Article 1. General

1.1. TITLE AND AUTHORITY

1.1.1. TITLE

This Ordinance regulates the use of land, the location and use of buildings and other site improvements, and the construction of public facilities and private improvements related to the development of land. This Ordinance shall be known as and may be cited as “The Unified Land Development Code of Floyd County and the City of Rome, Georgia” or, for brevity, “The Rome-Floyd County Development Code.”

1.1.2. AUTHORITY

This Ordinance is adopted under authority of Article 9, Section 2, Paragraphs 3 and 4 of the Constitution of the State of Georgia, and pursuant to the Zoning Procedures Law (O.C.G.A. 36-66-1 et seq.) and other applicable laws enacted by the General Assembly.

1.2. ADOPTION

1.2.1. REPEAL OF CONFLICTING ORDINANCES

All conflicting ordinances or parts of ordinances are hereby repealed to the extent of their conflict. Where this Ordinance and another overlap, whichever imposes the more stringent restriction shall prevail.

1.2.2. SEVERABILITY

If any section, subsection, sentence, clause, phrase or portion of this Ordinance or any amendment to it is for any reason held invalid or unconstitutional by any court of competent jurisdiction, such portion shall be deemed as a separate, distinct, and independent provision and such holding shall not affect the validity of the remaining portions of this Development Code or an amendment to it.

1.2.3. EFFECTIVE DATE

This Ordinance shall take effect for each jurisdiction upon its adoption by, respectively, the City Council and the Board of Commissioners.

1.3. PURPOSE AND INTENT

a. The purpose of this Ordinance is: To promote the health, safety, morals and general welfare of the public, and is intended:

(1) To promote the orderly and beneficial development and expansion of the City and County;

(2) To provide adequate access to natural light and air;

(3) To provide adequate water, sewerage, and surface drainage;

(4) To prevent undesirable overcrowding of population;

(5) To secure safety from fire, panic, and other dangers;

(6) To promote the orderly and desirable subdivision of land;

(7) To insure the orderly and desirable development of streets;

(8) To promote the orderly and desirable development of public and private utilities and services; and,

(9) To insure proper legal description and recordation of all subdivided land.

b. In the interpretation and application of this Ordinance all provisions shall be:

(1) Considered as minimum requirements;

(2) Deemed neither to limit nor repeal any other powers granted under state statutes.

c. This Ordinance is not intended to repeal, abrogate, or impair any valid easement, covenant or deed restriction duly recorded with the Clerk of the Superior Court.

1.4. APPLICABILITY

1.4.1. GENERAL APPLICABILITY

a. Use of Land or Structures.

(1) No structure or land shall hereafter be used, located, extended, converted or structurally altered except in full compliance with the provisions of this ordinance.

(2) No part of a yard, buffer or off-street parking spaces required in connection with any use or structure for the purpose of complying with this Ordinance shall be included as part of a yard, buffer or off-street parking spaces required for any other use or structure, unless specifically allowed under the provisions of this ordinance.

(3) Street rights-of-way shall not be considered a part of a lot or front yard setback for the purpose of meeting the minimum requirements of this Ordinance.

b. Acceptance of Public Streets.

The Governing Body shall not accept a public street unless such street substantially corresponds in its location and lines with a street shown on a preliminary subdivision plat approved under the provisions of this Ordinance.

c. Recordation and Transfer of Property.

(1) A properly approved plat must be filed and recorded with the Clerk of the Superior Court on any division of a property into 2 or more lots as required by this Ordinance.

(2) No construction permit shall be issued on any parcel for which a plat has not been properly filed and recorded with the Clerk of the Superior Court; provided further, that the description of metes and bounds in the instrument of transfer or other documents used in the process of selling or transferring such land shall not exempt the transaction from the requirements of this Ordinance.

d. Street Frontage Required.

No building permit shall be issued for and no building or other structure shall be erected on any lot unless the street giving access to such lot upon which said building is proposed to be placed shall be accepted, opened, and maintained as a public street prior to that time; shall be guaranteed to be completed, as provided in Article 6.4.6; shall otherwise be maintained by the City or County; or shall have been designated by the City or County as a private street.

e. One Principal Dwelling on a Lot.

With respect to single-family detached dwellings, one principal building and its customary accessory building may be erected on any one lot except that in the A-R and S-R districts two single-family dwelling units may be permitted on one lot if they are served by on-site sewage disposal as permitted by the Floyd County Health Department.

f. Lot Reduction Prohibited Any yard or lot existing prior to the effective date of this Ordinance or any other subsequent amendment thereto may be reduced in dimension or area below the minimum requirements as set forth in this Ordinance, subject to approval of the Building Official and Planning Director and/or their respective designee(s). Yards or lots created by subdivision after the effective date of this Ordinance shall meet at least the minimum requirements established by this Ordinance.

1.4.2. EXEMPTIONS

a. Previously Issued Permits.

