The following requirements shall be satisfied prior to approval of the final plat by the applicable departments:

(1) Submittals. The subdivider shall provide to the county all applicable submittals as required in the county's development regulations. A detailed list of the specific submittals and contact information for the applicable departments responsible for review and approval of each submittal is available from the county environmental management department.

(2) Final inspections. Upon completion of all minimum improvements, the subdivider shall notify the departments listed on the final plat checklist and request a field inspection. The subdivider is responsible for correcting all deficiencies identified during the final inspections. Improvements shall not be accepted unless they conform to the approved construction plans and all applicable federal, state and local requirements (see forms for final plat checklist at www.fayettecountyga.gov).

(3) Maintenance bond/irrevocable letter of credit. The subdivider shall provide to the county engineer, a maintenance bond or an irrevocable letter of credit for the purpose of guaranteeing the materials and workmanship of the minimum improvements for a period of two years. For purposes of bond/irrevocable letter of credit determination, "minimum improvements" includes all materials and work within the proposed right-of-way plus any part of the storm sewer infrastructure serving the subdivision. This includes, but is not limited to: storm pipe, open ditches, headwalls, stormwater management ponds, etc. The subdivider shall be responsible for making any needed repairs to the road or other "minimum improvements" as defined above within the two-year bonding period. Notification of needed repairs may be provided by the county to the subdivider at any time during the bonding period. If the subdivider does not make the necessary repairs within 90 calendar days of said notification, the county engineer shall claim funds from the bond or irrevocable letter of credit to adequately reimburse the county for its cost associated with having the repairs made by a contractor or the appropriate county department. Regardless of project size, the minimum maintenance bond/irrevocable letter of credit is $5,000.00. If a final plat becomes void, as may happen if not recorded into the county clerk of superior court records within 90 calendar days of approval by the planning commission, the existing maintenance bond/irrevocable letter of credit is also void and a new maintenance bond/irrevocable letter of credit will be required prior to approval of the new final plat.

(4) Ownership. Upon recordation of the final plat, subsequent to approval by the planning commission, the county shall accept ownership of any street right-of-way or other real property shown upon the final plat.

(5) Attorney review. Before acceptance of any maintenance bond or irrevocable letter of credit, the county engineer may, at his direction, have the county attorney review said instrument. If a bond is offered, it shall be executed by a surety or guaranty company qualified to transact business in the state. If an irrevocable letter of credit is offered, it shall be written by a financial institution licensed to do business in the state.

History

The history line the source prints at the end of the section.

(Ord. No. 2020-01, § 1, 5-28-2020)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fayette-county/zoning/104-600@2026-05-28-8a54552e97

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Fayette County Zoning Ordinance, Sec. 104-600. Acceptance and guarantee of completed minimum improvements; completion | Georgia Commons