Sec. 75-599. Surety for completion of improvements.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

In lieu of the completion of the required improvements in a subdivision, the subdivider may deposit surety for the completion of such improvement with the city, and present a final plat for approval. In no case shall any building be occupied or otherwise utilized until all required improvements are completed.

(1) Requirements. To ensure the construction and installation of required improvements, the subdivider shall deliver to the city a certified check, surety bond or other acceptable security in such aggregate amount as is estimated by the building inspector to be the total cost of the construction and installation of all required improvements.

In addition, the subdivider shall, if applicable, deposit surety for road maintenance for a period of one year.

(2) Conditions. Bonds or other surety posted shall run to the city and provide the subdivider, his heirs, successors, assigns and their agents shall comply with all applicable terms, conditions, provisions and requirements of these and other regulations and final plat; will faithfully perform and complete the work of constructing and installing all required improvements; that the subdivider shall be responsible to the city for any necessary expenses incurred through the failure of the subdivider, his heirs, successors, assigns or their agents to complete the work of such installation and construction in an acceptable manner, and from any damages growing out of negligence in performing or failing to perform such installation and construction. Before acceptance, any surety shall be approved by the city. If a bond is offered it shall be executed by a surety of a guaranty company qualified to transact business in the state.

Where a bond is required for a road construction project and is to be other than a bond issued by a commercial fidelity bonding company, the surety must meet the following conditions:

a. The surety must be an individual or group of individuals,

b. The sureties must all be residents of the city/county,

c. Collectively, the sureties must be worth at least double the estimated cost of paving the road in equity in real property located in the city,

d. The bond must be accompanied by an affidavit setting forth the facts in subsections (1), (2) and (3) of this section,

e. The bond must be double the amount of the estimated cost of the road project; and

f. If there is more that one surety, all sureties shall be jointly and severably liable.

(3) Duration and release. Bonds and/or other surety posted pursuant to this article shall be released or returned, as the case may be, at such time as the facilities guaranteed thereby have been installed and accepted. Acceptances shall be in writing accurately identifying the improvements covered. Facilities shall not be accepted unless they conform to the applicable specifications and requirements.

(4) Default procedures. If the construction or installation of any improvements of facilities for which a bond or other surety is posted is not completed within three months after substantial completion of any buildings or structures which such improvements or facilities are designed to serve, or within three years after the date of recording of the final plat, whichever is sooner, or if such construction and installation is not in accordance with the applicable specifications and requirements, the city shall, using the proceeds from such surety deposits, pay for such work. Such work may be done under contract or by city personnel. To the extent that any portion of a cash deposit is not required or used, such excess cash shall be repaid to the person making the deposit.

History

The history line the source prints at the end of the section.

(Ord. of 3-20-2006)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:eatonton/zoning/75-599@2026-11-11-bb12c6de5a

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Eatonton Zoning Ordinance, Sec. 75-599. Surety for completion of improvements | Georgia Commons