The provisions of this Ordinance and any subsequent amendments shall not affect the validity of any lawfully issued and effective building or development permit if:

(1) The development activity or building construction authorized by the permit has been commenced prior to the effective date of this Ordinance or the amendment, or will be commenced after such effective date but within 6 months of issuance of the permit;

and

(2) The development activity or building construction continues without interruption (except because of war or natural disaster) until the development or construction is complete. If the permit expires, any further development or construction on that site shall occur only in conformance with the requirements of this Ordinance in effect on the date of the permit expiration.

b. Governmental Bodies.

All Governmental Bodies and authorities generally, legally exempt from regulation under the police power of Floyd County or the City of Rome shall not be exempt from the regulations contained in this Ordinance.

1.4.3. NONCONFORMING DEVELOPMENT

Lawful nonconforming uses, structures, lots and signs are declared by this Ordinance to be incompatible with land uses, structures, lots and signs that conform to the requirements of the zoning districts in which the nonconformity exists.

a. Nonconforming Uses.

(1) To avoid undue hardship, the lawful but nonconforming use of any structure or land at the time of the enactment of this Ordinance or any subsequent amendment may be continued even though the use does not conform to the provisions of this Ordinance, except that the nonconforming use:

(a) Shall not be changed to another nonconforming use.

(b) Shall not be re-established after its removal from the property or its discontinuance for 12 months or more.

(c) Shall not be repaired, rebuilt or altered after damage exceeding 50% of its replacement cost at the time of destruction.

(d) Shall not be enlarged or altered in a way that increases its nonconformity if the structure or land is located in the city.

(e) Shall not be enlarged or altered in any way that increase its nonconformity if the structure or land is located in the county unless the nonconforming use shall comply with all applicable building codes, setback requirements, lot size requirements, and public safety issues that exist for the least restrictive zoning district in which the current use would normally be allowed.

(2) Exceptions.

(a) The strengthening or restoration to a safe condition of any structure or part thereof declared to be unsafe by an official charged with protecting the public safety or health shall be allowed upon order of such official.

(b) A nonconforming single-family detached, duplex or triplex may be repaired, rebuilt or replaced after damage exceeding 50% by approval as a special use, in accordance with the procedures of Article 2; provided, however, that a triplex dwelling constructed prior to the adoption of the code may be repaired, rebuilt, or replaced after damage exceeding 50%; and may be re-established after its removal from the property or its discontinuance for 12 months or more as a use permitted by right in the D-R Duplex-Residential zoning district.

(c) A use that was lawfully established prior to the adoption, revision or amendment of this Ordinance, but which, by reason of such adoption, revision or amendment now requires approval as a Special Use in the zoning district where the use is located, shall not be considered a nonconforming use under the provisions of this Ordinance, and, therefore is not subject to the prohibitions on enlargement or alteration of an existing use.

(d) Maintenance, repair and replacement of deteriorated elements such as roofs, foundations, windows, walls, fixtures and systems (plumbing, electrical, HVAC) shall be allowed if such maintenance, repair or replacement will not expand, enlarge or alter the use or structure in a way that increases its nonconformity; and if such maintenance will not exceed 50% of the replacement cost at the time.

b. Nonconforming Structures.

(1) A nonconforming structure may continue to be occupied and used, except that the nonconforming structure:

(a) Shall not be repaired, rebuilt or altered after damage exceeding 50% of its replacement cost at the time of destruction.

(b) Shall not be enlarged or altered in a way that increases its nonconformity.

(2) Exceptions.

(a) The strengthening or restoration to a safe condition of any structure or part thereof declared to be unsafe by an official charged with protecting the public safety or health shall be allowed upon order of such official.

(b) A nonconforming single-family detached, duplex or triplex dwelling may be repaired, rebuilt or replaced after damage exceeding 50% by approval as a special use, in accordance with the procedures of Article 2; provided, however, that a tri-plex dwelling constructed prior to the adoption of the code may be repaired, rebuilt, or replaced after damage exceeding 50%; and may be re-established after its removal from the property or its discontinuance for 12 months or more as a use permitted by right in the D-R Duplex-Residential zoning district .

(c) Maintenance, repair and replacement of deteriorated elements such as roofs, foundations, windows, walls, fixtures and systems (plumbing, electrical, HVAC) shall be allowed if such maintenance, repair or replacement will not expand, enlarge or alter the structure in a way that increases its nonconformity; and if such maintenance will not exceed 50% of the replacement cost at the time.

c. Nonconforming Lots.

(1) Where the owner of a legal lot of record at the time of the adoption of this Ordinance does not own sufficient land to conform to the minimum lot size or lot width requirement of this Ordinance, such lot may nonetheless be used as a building site provided that access to a public street is provided directly or through a recorded easement, and further provided that the minimum building setbacks are not reduced below the minimum specified in this Ordinance.

d. Nonconforming Signs.

(1) Permanent Signs.

A nonconforming sign that is permanently affixed to the ground or to a building may continue to be used, except that the nonconforming sign:

(a) Shall not be replaced except in conformity with the provisions of this Ordinance.

