Effingham County · Zoning Ordinance
Appendix D - DEVELOPMENT IMPACT FEE ORDINANCE
8.1. Failure to encumber trust funds or commence construction.
About this text
- As published by Municode, current through 2026-08-04
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
.1 Any development impact fees paid shall be refunded to the feepayor if (a) capacity is available and service is denied, or (b) the county has failed to commence construction of system improvements in accordance with this ordinance, or to encumber funds for such construction, within six years after the date on which such fee was paid.
.2 The refund shall include a pro-rata share of interest actually earned on the unused or excess development impact fees collected.
.3 When the right to a refund exists due to a failure of the county to encumber development impact fees, the county shall provide written notice of entitlement to a refund to the feepayor who paid the development impact fees at the address shown on the application for development approval, or to a successor in interest who has notified the county of a transfer or assignment of the right or entitlement to a refund and who has provided to the county a mailing address.
.4 When the right to a refund exists due to a failure or the county to encumber development impact fees, the county shall also publish the notice of entitlement to a refund within 30 days after the expiration of the six-year period after the date that the development impact fees were collected. Such published notice shall contain the heading "Notice of Entitlement to Development Impact Fee Refund".
.5 In order to be eligible for a refund, a feepayor or successor in interest shall file a written application for a refund with the board of commissioners or a designee within one year of the time such refund becomes payable under subsections 1(a) and (b) above, or within one year of publication of the notice of entitlement to a refund, whichever is later. If a successor in interest claims a refund of development impact fees, the board of commissioners or a designee may require written documentation that such rights have been conveyed to the claimant prior to issuing the requested refund.
.6 Refunds shall be paid within 60 days after the date on which the board of commissioners or a designee determines that a sufficient proof of claim for a refund has been made.
.7 A feepayor shall have standing to sue for a refund under the provisions of this chapter if there has been a timely application for a refund and the refund has been denied or has not been made within one year of submission of the application for refund to the county.
8.2 Failure to initiate development. If a feepayor has paid a development impact fee required by this ordinance and has obtained a building permit, and the building permit for which the fee was paid later expires or is abandoned without the possibility of further extension, then the feepayor or the feepayor's successor in interest shall not be entitled to a refund of development impact fees paid, but shall instead be entitled to credit for the present value of the development impact fee against future development impact fees for the same parcel of land. In order to be eligible to receive this credit for future development impact fees, the feepayor or a successor in interest shall be required to submit an application for such refund to the board of commissioners or a designee within 30 days after the expiration of the building permit for which the fee was paid. If a successor in interest claims a refund of development impact fees, the board of commissioners or a designee may require written documentation that such rights have been conveyed to the claimant prior to issuing the requested refund.
8.3 Limitations. After a development impact fee has been paid pursuant to this ordinance [Appendix D], no refund of any part of such fee shall be made if the project for which the fee was paid is later demolished, destroyed, or is altered, reconstructed, or reconfigured so as to reduce the size of the project or the number of units in the project.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.