The following performance criteria shall be applicable to all stormwater management plans, unless otherwise provided for in this article: (1) Design of stormwater management system. The design of the stormwater management system shall be in accordance with the applicable sections of the GSMM as directed by the administrator. Any design which proposes a dam shall comply with the Georgia Safe Dams Act and Rules for Dam Safety as applicable and article X of this chapter. (2) Natural resources inventory. Site reconnaissance and surveying techniques shall be used to complete a thorough assessment of existing natural resources, both terrestrial and aquatic, found on the site. Resources to be identified, mapped, and shown on the stormwater management plan, shall include, at a minimum (as applicable): a. Topography (minimum of two-foot contours) and Steep Slopes (i.e., areas with slopes greater than 15 percent), b. Natural drainage divides and patterns, c. Natural drainage features (e.g., swales, basins, depressional areas), d. Natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers, drinking water wellhead protection areas and river corridors, and e. Predominant soils (including erodible soils and karst areas). (3) Stormwater runoff quality/reduction. Stormwater runoff quality/reduction shall be provided by using the following: a. For development with a stormwater management plan submitted before [insert applicable date], the applicant may choose either (A) runoff reduction or (B) water quality. b. For development with a stormwater management plan submitted on or after [insert applicable date], the applicant shall choose (A) runoff reduction and additional water quality shall not be required. To the extent (A) runoff reduction has been determined to be infeasible for all or a portion of the site using the practicability policy , then (B) water quality shall apply for the remaining runoff from a 1.2-inch rainfall event and must be treated to remove at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM. 1. Runoff reduction. The stormwater management system shall be designed to retain the first 1.0 inch of rainfall on the site using runoff reduction methods, to the maximum extent practicable. 2. Water quality. The stormwater management system shall be designed to remove at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM for runoff from a 1.2-inch rainfall event. 3. If a site is determined to be a hotspot as detailed in section 104-559, Fayette County may require the use of specific or additional components for the stormwater management system to address pollutants of concern generated by that site. (4) Drainage system guidelines stormwater management system criteria. May include, catchbasins, drop inlets, junction boxes, headwalls, gutter, swales, channels, ditches, and energy dissipaters shall be provided, when necessary, for the protection of public right-of-way and private properties adjoining project sites and/or right-of-ways. Stormwater management systems that are designed to carry runoff from more than one parcel, existing or proposed, shall meet the following requirements: a. Methods to calculate stormwater flows shall be in accordance with the stormwater design manual; b. Design and construction of stormwater management systems shall be in accordance with the criteria and specifications found in the stormwater design manual; c. If a project is developed in phases, the stormwater management system in an initial phase must be sized and constructed to handle the quantity and effects of stormwater that may flow into that system subsequent phases. (5) New street construction design criteria. All new streets constructed within the county except those constructed to serve subdivisions in which all lots are five acres or larger, shall have curbs and gutters. Rolled-back curbs are not acceptable, only straight-back curbs are allowed. A curb shall be six inches high and a gutter shall be 24 inches from face of the gutter to back of the curb. a. Curb inlets shall conform to the Georgia Department of Transportation (GDOT) specifications. Spacing of inlets shall not exceed 500 feet on a continuous grade and shall be sized to intercept a minimum of 85 percent of the flow in the gutter section. Inlets shall be located to prevent stormwater from crossing an intersection, but may not be located in a radius for the intersections. Inlets located in a sag shall be sized to prevent gutter spread from covering more than half of the road's travel surface during the 25-year storm event. If grates are proposed for inlet devices, the bars must be perpendicular to the road and shall pose no hazard to bicycle traffic. In any case, throat height shall not exceed eight inches. All stormwater structures requiring inverts shall be paved. b. Only reinforced concrete shall be used for storm drain structures under the roadway including curb and gutter, and in applications to create buildable lots. The pipe must be designed and installed to meet the requirements in the latest edition of the concrete pipe design manual. A third-party pipe standardized installation inspection report is required for all pipes being placed in the ground prior to final plat. Additional information may be requested for the pipe installation report. c. Other pipe materials may be used in applications approved by GDOT. d. Cross drains, laterals and outfalls that are part of a street drainage system shall be sized for subcritical gravity flow. The design engineer must provide calculations to show that any pipes are not flowing under pressurized conditions and that the hydraulic grade lines are below finished grade at all points for the 25-year storm event. Calculations determining the headwater elevation (inlet or outlet controlled) for the 100-year storm event shall be provided by the design engineer. The backwater area inundated by the 100-year storm event shall be shown and designated on the final plat as an area of special flood hazard area. It shall be based on as-built road conditions and shall be subject to the same conditions and limitations as any other area of special flood hazard (article IV of this chapter). e. Storm drains shall not exceed 500 feet of continuous length between an inlet, manhole or junction box access. All junctions boxes shall be installed with accesses at grade. f. Easements shall extend to receiving waters and/or next stormwater system. g. For bridges crossing streams with a regulatory floodway and or floodplain, the bridge must meet criteria set forth in the county development regulations, article IV of this chapter. h. All