(b) Shall not be repaired, rebuilt or altered after damage exceeding 50% of its replacement cost at the time of destruction.

(c) Shall not be enlarged or altered in a way that increases its nonconformity.

(2) Permanent Signs in the County Section 1.4.3(d) (1) shall have application only in the city, and Section 1.4.3(d)

(2) shall have application only in the county. In the county, a nonconforming sign structure that is permanently affixed to the ground or to a building may continue to be used or repaired as a legal, nonconforming use except:

(a) If the repair of a sign structure or any portion thereof causes the area of the sign face to the be greater than 110% of the area of the previous sign face, then the sign structure may be repaired but only in conformance with the provisions of Article 5 Sign Regulations of this Ordinance; and

(b) If the repair of a sign structure or any portion thereof relates to anything other than minor repairs such as painting, replacement of defective parts, cleaning or similar minor maintenance to a sign designed to keep a sign at an acceptable functional and aesthetic level, then the sign structure may be repaired but only in conformance with the provisions of Article 5 Sign Regulations of this Ordinance.

1.5. INTERPRETATION

1.5.1. RESPONSIBILITY FOR INTERPRETATION

a. The Chief Building Official shall be responsible for the interpretation of the requirements, standards, definitions or any other provision of this Ordinance.

b. Interpretations of the Chief Building Official may be appealed under the provisions of Article 2 relating to Appeals.

1.5.2. USE OF FIGURES

Figures associated with defined terms or regulatory paragraphs in this Ordinance are provided for illustration only and do not limit or change the meaning of the term as defined or the requirements of the regulation as written.

1.5.3. USE OF WORDS AND PHRASES

For the purpose of this Ordinance, the following shall apply to the use of words and phrases:

a. Words used in the present tense include the future tense. Words used in the singular tense include the plural tense, and words used in the plural tense include the singular tense. The masculine person “he” or “his” also means “her” or “hers.”

b. Use of the capitalized word “City” refers to the government of the City of Rome, Georgia, while the lower case word “city” refers to its incorporated geographical area.

c. Use of the capitalized word “County” refers to the government of Floyd County, Georgia, while the lower case word “county” refers to its unincorporated geographical area.

d. References to the “City” and to the City Commission and any public officials or appointed bodies of the City not otherwise named by political jurisdiction or defined in this Ordinance shall always mean the City of Rome, Georgia, and it’s Governing Body, appointed or employed officials, and appointed bodies as named.

e. References to the “County” and to the County Commission and any public officials or appointed bodies of the County not otherwise named by political jurisdiction or defined in this Ordinance shall always mean Floyd County, Georgia, and it’s Governing Body, appointed or employed officials, and appointed bodies as named.

f. References to public officials, departments or appointed bodies of jurisdictions other than Floyd County or the City of Rome shall always mean such persons or bodies having jurisdiction over or relative to Floyd County or the City of Rome, Georgia. These may include one or more of the following:

(1) The Clerk of the Superior Court of Floyd County, Georgia.

(2) The Floyd County Health Department.

(3) Rome/Floyd County Historic Preservation Commission.

(4) The Coosa River Soil and Water Conservation District.

(5) The Coosa Valley Regional Development Center.

(6) The Georgia Departments of Natural Resources and Transportation.

(7) The United States Army Corps of Engineers, the Federal Aviation Administration, the Federal Emergency Management Agency and the Environmental Protection Agency, the Natural Resource Conservation Service.

g. The word “person” is intended to include any individual, partnership, firm, association, joint venture, public or private corporation , trust, estate, commission, board, public or private institution, utility, cooperative, state agency, municipality, or other political subdivision of this State, any interstate body or any other legal entity.

h. The words “shall” and “must” are always mandatory and not discretionary, while the word “may” is permissive.

i. The word “and” indicates that all of the conditions, requirements or factors so connected must be met or fulfilled, while the word “or” indicates that at least one condition, requirement or factor so connected must be met.

j. The term “such as” is intended to introduce one or more examples in illustration of a requirement or point, and is intended to mean “including but not limited to the following.”

k. The verbs “zone” and “rezone” have the same meaning and refer to the act of amending the Official Zoning Map through the process established by this Ordinance.

l. The nouns “zone,” “zoning district” and “district” have the same meaning and refer to the zoning districts established under this Ordinance.

m. The word “day” shall mean a calendar day unless otherwise specified.

1.5.4. MEANING OF WORDS AND PHRASES

a. All words and phrases shall be interpreted within the context of the sentence, paragraph, section and Article in which they occur.

b. Words and phrases defined in this Ordinance shall be interpreted as defined without regard to other meanings in common or ordinary use, unless the context of the word or phrase indicates otherwise. Words and phrases not defined in this Ordinance shall be construed to have the meaning given by common and ordinary use as defined by a contemporary dictionary.

Article 2. Procedures

2.1. GENERALLY

2.1.1. PURPOSE OF ARTICLE 2

This Article describes the process through which a zoning change may be approved on a property, the approved process for construction of land development projects, the procedures for amendments to the text of this Development Code, and the process for appeals from an administrative decision, for a special exception or for hardships.

