Sec. 80-241. Data centers.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) [Definition.] [A] data center shall be defined as any building, structure, complex or group of buildings and/or structures, facility, or dedicated space within a building, structure, complex, or facility that houses information technology related infrastructure, including, but not limited to, computer systems, networks, servers, applications, appliances, services, and other associated components or facilities used for the remote storage, processing, or transmission of digital data associated with those computer systems, networks, servers, applications, appliances, services, and other associated components or facilities. Associated components and facilities may also include air handlers, water cooling towers, generators, fuel storage cells, storage facilities, utility substations, and any other associated utility infrastructure to support operations.

(b) [Allowable districts.] Data centers may only be considered in the light and heavy industrial zoning districts with a use permit.

The application for the installation or construction a data center, or for modifications to a lawfully existing data center beyond routine maintenance, shall follow the application procedures for use permits and any other procedures as may be required by this section for data centers, such as zoning map amendments, platting, or variances. In addition, the applicant shall provide the following:

(1) Applicant name(s) and contact information. The applicant must also identify on the application, if different than the

applicant, the owner of record of the property.

(2) A narrative describing the proposed project, including a description of how the project meets market demand, the estimated facility's processing capacity, and the facility's anticipated water and electricity needs.

(3) A study prepared by an acoustical engineer that describes the anticipated noise level of the facility and any proposed mitigation efforts such as sound walls,

baffles, ventilation silencers, etc.

(4) A site plan, drawn to scale, showing the location and dimensions of all existing

and proposed structures, screening, fencing, lighting, electrical connections, property lines, and roadway access.

(5) Four-sided elevations showing the building height, color and materials shall be provided.

(6) Boundary survey (sealed by a registered land surveyor).

(7) Letter of capability or commitment to serve water, sewer, and power.

(8) A map of the project area showing all single-family and multi-family dwellings, schools, places of worship or assembly, parks, and any other

recreational amenities located within five miles of the exterior boundaries of the

property where the data center will be located.

(9) At least one neighborhood meeting must be held to discuss proposed sound mitigation aspects of the project design prior to the first planning and zoning commission meeting. The neighborhood meeting must comply with standards and

procedures outlined in section 80-474 and section 80-475.

(10) Before the first neighborhood meeting, a third-party acoustic engineer must

conduct a sound study to measure noise level at any property line shared with residentially zoned or planned land, or shared with other "noise sensitive use," as determined by the city staff.

(c) Development standards. A data center use shall be subject to the following:

(1) Building height. All buildings, structures, and appurtenances on the property where

the data center will be located shall be limited to 60 feet, unless approved by the fire marshal. The allowable height shall be measured as the vertical distance

from the finished grade to the highest point of the structure.

(2) Lights. Exterior lighting shall be designed and constructed with fully shielded

fixtures that direct light downward and into the interior of the property and away from adjacent roads and adjacent properties.

(3) Parking. Data centers must provide one space per 7,500 square feet of gross floor area.

(4) Building facades. Principal building facades that face adjacent public roads

shall meet the following standards:

a. If located outside of the Highway 74 overlay district, 75 percent of each elevation facing a public roadway shall be brick, stone or accent material.

b. Principal facade requirements apply to all the front elevations of all building facades:

1. Vary and articulate facades to avoid large monotonous walls.

Walls that exceed a length of 250 feet shall be articulated through changes in the plane of the facade, installation of windows, recessed panels, trellis features, landscaping, wall articulation, arcades, or other

features.

2. City officials may consider the use of other textures, color, murals, building material changes, or other treatments.

3. When a building has more than one principal facade, such principal building facades shall be consistent in terms of design, materials, details, and treatment.

c. All equipment necessary for cooling, ventilating, or otherwise operating the facility must be contained within an enclosed building or be encompassed on three sides by an opaque barrier wall constructed of durable, non-weathering materials.

This includes emergency power generators and other emergency power supply equipment. Barrier walls shall originate no higher than 18 inches above finished grade and shall extend at least 12 inches in height above the tallest mechanical equipment intended to be screened where the use is located. The barrier wall must be continuous and solid with no gaps, holes, or openings outside of the access gate or area. The access gate or area must

not be visible from any public street or any common or open area. If [a] barrier wall is constructed of masonry materials, it must be painted a similar color to the principal structure.

d. Any other equipment located in a manner found to have no adverse impact on adjacent roads and adjacent property, as determined by the city staff, shall not be required to be screened.

(5) [A] 40-foot heavy planted landscape buffer shall be required along public roadways.

Use of natural topography and preservation of existing vegetation, supplemented by new vegetation, if needed, may be

substituted for the above requirements when found by [the] director to provide screening at the appropriate density, depth and height. The landscape shall be

maintained for the life of the project.

(6) Separation from sensitive properties.

a. No data center building or appurtenance shall be located within 100 feet of a collector or local roadway. The mayor and city council may consider sites which intersect with an arterial or higher classification roadway.

b. Site line studies shall be provided to confirm screening of equipment from

adjacent roads and properties.

c. Noise testing shall be required prior to issuance of a certificate of

occupancy to ensure compliance with the noise ordinance. The data center must be designed and built with noise mitigation such that noise levels at the property line during operation do not exceed those of the baseline study completed prior to construction of the first building.

The data center operator must submit an annual third-party noise study to the city every year for the first seven years of operation. This study must demonstrate no increase in property line noise levels out of compliance with the city ordinance.

d. Use and testing of backup generators (outside emergency use during outages) is limited to 9:00 a.m. to

5:00 p.m., and prior notification must be provided to the city and posted on a public website announcing the time the generators will be in operation. Notice is required at least 48 hours prior to use or testing.

History

The history line the source prints at the end of the section.

(Ord. No. 2024-08, § 1(Exh. A), 3-25-2024)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fairburn/zoning/80-241@2026-11-11-6cb4b8e01d

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Fairburn Zoning Ordinance, Sec. 80-241. Data centers | Georgia Commons