8.275.1 Industrialized buildings. Industrialized buildings shall comply with the requirements of O.C.G.A. § 8-2-110 et seq. and the rules and regulations promulgated thereunder.
8.275.2 Non-discrimination. Pursuant to O.C.G.A. § 8-2-112, the city shall not exclude residential industrialized buildings from being sited in a residential district solely because the building is a residential industrialized building.
8.275.3 Permitting, inspection, certificate of occupancy and fees. A city installation permit shall be required to locate an industrialized building in the jurisdiction.
(A) Permit. To obtain a permit, applicants shall provide to the building inspector:
1. An application form signed by the applicant containing such information as is required by the city.
2. The permit and inspection fee required by 8.275.3(D).
(B) Inspection. Upon receipt of a permit, applicants may relocate the industrialized building to a site for purposes of inspection. The applicant shall arrange for an inspection to be held once the installation of the building is complete.
(C) Fees. A permit and inspection fee of shall be charged to the applicant to cover the cost to the city to process the permit application and inspect the building once installed. Such fee shall cover the initial inspection and one follow-up inspection. The applicant shall be charged a fee for each additional follow up inspection that may be necessary. Fees shall be set by the city in a separate fee ordinance or resolution.
(D) Certificate of occupancy. A certificate of occupancy shall be issued to the applicant at such time that the building inspector certifies that the requirements of this division have been met. In the event the building, once installed, cannot meet the requirements of this division, it either must be repaired up to the standards herein or removed.
8.275.4 Additional requirements. The following requirements must be satisfied for an industrialized building to secure a certificate of occupancy:
(A) Installation requirements. Industrialized homes must be installed in accordance with O.C.G.A.
§ 8-2-110 et seq. and regulations promulgated thereunder.
(B) Utility connections. Utility connections prior to the final inspection of the installation will be considered temporary and will be approved only when arrangements for complete installations have been made.
(C) Entry landing. All industrialized home installations shall provide an adequate means of entry (including steps and a landing at each doorway), of a minimum size of four feet by eight feet.
(D) Sewage management. A septic permit or a sewer tap must be secured and provided to building inspections approval of an on-site sewage management system by the health department, or a sewer tap must be secured and provided to the city before an installation permit for an industrialized home will be permitted.
(E) Foundations. The dwelling must be placed on a foundation and a curtain wall, unpierced except for required ventilation and access, must be installed so that it encloses the area located under the home to ground level. Such a wall shall have a minimum thickness of four inches and shall be constructed of masonry or similar material as approved by the building inspector.