2.1.2. OVERVIEW-LAND DEVELOPMENT

The following presents a summary of the plans and procedures involved in the land development approval and construction.

a. Zoning Changes.

All applications for rezoning or a special use permit for a multi-family or nonresidential use must be filed with the Rome/Floyd County Planning Department.

b. Multi-Family and Nonresidential Projects.

(1) Project Approval is granted by the Planning Department upon review and approval of a Site Plan for the project.

(2) A Development Permit is issued by the Chief Building Official, based on review and approval of development plans for construction of the project.

(3) The Chief Building Official, based on review and approval of architectural plans, issues a Building Permit. Buildings falling under the authority of the State Fire Marshall shall be approved by the Fire Department prior to issuance of the building permit.

(4) Receipt by the Public Works Department of accurate surveys of the as-built condition of all public improvements is required in order to authorize permanent water and sanitary sewer service.

(5) The Chief Building Official, based on final inspection and issuance of a Certificate of Occupancy, authorizes permanent electric power and occupancy of the building.

c. Single Family Residential Projects Single family residential projects shall follow the process outlined in Article 6 for the review and approval of preliminary and final subdivision plat and development permits.

d. City-County Coordination.

In order to assure full coordination between all affected departments and agencies and to increase efficiency in the processing of permits, all applications for a rezoning or special use approval shall be submitted to the Planning Department for handling. All applications for a development permit or flood area permit shall be submitted to the Building Inspection Department for handling.

2.2. ZONING CHANGES

The Official Zoning Map may be amended from time to time and the Governing Body under the procedures in this Section may approve special uses for specific properties. In addition, the Governing Body, following the procedures in this section, may also approve changes in the conditions of approval pertaining to a specific rezoning or conditional use approval. All of these types of actions are referred to as “zoning changes” and must be filed with the Rome/Floyd County Planning Department.

2.2.1. INITIATION

a. An application for a zoning change for any property or properties may be initiated by the Governing Body, by the Planning Commission, or by the owner of the property. Unless the initiated by the Governing Body or the Planning Commission, the owner of a majority interest in the property affected shall initiate all such applications.

b. All applications shall be submitted to the Planning Department on the Department’s application forms. A non-refundable fee as fixed from time to time by the Governing Body shall accompany all applications. A fee shall not be charged if the Governing Body or the Planning Commission has initiated the application.

c. The Planning Department shall review the application for completeness within 5 business days of submission. Incomplete or improper applications will be returned to the applicant.

d. An application for a zoning change affecting the same property shall not be considered by the Governing Body more often than once every 12 months; provided, however, that the Governing Body may approve a reduction in the waiting period to no less than 6 months.

2.2.2. SKETCH PLAN

a. An application for a rezoning or special use permit approval, related to any use other than a single family residence, shall be accompanied by a sketch plan if any new construction is proposed or alteration of the site is required under the site or development design standards of the Development Code (Article 6). A plat drawing may be submitted in lieu of a sketch plan, if the purpose of the rezoning request is to market the property.

b. All sketch plans shall be considered binding when made a condition of approval of the rezoning or special use by the respective Governing Body.

c. The applicant, a professional engineer, a registered land surveyor, a landscape architect, a land planner, or any other person familiar with land development activities may prepare a sketch plan.

d. The sketch plan shall be drawn to approximate scale on a boundary survey of the tract or on a property map showing the approximate location of the boundaries and dimensions of the tract.

e. The sketch plan shall show the following, as appropriate to the zoning or special use requested:

(1) Name and address of the property owner.

(2) Name, address, and telephone number of the applicant, if different from the owner.

(3) Date of survey, north point and graphic scale, source of datum, date of plan drawing, and revision dates, as appropriate.

(4) Proposed use of the property, if known.

(5) Location (Land District and Land Lot) and size of the property in acres (or in square feet if less than an acre).

(6) Location sketch of the property in relation to the surrounding area with regard to well-known landmarks such as arterial streets or railroads. Sketches may be drawn freehand and at a scale sufficient to show clearly the information required, but not less than 1 inch equal to 2,000 feet. U.S. Geological Survey maps may be used as a reference guide for the location sketch.

(7) Zoning district classification of the subject property and all adjacent properties, and zoning district boundaries if they cross the property.

(8) Man-made features within and adjacent to the property, including existing streets and names, city and county political boundary lines, and other significant information such as location of bridges, utility lines, existing building to remain, and other features as appropriate to the nature of the request.

(9) The proposed project layout including the approximate outline and location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas and driveways.

(10) A statement as to the source of domestic water supply.

(11) A statement as to the provision for sanitary sewage disposal.

(12) The approximate location of proposed storm water detention facilities.

(13) Such additional information as may be useful to permit understanding of the proposed use and development of the property.

