Sec. 40.5. General Requirements.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) For any development, building, structure, or activity to which this Article applies, approval of a design plan shall be required before a building permit or other permit, as appropriate, is issued or any improvement, grading, alteration of land(s), or construction of building(s) commences.

(b) The Zoning Administrator shall not authorize, and the Building Inspector shall not issue, a building permit, a certificate of occupancy, or a development permit until all requirements of this, and any and all relevant articles pertaining to review are satisfactorily met.

(c) For any business, activity, or establishment which is required to obtain a business registration pursuant to the Flowery Branch City Code, no such business registration shall be issued, and operation shall not commence, until the business, activity, or establishment has either received approval of a design review request as required by this Article or has been found by the Zoning Administrator to be exempt

from design plan approval.

(Ord. No. 348-18, § 1 (Exh. A), 9-6-2018; Ord. No.

657, § 1(Exh. A), 12-16-2021)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:flowery-branch/zoning/40.5@2026-11-11-b88c3515c8

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Flowery Branch Zoning Ordinance, Sec. 40.5. General Requirements | Georgia Commons