(1) Site plans. Applications for a local DEVELOPMENT PERMIT within the Generalized Wetland Protection District shall include a site plan, drawn at a scale of one-inch equals 50 feet, with the following information: 1. A map of all planned excavation and fill, including calculations of the volume of cut and fill involved, cross-sectional drawings showing existing and proposed grades. Elevations, horizontal scale and vertical scale must be shown on the cross-sectional drawings. 2. A map of any WETLAND boundaries occurring within the site must be provided. This boundary may be included on other maps provided by the APPLICANT. 3. Location, dimensions and area of all IMPERVIOUS SURFACES, both existing and proposed, on the site and adjacent to the site for a distance of 200 feet. 4. The orientation and distance from the boundaries of the proposed site to the nearest bank of an affected perennial stream or water body. 5. Elevations of the site and adjacent lands within 200 feet of the site at contour intervals of no greater than two feet; and no greater than one foot for slopes less than or equal to two percent. 6. Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally released hazardous or toxic materials. 7. All proposed temporary disruptions or diversions of local hydrology. (2) Activities to comply with the site plan. 1. All development activities or site work conducted after approval of the site plan shall conform with the specifications of said site plan. The site plan may be amended only with the approval of the board of commissioners. The board of commissioners may require additional information deemed necessary to verify compliance with the provisions of this article or to evaluate the proposed use in terms of the purposes of this article. 2. The COUNTY may require a bond up to the larger of $5,000.00 or $1,000.00 per acre of project area and with surety and conditions sufficient to secure compliance with the conditions and limitations set forth in the permit. The particular amount and conditions of the bond shall be consistent with the purposes of this article. In the event of a breach of condition of any such bond, the COUNTY or its designee may collect such bond or institute an action in a court of competent jurisdiction upon such bond and prosecute the same to judgment and execution. 3. Review procedures. The application shall be made to the BUILDING INSPECTOR or appointed designee and will be reviewed within 30 days. At the time of the application, the APPLICANT shall pay a filing fee as specified by the board of commissioners. Filing fees up to the larger of $500.00 or $100.00 per acre may be required to evaluate the application. The fee may be used to retain expert consultants who will provide services pertaining to functional assessment, mitigation, and WETLAND boundary determinations, as deemed necessary by the BUILDING INSPECTOR or appointed designee. The review period shall include the preparation of findings (approval, approval with conditions or disapproval) by the BUILDING INSPECTOR or appointed designee. The APPLICANT will receive written notification of the findings of the BUILDING INSPECTOR or appointed designee. If the review process is not completed within 30 days, the application is considered to be approved. Decisions of the BUILDING INSPECTOR or appointed designee may be appealed to the board of commissioners.