(1) Permit requirements. Within the WATER SUPPLY WATERSHED DISTRICT, no LAND DISTURBING ACTIVITY, construction or other DEVELOPMENT, other than certain exempted activities identified within, may be conducted without a permit from the board of commissioners and must be in full compliance with the terms of this article and other applicable regulations. All activities that are not permissible as of right or as special permit uses shall be prohibited.
(2) TEMPORARY EMERGENCY PERMIT. Notwithstanding the provisions of this DISTRICT or any other law to the contrary, the board of commissioners may issue a TEMPORARY EMERGENCY PERMIT through oral or written authorization, provided a written permit is accomplished within five days, if it deems that an unacceptable threat to life or severe loss of property will occur if a TEMPORARY EMERGENCY PERMIT is not granted. The TEMPORARY EMERGENCY PERMIT may be terminated at any time without process upon a determination by the board of commissioners that the action was not or is no longer necessary to protect human health or the environment.
(3) Exemptions. The following land use activities are exempted from the permit and site plan requirements of this article:
1. Agriculture and forestry. Normal agricultural activities involving planting and harvesting of crops are exempted if they conform to best management practices established by the state department of agriculture. Silvicultural activities must conform to best management practices established by the state forestry commission.
(4) Enforcement. The board of commissioners, its agents, officers and employees shall have authority to enter upon privately owned land for the purpose of performing their duties under this article and may take or cause to be made such examinations, surveys or sampling as the board of commissioners deems necessary.
1. The CODE ENFORCEMENT OFFICER is hereby designated as the administrator and enforcement authority for this article.
2. The board of commissioners shall have authority to enforce this article; issue permits hereunder; and address violations or threatened violations hereof by issuance of violation notices, administrative orders and civil and criminal actions. All costs, fees and expenses in connection with such actions may be recovered as damages against the violator.
3. Law enforcement officials or other officials having police powers shall have authority to assist the board of commissioners in enforcement of this article.
4. Any PERSON who commits, takes part in or assists in any violation of any provision of this article shall be fined not more than $1,000.00 or three months for each offense. Each violation shall be a separate offense, and, in the case of a continuing violation, each day's continuance shall be deemed to be a separate and distinct offense.
5. The board of commissioners shall have the authority to issue cease and desist orders in the event of any violation of this article. Cease and desist orders may be appealed to a court of competent jurisdiction, as identified in subsection (15) of this section.
6. When a BUILDING or other STRUCTURE has been constructed in violation of this article, the violator shall be required to remove the STRUCTURE.
7. When removal of vegetative cover, excavation or fill has taken place in violation of this article, the violator shall be required to restore the affected land to its original contours and to restore vegetation, as far as practicable.
(5) Permit review.
1. Site plans required. Except for the exemptions listed in this section, all forms of development within the WATERSHED DISTRICT shall be required to have a site plan prepared and approved according to this article before any BUILDING permits or other development related permits may be issued or any land disturbing activity may take place.
2. Information required. Each site plan submitted under this article shall include the following:
a. A site plan drawn to a scale of one inch equals 50 feet showing all planned improvements including the width, depth and length of all existing and proposed STRUCTURES, roads, watercourses and drainageways; water, wastewater and stormwater facilities; and UTILITY installations.
b. Location, dimensions and area of all IMPERVIOUS SURFACES, both existing and proposed, on the site.
c. The orientation and distance from the boundaries of the proposed site to the nearest bank of an affected perennial stream or water body.
d. Elevations of the site and adjacent lands within 200 feet of the site at contour intervals of no greater than five feet.
e. Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally released hazardous or toxic materials.
f. Calculations of the amount of cut and fill proposed and cross-sectional drawings showing existing and proposed grades in areas of fill or excavation. Elevations, horizontal scale and vertical scale must be shown on cross-sectional drawings.
NOTE: A stormwater prevention plan submitted to the state department of natural resources, environmental protection division may meet the requirements of this section.
(6) Activities to comply with site plan. All development activities or site work conducted after approval of the site plan shall conform with the specifications of said site plan.