culverts and storm drain system inlets and outfalls shall have headwalls or tailwalls. Flared and, vertical wall or vertical wall with wing-walled outfall types are acceptable. i. All outlets must be designed with energy dissipaters if outlet velocities are greater than four feet per second during the 25-year storm event. j. Drainage ditches shall have a minimum bottom width of two feet and shall have 3:1 side slopes. Ditches must be designed to handle the 100-year flow rate and lined with an appropriate erosion control matting capable of withstanding the 25-year flow velocity. k. Upon completion of the construction activities, the applicant shall submit as-built plans for all stormwater management facilities and practices associated with the project. The plan must show the final design specifications for all stormwater management facilities and practices and must be certified by a professional engineer registered in the state. The as-built plan shall also include stage/storage data for all detention or retention structures. These data shall be provided and certified by a registered land surveyor. A final inspection by the stormwater department is required before the release of any performance securities can occur. l. Lots requiring a driveway culvert, either non-curb and guttered subdivisions or lots deemed by the environmental management department, shall be designed by a professional engineer registered in the state of Georgia. (6) Stormwater structural controls. All stormwater structural controls shall be selected and designed using the appropriate criteria from the stormwater design manual. All structural stormwater controls must be and designed appropriately to meet their intended function. For other stormwater structural controls not included in the, stormwater design manual or for which pollutant removal rates have not been provided, the effectiveness and of the pollutant removal of the structural control must be documented through prior studies, literature reviews, or other means and receive approval from the environmental management department before being included in the design of a stormwater management system. In addition, if hydrologic or topographic conditions, or land-use activities warrant greater control than that provided by the minimum control requirements, the environmental management department may impose additional requirements deemed necessary to protect upstream and downstream properties and aquatic resources from damage due to increased volume, frequency, and rate of stormwater runoff or increased nonpoint-source pollution loads created on the development. a. The outlet control structure shall be designed so as not to be submerged due to downstream conditions. b. Detention basins shall be located far enough from any property line to allow non-erosive dissipation of the discharge, unless the basin discharges directly into a receiving stream. In either case, erosion control considerations shall be addressed in the erosion and sedimentation control plan. c. An emergency spillway shall be provided to bypass flows for the 100-year storm in the event that the principal outlet structure gets blocked. d. Unless otherwise approved by the environmental management department, any stormwater management facility shall be fenced to prevent access to the basin. A gate shall be provided for maintenance access. The gate shall be large enough to accommodate trucks or excavation equipment. e. A stormwater management system shall not be constructed on state waters, unless all federal, state and local environmental permits have been acquired. f. If detention is to be provided by a lake or pond, adequate storage must be provided, or be available in the case of existing lakes or ponds, to manage the runoff from the 100-year storm. In addition to these requirements, ponds or lakes must meet the requirements articles IV and X of this chapter and all applicable federal and state and local regulations. g. Water quality requirements cannot be satisfied by existing or proposed lakes or ponds. h. In common residential developments (e.g., subdivisions), all stormwater management systems except those used exclusively for water conveyance (e.g., swales, ditches, and storm pipes) shall be on common property owned by a homeowners' association, or other entity if approved by the environmental management department, and not counted as an area for an individual lot. i. The environmental management department shall require documentation and calculations beyond the original submittal if, in their opinion, the plan does not satisfy the purpose as stated in this article. The approval of the plan does not preclude the necessity for field changes once construction has begun. Any such amendments to the approved plan shall be submitted to the environmental management department on revised drawings and shall be supported by such documentation as is appropriate j. Applicants shall consult the stormwater design manual for guidance on the factors that determine site design feasibility when selecting and locating a stormwater structural control. (7) Modifications for off-site facilities. The stormwater management plan for each land development project shall provide for stormwater management measures located on the site of the project, unless provisions are made to manage stormwater by an off-site or regional facility. The off-site or regional facility must be located on property legally dedicated for the purpose, must be designed and adequately sized to provide a level of stormwater quantity and quality control that is equal to or greater than that which would be afforded by on-site practices and there must be a legally-obligated entity responsible for long-term operation and maintenance of the off-site or regional stormwater facility. In addition, on-site measures shall be implemented, where necessary, to protect upstream and downstream properties and drainage channels from the site to the off-site system. A stormwater management plan must be submitted to the environmental management department that shows the adequacy of the off-site or regional facility. To be eligible for a modification, the applicant must demonstrate to the environmental management department that the use of an off-site or regional facility will not result in the following impacts to upstream or downstream areas: a. Increased threat of flood damage to public health, life, and property; b. Deterioration of existing culverts, bridges, dams, and other structures; c. Accelerated streambank or streambed erosion or siltation; d. Degradation of in-stream biological