair needs and ensure compliance with the requirements of the agreement, the plan and this division. (2) A stormwater management facility or practice must be inspected on a periodic basis by the responsible person in accordance with the approved inspection and maintenance agreement. In the event that the stormwater management facility has not been maintained and/or becomes a danger to public safety or public health, the public works director must notify the person responsible for carrying out the maintenance plan by registered or certified mail to the person specified in the inspection and maintenance agreement. The notice must specify the measures needed to comply with the agreement and the plan and must specify the time within which such measures must be completed. If the responsible person fails or refuses to meet the requirements of the inspection and maintenance agreement, the city may pursue all available enforcement actions and penalties. (3) Inspection programs by the city may be established on any reasonable basis, including but not limited to: routine inspections; random inspections; inspections based upon complaints or other notice of possible violations; and joint inspections with other agencies inspecting under environmental or safety laws. Inspections may include, but are not limited to: reviewing maintenance and repair records; sampling discharges, surface water, groundwater, and material or water in stormwater management facilities; and evaluating the condition of stormwater management facilities and practices. (e) Right-of-entry—Maintenance agreements. The terms of the inspection and maintenance agreement must provide for the right of entry for authorized city or city contracted officials for the purpose of maintenance inspections and other specified purposes. If a site was developed before the requirement to have an inspection and maintenance agreement or an inspection and maintenance agreement was for any reason entered into, recorded, or has otherwise invalidated or deemed insufficient, the City of Dunwoody shall have the right to enter an make inspections pursuant to the City of Dunwoody's general provisions for right of entry in chapter 8 of the Dunwoody Code of Ordinances. (f) Maintenance responsibilities. (1) Except as otherwise provided in this section, commercial and/or multifamily residential property owner is responsible for the maintenance of the stormwater management facilities during grading, construction, and following final approval of the completed project. This maintenance and certification obligation is binding on all future owners, successors and assigns of the property. (2) Stormwater management facilities in single-family residential subdivisions constructed under permits issued prior to the adoption of the city ordinance assigning maintenance responsibility will not be accepted for city maintenance unless individually approved by and at the discretion of the public works director and suitable access easements are provided. The public works director shall make a decision within 30 days of submittal of the request. The applicant shall be empowered to appeal the decision of the public works director to the mayor and city council, which shall hear the appeal within 30 days of receipt of the appeal. (g) Owner's failure to maintain the stormwater management system. The terms of the inspection and maintenance agreement shall provide for what constitutes a failure to maintain a stormwater management system and the enforcement options available to the City of Dunwoody. If a site was developed before the requirement to have an inspection and maintenance agreement or an inspection and maintenance agreement was for any reason not entered into, recorded, or has otherwise been invalidated or deemed insufficient, then: (1) An owner's failure to maintain the stormwater management system so that it performs as it was originally designed shall be addressed as a violation of, or failure to comply with, owner's property maintenance obligations pursuant to section 8-1 (State Minimum Standard Codes) and (2) To address such failure to maintain the stormwater management system, the City of Dunwoody shall have all the powers and remedies that are available to it for other violations of an owner's property maintenance obligations, including, without limitation, prosecution, penalties, abatement, and emergency measure. If a responsible person fails or refuses to meet the requirements of the inspection and maintenance agreement, the public works director, after 30 days' written notice (except, that in the event the violation constitutes an immediate danger to public health or public safety, 24-hour notice is deemed sufficient), may correct a violation of the design standards or maintenance requirements by performing the necessary work to place the facility or practice in proper working condition. The city may assess the owners of the facility for the cost of repair work, which will be a lien on the property, and may be placed on the ad valorem tax bill for such property and collected in the ordinary manner for such taxes. (h) Special drainage system maintenance requirements. (1) Pursuant to all applicable city and county law, trash, garbage, construction materials, construction by-products or other debris may not be deposited in any part of the drainage system. (2) No restriction or barriers, including fences, may be placed in the drainage system or special flood hazard areas without first obtaining a development permit. When on-site or off-site debris has accumulated within a special flood hazard area in such a manner as to interfere with the free flow of water so as to increase the risk of hazardous inundation of upstream properties adjacent to special flood hazard areas, the community development director must require the owner of the property where this debris was generated, if its source can be identified, to clear and remove the debris so as to permit the free flow of water. (3) No impoundment of water which retains in excess of 0.5 acre-foot of runoff may be removed without first obtaining a development permit, which may only be issued after competent engineering studies provided by the applicant show that this removal will not adversely affect downstream properties.