Significant changes to the site plan that would alter the amount and velocity of stormwater runoff from the site, increase the amount of IMPERVIOUS SURFACE within the DEVELOPMENT, alter the overall DENSITY of DEVELOPMENT, result in a considerable increase in the amount of excavation, fill or removal of vegetation during construction or otherwise result in an ALTERATION of the overall appearance of the DEVELOPMENT as proposed, can be amended only with the approval of the board of commissioners. Minor changes, such as realignment of STREETS or minor ALTERATIONS to drainage STRUCTURES and other infrastructure to meet unexpected conditions, are exempted from this requirement.
(7) Exemptions from site plan requirement.
1. The following activities and developments are exempt from the requirement for detailed site plans:
a. Single-family detached homes constructed within a SUBDIVISION of fewer than five parcels.
b. Repairs to a facility that is part of a previously approved and permitted development.
c. Construction of ACCESSORY BUILDINGS or additions to single-family residences.
(8) Pre-application conference.
1. A pre-application conference is strongly encouraged between the APPLICANT and the board of commissioners and can be scheduled at the request of the APPLICANT. The purpose of the meeting is to review local land use restrictions, site plan requirements and the permitting process.
(9) Filing fee.
1. At the time of the application, the APPLICANT shall pay a filing fee specified by the board of commissioners. This fee may be used to retain expert consultants who will provide services pertaining to functional assessment and mitigation measures as deemed necessary by the board of commissioners.
(10) Review procedures.
1. The application shall be made to the CODE ENFORCEMENT OFFICER and will be reviewed and notice given to the board of commissioners within 30 days.
The review period shall include the preparation of findings (approval or disapproval) by the CODE ENFORCEMENT OFFICER. The APPLICANT will receive written notification of the findings of the CODE ENFORCEMENT OFFICER. If the review process is not completed within 45 days, the application is considered to be approved.
2. Board of commissioners action. The board of commissioners shall review the record prepared by the PLANNING COMMISSION and vote on the permit application. The board of commissioners may approve, approve with conditions, or deny the application. Within seven days of its decision, the board of commissioners shall notify the APPLICANT. If the board of commissioners fails to act on the application within 30 days of its submission to the board of commissioners, the application is deemed to have been approved.
(11) Denial. If the permit is denied by the board of commissioners, then the same permit application cannot be considered until the expiration of at least six months immediately following the denial of the permit.
(12) Appeals. Decisions on permit applications made by the board of commissioners may be appealed to the board of commissioners. The appeal must be made within 30 days of the decision rendered by the board of commissioners.
(13) Duration of permit validity.
1. If construction described in the DEVELOPMENT PERMIT has not commenced within 12 months from the date of issuance, the permit shall expire.
2. If construction described in the DEVELOPMENT PERMIT is suspended after work has commenced, the permit shall expire 12 months after the date that work ceased. In cases of permit expiration due to abandonment or suspension of work, the landowner shall be required to restore topography to its original contours and restore vegetation as far as practicable.
3. Written notice of pending expiration of the DEVELOPMENT PERMIT shall be issued by the board of commissioners no later than 30 days prior to expiration.
4. Board of commissioners action. The board of commissioners shall review the record prepared by the PLANNING COMMISSION and vote on the permit application. The board of commissioners may approve, approve with conditions, or deny the application. Within seven days of its decision, the board of commissioners shall notify the APPLICANT. If the board of commissioners fails to act on the application within 30 days of its submission to the board of commissioners, the application is deemed to have been approved.
(14) Denial.
1. If the permit is denied by the board of commissioners, then the same permit application cannot be considered until the expiration of at least six months immediately following the denial of the permit by the board of commissioners.
(15) Appeals.
1. Decisions on permit applications made by the board of commissioners may be appealed to the board of commissioners. The appeal must be made within 30 days of the decision rendered by the board of commissioners.
(16) Duration of permit validity.
1. If construction described in the DEVELOPMENT PERMIT has not commenced within 12 months from the date of issuance, the permit shall expire.
2. If construction described in the DEVELOPMENT PERMIT is suspended after work has commenced, the permit shall expire 12 months after the date that work ceased. In cases of permit expiration due to abandonment or suspension of work, the landowner shall be required to restore topography to its original contours and restore vegetation as far as practicable.
3. Written notice of pending expiration of the DEVELOPMENT PERMIT shall be issued by the board of commissioners later than 30 days prior to expiration.