(a) Permits shall be issued or denied as soon as practicable but no later than 15 days after receipt by the environmental management department of a completed application, provided all state and federal permits/variances and local bonding are obtained, as applicable. (b) Any variances required herein must be obtained; bonding requirements, if necessary, must be met; all the county ordinances, rules and regulations in effect must be complied with; and the plan must be approved prior to issuance of a permit by the environmental management department. (c) If the permit is denied, the reason for denial shall be furnished to the applicant. (d) Any land disturbing activities by a local issuing authority shall be subject to the same requirements of this article. (e) If the tract is to be developed in phases, then a separate permit shall be required for each phase. If a decision is made to plat the subdivision in phases after the permit has been issued, and the rights-of-way have been cleared, the cleared areas outside of the phase to be constructed must be mulched and grassed. A new permit must be issued before work can begin in any subsequent phase, though the work may be continued under the initial NOI if a NOT has not be filed with the state. (f) The permit may be suspended, revoked, or modified by the environmental management department, as to all or any portion of the land affected by the plan, upon finding that the holder or successor in the title is not in compliance with the approved plan or that the holder or successor in title is in violation of this article. A holder of a permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the permit. (g) A permit shall not be issued for any lot in a subdivision with a minimum lot size less than two acres unless it is issued in conjunction with a building permit. (h) If the work has not begun within 90 calendar days of the issuance of a permit, then the permit shall expire. The permit will expire if the project is not completed and approved within 24 months of the issuance of the permit. If project is a phased project, as indicated on the approved site plan or preliminary plat, then each phase of the project has a 24-month time limit. When a permit expires, the developer will have to apply for a new permit, however, once a new permit is issued, work may continue under the initial NOI, if a NOT has not be filed with the state. (i) The permit must be posted at the site entrance in a place where it can easily be seen.