Sec. 27-27. Applications, permits and approvals.

About this text

  • As published by Municode, current through 2020-02-10
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Any building, development or structure for which a building permit was issued or a complete permit application had been accepted for processing before October 21, 2013, may be completed in conformance with the issued building permit and other applicable permits and conditions, even if such building, development

or structure does not fully comply with provisions of this zoning ordinance. If building is not commenced and completed within the time allowed under the original building permit, then the building, development or structure may be

constructed, completed and occupied only if it complies with the standards of this zoning ordinance.

(b) Variances, special exceptions and special permits lawfully authorized and granted prior to effective date specified in section 27-4 remain

valid after the effective date specified in section 27-4, provided the terms of the authorization are met.

(c) Applications for variances, special exceptions and special land use permits that were submitted in complete form and are pending

approval on the effective date specified in section 27-4 must be reviewed wholly under the terms of the zoning ordinance in effect immediately before the effective date specified in section 27-4. Building permits for construction and development approved under such zoning approvals may be issued in accordance with subsection (d).

(d) Building permits may be issued for construction or development approved under subsections (b) and (c) even if such building, development or structure does not fully comply with provisions of this zoning ordinance. If building is

not commenced and completed within the time allowed under the building permit, then the building, development or structure may be constructed, completed and occupied only if it complies with the standards of this zoning ordinance.

(e) When a use classified as a special use under this zoning ordinance exists as a special use, permitted use, nonconforming use or a lawful use by court decree on the effective date specified in section 27-4, such use will be considered a lawfully established special use under this zoning ordinance. When any amendment to

this zoning ordinance changes the classification of a permitted use to a special use, any use lawfully established before such amendment will be considered a lawfully established special use after the effective date of such amendment.

A lawfully established existing use that is not allowed as a special use or permitted use in the district in which the use is now located will be considered a nonconforming use and will be subject to all applicable regulations of article VI, division 4.

History

The history line the source prints at the end of the section.

(Ord. No. 2013-10-15, § 1(Exh. A § 27-2.20), 10-14-2013)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:dunwoody/zoning/27-27@2020-02-10-b09c3728d6

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Dunwoody Zoning Ordinance, Sec. 27-27. Applications, permits and approvals | Georgia Commons