functions or habitat; or e. Water quality impairment in violation of state water quality standards, and/or violation of any state or federal regulations. (8) Downstream analysis. Due to peak flow timing and runoff volume effects, some structural components of the stormwater management system fail to reduce discharge peaks to pre-development levels downstream from the site. A downstream peak flow analysis shall be provided to the point in the watershed downstream of the site or the stormwater management system where the area of the site comprises ten percent of the total drainage area in accordance with Section 3.1.9 of the GSMM. This is to help ensure that there are minimal downstream impacts from development on the site. The downstream analysis may result in the need to resize structural components of the stormwater management system. In calculating runoff volumes and discharge rates, consideration may need to be given to any planned upstream land-use changes. The analysis shall be in accordance with the Stormwater Design Manual. All downstream stormwater systems (eg. road culverts) withing the analysis area shall be studied for the impacts of the development. (9) Water quality. All stormwater runoff generated from a site shall be adequately treated before discharge. It will be presumed that a stormwater management system complies with this requirement if: a. It is sized to treat the prescribed water quality treatment volume from the site, as defined in the stormwater design manual; and b. Appropriate stormwater structural controls or nonstructural practices are selected, designed, constructed or preserved, and maintained according to the specific criteria in the stormwater design manual. (10) Stream channel protection. Stream channels shall be protected from bank and bed erosion and degradation by providing all of the following three approaches: a. Preservation, restoration and/or reforestation (with native vegetation) of the applicable stream buffer, as established in articles VII and IX of this chapter; and b. Twenty-four-hour extended detention storage of the one-year, 24-hour storm event. This requirement may be adjusted or waived by the environmental management department for sites that discharge directly into larger perennial streams, rivers, jurisdictional wetlands, or lakes, if the applicant can demonstrate that the reduction in these flows will not have an impact on upstream or downstream streambank or channel integrity; and c. Erosion prevention measures such as energy dissipaters that control velocity. (11) Overbank and extreme flood protection. Downstream overbank flood and property protection shall be provided by controlling (attenuating) the post-construction peak-discharge rate to the predevelopment rate for the 25-, 50-, and 100-year, 24-hour storm events. If control of the one-year, 24-hour storm events under subsection (7)b of this section is exempted, then peak discharge rate attenuation of the two-year through the 25-year return frequency storm event shall also be provided, (i.e., the two-, five-, ten- and 25-year storm events). Overbank and extreme flood protection shall be provided for all drainage basins within a development. The procedures for providing overbank and extreme flood protection shall follow the criteria specified in the stormwater design manual. This requirement may be adjusted or waived by the environmental management department, on a sub-watershed by sub-watershed basis, for sites where the post-construction downstream analysis shows that uncontrolled post-construction conditions will not increase downstream peak flows, or that meeting the requirement will cause greater peak flow downstream impacts than the uncontrolled post-construction conditions. (12) Site design credits for nonstructural measures. The use of one or more site design measures by the applicant may allow for a reduction in the water quality treatment volume required under subsection (6) of this section. The applicant may, if approved by the environmental management department, take credit for the use of stormwater better site design practices and reduce the water quality volume requirement. For each potential credit, there is a minimum set of criteria and requirements, which identify the conditions or circumstances under which the credit may be applied. The site design practices that qualify for this credit and the criteria and procedures for applying and calculating the credits are included in the stormwater design manual. All applicable documentation requirements shall be submitted and approved by the environmental management department prior to issuance of a certificate of occupancy or final plat approval. (13) Drainage easements. Drainage easements shall be provided for all stormwater management facilities designated for water conveyance. These easements shall generally be 20 feet in width, except where existing streams or creeks or constructed basins require greater width. Such easement shall be shown on plans and plats as required by other sections of the county's ordinances. Since these easements are part of an overall system for the development, neither the easement location not the system element located in it may be modified without the approval of the environmental management department. (14) Maintenance access easements. The applicant must ensure access from public right-of-way to stormwater management systems requiring regular maintenance at the site for the purpose of inspection and repair by securing all the maintenance access casements needed on a permanent basis. Such access shall be sufficient for all necessary equipment for maintenance activities. Upon final inspection and approval, a plat or document indicating that such easements exist shall be recorded and shall remain in effect even with the transfer of title of the property and All maintenance access casements shall be inspected and maintained as part of the annual operations and maintenance program. (15) Stormwater management system inspection and maintenance. The components of the stormwater management system that will not be dedicated to and accepted by Fayette County, including all drainage facilities, best management practices, credited conservation spaces, and conveyance systems, shall have an inspection and maintenance agreement to ensure that they continue to function as designed. All new development and redevelopment sites are to prepare a comprehensive inspection and maintenance agreement for the on-site stormwater management system. This plan shall be written in accordance with the requirements in section 104-561.