2.2.3. PROCESS FOR ZONING CHANGES

Before the Governing Body may take final action on a proposed zoning change, the Planning Commission shall hold a public hearing on the proposal.

a. Public Notice.

(1) Notification to the General Public.

(a) At least 15 days but not more than 45 days prior to the public hearing, notice shall be published in a newspaper of general circulation within the county. The Planning Department shall prepare such notice, which shall state the time, place and purpose of the hearing.

(b) A zoning change initiated by a party other than the Governing Body or the Planning Commission shall be heard at a public hearing only upon:

1) The published notice, in addition to the requirements above, shall include the location of the property, the present zoning classification, and the proposed zoning classification of the property or the special use requested; and

2) At least 15 days prior to the public hearing, the Planning Department shall post a sign or signs of not less than 6 square feet stating “Zoning Action Pending. For further information please contact the Rome-Floyd County Planning Department at (phone number) or (e-mail address).” One such sign shall be placed in a conspicuous location along each street frontage of the property for which the zoning change has been requested. If the property has no street frontage, the sign shall be placed on each street from which access will be gained to the property.

(2) Notice to Surrounding Property Owners.

All adjacent property owners are to be notified of any proposed zoning change without regard for who the applicant is for a zoning change.

(a) Notice shall be given to all surrounding property owners as follows: At least 5 days prior to the Planning Commission public hearing, the Planning Department shall cause a notice to be mailed to all persons owning property located adjacent to or across the street from the property that is the subject matter of the zoning change.

(b) The notice shall state the time, place, and purpose of the hearings. The written notice shall be mailed to the property owners as such names and addresses appear on the County’s ad valorem tax records.

b. Planning Commission Public Hearing.

The public hearing held by the Planning Commission for zoning changes shall be conducted in the following manner:

(1) The Chairperson, the Vice Chairperson, or the Planning Commission’s designee, who shall act as the Presiding Official, shall convene the public hearing at the scheduled time and place.

(2) The Presiding Official shall call for each proposed zoning change to be presented to the Planning Commission.

(3) No person in attendance shall speak unless first formally recognized by the Presiding Official. Upon rising to speak each person recognized shall state his or her name and home address. The Presiding Official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed zoning change. No less than 10 minutes shall be provided for all of those speaking in support of a zoning change and no less than 10 minutes shall be provided for all of those speaking against, unless such proponents or opponents take less time than the minimum allowed. If reasonable time limitations permit, any member of the public may speak at a hearing. However, the applicant and nearby property owners shall be afforded the first opportunity to speak. Each side shall be afforded an equal minimum time period for the presentation of data, evidence, and opinion.

(4) The applicant shall be allowed to speak first in order to present the application.

Others in support of the application may then speak, followed by those in opposition to the application. The applicant will then be allowed time for rebuttal provided they have not used all their allotted time during the presentation. Rebuttal must be limited to points or issues raised by opponents to the application at the hearing.

(5) During the public hearing, the Planning Commission members may ask questions at any time. Time devoted to questions and answers will not be counted against any time limitations that have been imposed on presentations.

(6) Following the public hearing on each zoning change, the Planning Commission at that time shall make its recommendation or take such other action as may be appropriate.

(a) A motion to recommend approval that receives an affirmative vote from a majority of the voting members present will be forwarded to the Governing Body as a recommendation for approval. A motion to recommend approval that receives a negative vote from a majority of the voting members present will be forwarded as a recommendation for denial.

(b) A motion to recommend denial that receives an affirmative vote from a majority of the voting members present will be forwarded to the Governing Body as a recommendation for denial. A motion to recommend denial that receives a negative vote from a majority of the voting members present will be forwarded as a recommendation for approval.

(c) A tie vote on a motion will be forwarded to the Governing Body as no recommendation with the actual vote transmitted.

(d) If no action is taken on an application, it will go forward to the Governing Body with no recommendation.

(e) A motion to postpone that receives an affirmative vote from a majority of the voting members present will result in action on the zoning change being deferred for a period of time as specified by the members of the Planning Commission.

However, where the governing body has initiated a zoning change, the Planning Commission shall act on the zoning change by the date specified by the governing body. At the discretion of the chair, a postponed zoning change may be considered at a specially called meeting.

(7) In making its recommendation or taking such action as may be appropriate, the planning commission shall not discriminate against any person in violation of law, including the Fair Housing Act.

c. Governing Body Public Hearing.

(1) The Governing Body shall conduct a public hearing to consider an application for a zoning change within its jurisdiction. Said public hearing shall be held no later than the second regular meeting of the Governing Body following the public hearing of the Planning Commission. At a regular meeting prior to its public hearing, the Governing Body shall have a first reading of any proposed rezoning or Special Use ordinance.

(2) The Chairperson of the Governing Body or another person designated by the Governing Body shall act as Presiding Official.

(3) The Presiding Official shall call for each proposed zoning change to be presented to the Governing Body. As each application for a zoning change is called for consideration, the Presiding Official shall have the recommendation of the Planning Department read and shall present such other documentation as may be deemed pertinent.

