Flowery Branch · Zoning Ordinance
Appendix C - ZONING ORDINANCE / Article 14 - SPECIFIC PROVISIONS FOR PRINCIPAL NONRESIDENTIAL
Sec. 14.9. Mining, Quarrying, or Extraction.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Any facility engaged in the extraction of earth products, such as sand, soil, gravel, rock, stone, clay, or other mining operations, etc. shall comply with the following:
(a) State Permits. The property owner shall submit to the Zoning Administrator a full and complete copy of all approved state permits
required for operation of the mine or quarry.
Whenever a revision or renewal of any such state permit is required or sought, the property owner shall submit to the Zoning Administrator a full and complete copy of all such applications pending along with relevant correspondence from governing state agencies regarding the disposition of the application
for permit revision or renewal.
(b) Noise Studies and Sound Level Monitoring.
The property owner may be required to submit to the Zoning Administrator a noise study meeting specifications and content details
specified by the Zoning Administrator and providing specific measurements at multiple locations along the perimeter of the property ownership boundary. Said noise study if required shall evaluate observed sound levels with noise standards of the City of Flowery
Branch as contained in its comprehensive plan and/or zoning ordinance. At any points where sound levels from such noise studies reveal that the acceptable noise threshold of the City of Flowery Branch of operational sounds (as distinguished from off-site, ambient noise) is exceeded, the professional preparing the noise study shall recommend
and the property owner shall propose noise mitigation measures and a time frame for their implementation acceptable to the City of Flowery Branch. Mitigation measures may include but shall not be limited to berms and noise attenuation barriers.
(c) Hours of Operation. Hours of operation of a mine or quarry and any on-site tenants shall be limited to 6:00 a.m. to 10:00 p.m., Monday through Saturday, with the exception that: Hours of operation (but not including
blasting) may be extended to 24 hour a day and Sunday operations as reasonably necessary for the applicant or any tenant to supply materials to a governmental project.
In all such cases the applicant for tenant shall submit a copy of the executed governmental contract for which such extended hours are reasonably necessary to the Zoning Administrator within five days of receipt of the contract. Applicant or tenant shall also
supply an anticipated schedule of extended operating hours pertaining to the contract to show that such extended hours are authorized by this condition. This exception shall only be permitted for the duration of government contracts only.
(d) Fencing. The property owner shall submit to the Zoning Administrator a detailed site plan showing the location and nature of fencing of the mine or quarry operations and/or the mine or quarry property ownership boundary. In submitting the fencing site plan, the property owner shall indicate where new
fencing (and the type of fencing) is proposed. Where no fencing is proposed by the property owner, reasons for not proposing
fencing shall be given. The fencing site plan shall be subject to the approval of the Zoning Administrator, and for good cause shown, the Zoning Administrator may disapprove of any site plan that does not provide adequate security of the area of mining or quarry operations and/or the entire ownership site.
(e) Road Surfacing. Permanent roads, defined as those to be used in excess of one year, within the excavation site shall be surfaced with a dust-free material. Roads other than permanent roads shall be treated with dust inhibitors which will reduce the generation of dust from the road surfaces as a result of wind or vehicular action.
(f) Activity Setback. The proposed extraction shall not take place within one-hundred (100) feet of a property line.
(g) Stockpiles. Product piles, spoil piles, and other accumulations of by-products shall not be created to a height more than thirty-five
(35) feet above the original contour.
(h) Blasting. The property owner shall be continuously responsible for assuring that blasting meets the Georgia Blasting Standards Act and the safe blasting limit of 2.0 inches
per second, peak particle velocity. The property owner shall achieve compliance with this regulation by monitoring blast operations. Upon request, the property owner shall submit to the Zoning Administrator a copy of
all such monitoring results from a qualified professional. In addition, any correspondence between the property owner and the State Fire Marshall relative to compliance
with the Georgia Blasting StandardsAct shall be submitted to the Zoning Administrator.
Blasting shall only be done between the hours of 10:00 a.m. and 5:00 p.m. on weekdays (except on holidays, when no blasting shall be allowed). Blasting shall not be done
at other times, except when necessary to detonate a loaded shot that could not be detonated because of adverse weather or other conditions that could not be reasonably foreseen, to maintain blasting safety, or as required to comply with applicable governmental requirements. The mine or quarry operator shall notify the Zoning Administrator of any blast that occurs outside the prescribed times of day and state why such blast occurred outside of such time within 24
hours of such blast.
History
(Ord. No. 348-16, § 1 (Exh. A), 7-19-2018)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.