(4) No person in attendance shall speak unless first formally recognized by the Presiding Official. Upon rising to speak each person recognized shall state his or her name and home address. The Presiding Official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed zoning change. No less than 10 minutes shall be provided for all those speaking in support of a zoning change and no less than 10 minutes shall be provided for all of those speaking against, unless such proponents or opponents take less time than the minimum allowed. If reasonable time limitations permit, any member of the public may speak at a hearing. However, the applicant and nearby property owners shall be afforded the first opportunity to speak. Each side shall be afforded an equal minimum time period for presentation of data, evidence, and opinion.

(5) The applicant shall be allowed to speak first in order to present the application.

Others in support of the application may then speak, followed by those in opposition.

The applicant will then be allowed time for rebuttal provided they have not used all their allotted time during the presentation. Rebuttal must be limited to points raised by opponents to the application at the hearing.

(6) During the public hearing, the members of the Governing Body may ask questions at any time. Time devoted to questions and answers will not be counted against any time limitations that have been imposed on presentations.

(7) Following the public hearing on the zoning change (or upon second reading), action shall be considered by vote of the Governing Body.

(a) A motion to approve or deny an application must be approved by an affirmative vote of at least a quorum of the members in order for the motion to be approved.

(b) If a motion to approve an application fails, the application is automatically denied.

If a motion to deny an application fails, another motion would be in order.

(c) A tie vote on a motion for approval of an application shall be deemed a denial of the application. A tie vote on any other motion shall be deemed to be no action, and another motion would be in order.

(d) If no action is taken on an application, it shall be considered tabled and action deferred to the next regular meeting of the Governing Body.

(8) If taking action on an application, the Governing Body may:

(a) Either approve, approve with conditions, or deny the proposal; or,

(b) Allow withdrawal if so requested by the applicant (with or without imposing a six month period during which another zoning change on the property may not be considered); or,

(c) Table the proposal for consideration at its next scheduled meeting; or,

(d) Refer the application back to the Planning Commission for further consideration.

(9) In taking action on an application the Governing Body shall not discriminate against any person in violation of law including the Fair Housing Act.

d. Referral to Planning Commission for Further Consideration.

If the Governing Body refers an application back to the Planning Commission for further study:

(1) The Planning Department shall give public notice of the Planning Commission’s hearing for further consideration in the same manner as described above, and the Planning Commission shall conduct its additional public hearing and take action as described above.

(2) After the Planning Commission’s rehearing and recommendation on the referred application, the Governing Body shall follow the same procedures set forth above to consider the application.

e. Rezoning of Areas to be annexed into the City.

An area proposed for annexation into the city shall first be considered for rezoning prior to its annexation. Consideration of the rezoning shall be subject to the same procedures, standards, and requirements for any zoning change as contained in this Section, except as modified below:

(1) COUNTY: Where the property to be annexed does not include a request for a change in zoning district classification, the Planning Commission shall review the annexation request and make a recommendation to the City to approve or deny the annexation.

(1) CITY: If the property to be annexed is to continue to have the some zoning district classification for which the property was zoned immediately prior to the annexation, the City requires no further action and the existing zoning on the property shall continue in full force and effect.

(2) If the property to be annexed is proposed or requested to be rezoned, upon or following the date of notice to the County of the proposed annexation as required under O.C.G.A. § 36-36-6, the City Commission shall initiate the rezoning of the property to be annexed or consider an application for a zoning change submitted by or on behalf of the owner of such property under the provisions of this Section.

(3) The Planning Commission and the Governing Body shall conduct their public hearing on the zoning change prior to the annexation of the land into the city. Notice of such hearing shall be provided under the provisions of this Section, provided further that the notice shall be published in a newspaper of general circulation in the county.

(4) Following its public hearing on a zoning change for a property proposed to be annexed, the governing body may take action on the zoning change or it may table such action pending action on the proposed annexation. In any event, the zoning change shall become effective on the later of:

(a) The date the zoning is approved by the governing body; or,

(b) The date that the annexation becomes effective under O.C.G.A. § 36-36-2.

(5) Disputes between the City and County concerning annexation shall be resolved in accordance with the O.C.G.A. §36-36-110 et seq.

2.2.4 STANDARDS FOR ZONING CHANGES

a. Zoning Map Amendments (Rezoning).

The Planning Commission and the Governing Body shall consider the following standards in considering any zoning proposal that would result in a change in the boundary of a zoning district, giving due weight or priority to those factors that are appropriate to the circumstances of each proposal:

(1) Is the proposed use or development consistent with the stated purpose of the zoning district?

(2) Is the proposed use suitable in view of the zoning and development of adjacent and nearby property?

(3) Will the proposed use not adversely affect the existing use or usability of adjacent or nearby property?

(4) Is the proposed use compatible with the purpose and intent of the Comprehensive Plan?

(5) Are there substantial reasons why the property cannot or should not be used as currently zoned?

(6) Will the proposed use not cause an excessive or burdensome use of public facilities or services, including but not limited to streets, schools, water or sewer utilities, and police or fire protection?

(7) Is the proposed use supported by new or changing conditions not anticipated by the Comprehensive Plan or reflected in the existing zoning on the property or surrounding properties?

(8) Does the proposed use reflect a reasonable balance between the promotion of the public health, safety, morality, or general welfare and the right to unrestricted use of property?

b. Special Uses.

A special use otherwise permitted within a zoning district shall be considered to be compatible with other uses permitted in the district, provided that due consideration is given to the following objective criteria as applicable to the specific use proposed:

(1) Is the proposed special use consistent with the stated purpose of the zoning district?

(2) Is or will the type of street providing access to the use be adequate to serve the proposed special use?

(3) Is or will access into and out of the property be adequate to provide for traffic and pedestrian safety, the anticipated volume of traffic flow, and access by emergency vehicles?

(4) Are or will public facilities such as schools, water or sewer facilities, and police or fire protection be adequate to serve the special use?

(5) Are or will refuse service, parking and loading areas on the property be located or screened to protect other properties in the area from such adverse effects as noise, light, glare, or odor?

(6) Will the hours and manner of operation of the special use have no adverse effects on other properties in the area?

(7) Will the height, size or location of the buildings or other structures on the property be compatible with the height, size or location of buildings or other structures on neighboring properties?

c. Change in Conditions of Approval.

Any application that proposes a change in the conditions of approval previously established by the Governing Body through action on a zoning change shall be reviewed in light of the standards set forth in this Section for a map amendment or special use, as appropriate.

2.2.5. WITHDRAWAL

Any applicant wishing to withdraw a proposed zoning change prior to final action by the Governing Body shall file a written request for withdrawal with the Director of Planning.

a. If the request for withdrawal is received prior to the publication of notice for the public hearings, the application shall be withdrawn administratively by the Director of Planning without restriction on the re-filing of a proposed zoning change on the property in the future.

b. If notice has been published but the application has not been heard by the Planning Commission, the application shall be withdrawn administratively by the Director of Planning upon receipt of a written request. An application for zoning change on the property may then be resubmitted by the applicant, without waiting the period of six (6) months. If a second application for rezoning is withdrawn within six (6) months of withdrawal of an application for rezoning of the same property, a third application may not be resubmitted for six (6) months.

c. Should any request for withdrawal be made by the applicant at or following the Planning Commission hearing, the application shall remain on the Governing Body’s public hearing agenda and the withdrawal request shall be considered for approval or denial, with or without prejudice, by the Governing Body.

2.2.6. DEVELOPMENTS OF REGIONAL IMPACT

a. Any application for rezoning, Special Use Permit, or development or building permit that would result in an activity or project that meets or exceeds any of the State of Georgia thresholds shall be considered a Development of Regional Impact:

b. Any Development of Regional Impact (DRI) shall be submitted by the applicant to the Coosa Valley Regional Development Center (RDC) prior to submission of the application to the Planning Department. Once the RDC has accepted the completed form, and has made an official determination that the project is a DRI (within 5 calendar days), the 30-day review period officially begins.

c. The Governing Body shall not take final action to approve a Development of Regional Impact until either:

(1) A report has been received from the Coosa Valley RDC reflecting its finding and recommendations, if any; or

(2) Said report is not received within 30 days of submittal of the application to the RDC.

2.2.7. EFFECT

a. Approval of a zoning change shall be in full force and effective upon its approval by the Governing Body, except that:

b. Approval of a zoning change on a property that is being annexed into the city shall become effective on the latter of:

(1) The date the rezoning is approved by the City Commission; or,

(2) The date that the annexation becomes effective pursuant to the State law under

O.C.G.A. §36-36-2.

c. For a property on which a use, building, structure or other improvements existed in conformity with this Development Code prior to the effective date of a zoning change affecting the property, any such building, structure or other improvements no longer in conformance shall be governed under the provisions for Nonconforming Development in Article 1 of this Development Code.

d. Construction of any use, building, structure, or other improvements for which a building permit has been issued in conformity with this Development Code prior to the effective date of a zoning change affecting the property may continue to completion as though no change has occurred and, upon completion, shall be governed under the provisions for Nonconforming Development in Article 1 of this Development Code, as applicable.

2.3. LAND DEVELOPMENT PROJECT APPROVAL

The Planning Department must first approve the site plan for development of a multifamily or nonresidential project prior to the issuance of a Development Permit or initiation of any land disturbing or construction activities.

2.3.1. RESPONSIBILITY

a. The Chief Building Official is responsible for administering the review and approval process for site plans. The Chief Building Official shall forward a copy of the project approval application to appropriate City or County Departments, the Georgia Department of Transportation, or others as appropriate, for their review and comment. The Chief Building Official shall provide all comments to the applicant for resolution, who shall work with each City or County Department or other agency as necessary to resolve all issues.

b. A professional engineer, registered land surveyor or landscape architect registered to practice in the State of Georgia may prepare the site plan.

2.3.2. PROCEDURE FOR PROJECT APPROVAL

a. An application for project approval may be processed independently or in conjunction with an application for issuance of a development permit.

b. The property owner or their authorized representative shall submit an application for project approval to the Building Inspection Department. The application shall include:

(1) A properly completed application form, as furnished by the Building Inspection Department, requesting review for project approval.

(2) Copies of the site plan showing the entire ownership drawn to the specifications of this Section, in a number as required by the Building Inspection Department.

(3) Payment of all applicable application and review fees, as established by the Governing Body from time to time.

c. The Building Inspections Department shall review the application for completeness at the time of submission. Incomplete applications will be returned to the applicant.

d. Within 2 weeks following the receipt of the application, the Building Inspection Department shall return to the applicant, on the drawing or in writing, all comments related to compliance with this Development Code.

e. The owner shall be responsible for compliance with all codes, regulations, and zoning requirements and for the satisfaction of all the noted and written comments.

f. The Building Inspection Department may not approve any site plan whereon is shown a lot or situation that would clearly require a variance to order to be reasonably usable, whether due to the presence of flood plain, unusual configuration, zoning compliance, lack of public utilities, or for any reason.

g. When the Building Inspection Department has determined that the site plan is in compliance with the requirements, purpose and intent of this Development Code, it shall be approved. The Chief Building Official or his designee shall sign and date the CERTIFICATE OF PROJECT APPROVAL stamped or printed on a reproducible copy of the site plan. One copy of the approved drawing shall be transmitted to the applicant and 1 copy shall be retained by the Building Inspection Department.

h. The Certificate of Project Approval shall remain in effect for a period of 6 consecutive months after which time it shall become null and void and a new Certificate may be required after which time it shall become required if either no permit has been issued or a permit has been issued but no development activity has begun.

2.3.3. GENERAL STANDARDS

a. The proposed name of the development shall not duplicate or too closely approximate, phonetically, the name of any other development in the city or county. If shown to the contrary, the Building Inspection department may refuse to accept such.

b. The site plan shall be prepared on a boundary survey of the entire tract to be subdivided or developed showing the location of the boundaries and dimensions of the tract to be developed.

c. The site plan shall be clearly and legibly drawn at a scale of 100 feet or less to 1 inch.

The recommended maximum dimensions of the sheet size is 36 inches by 48 inches and the minimum dimensions of 17 inches by 22 inches; however, the Chief Building Official may approve other sheet sizes and scales as appropriate.

d. For property of over 1,000 acres, a smaller scale may be used where, in judgment of the Chief Building Official, presentation of detailed data is not necessary to evaluate the entire project. It is the intent of this provision that in all cases sufficient information shall be provided for an adequate evaluation of the public and private improvements.

2.3.4. SITE PLAN REQUIREMENTS

a. Proposed name of development.

b. Name and address of the property owner and developer.

c. Name, address, and telephone number of the applicant.

d. Date of survey, north point and graphic scale, source of datum, date of plan drawing, and revision dates, as appropriate.

e. Proposed use of the property.

f. Location (Land District and Land Lot) and size of the property in acres (or in square feet if less than an acre).

g. Location sketch of the property in relation to the surrounding area with regard to wellknown landmarks such as arterial streets, railroads, or others. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, not less than 1 inch equal to 2,000 feet. U.S. Geological Survey maps may be used as a reference guide for the location sketch.

h. Zoning district classification of the subject property and all adjacent properties, and zoning district boundaries as appropriate.

i. Delineation of required buffers, landscape areas, tree protection areas, and river corridor buffers, as applicable.

j. Rezoning or conditional use application number, date of approval, and conditions of approval, as applicable. Variances obtained on the property by application number, date of approval, and conditions of approval, as applicable.

k. Recorded deed names of adjoining property owners.

l. Natural features within, affecting or affected by the property, including wetlands, drainage channels, bodies of water, wooded areas and other significant natural features such as rock outcroppings. On all watercourses entering or leaving the property, the direction of flow shall be indicated. The 100-year flood plain and wetlands, if any shall be outlined. The location of the site within a protected groundwater recharge area shall be noted if applicable.

m. Man-made features within and adjacent to the property, including street right-of-way and pavement widths, names of existing streets, all easements, city and county political boundary lines, and other significant information such as location and dimensions of bridges, utility lines, existing buildings to remain, and other features.

n. The proposed project layout including:

(1) For multi-family and nonresidential development site plans, the outline and location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas, driveways, curb cuts, and designated fire lanes.

o. The proposed phasing of the development if it is proposed to be built in sections.

p. A statement as to the source of domestic water supply.

q. A statement as to the provision for sanitary sewage disposal. For those properties that will not be served by a public sanitary sewerage system, written approval by the Floyd County Health Department shall be submitted.

r. The approximate location of proposed storm water detention facilities.

s. Such additional information as may be reasonably required to permit an adequate evaluation of the development activity proposed in the application.

2.3.5. EVIDENCE OF PROJECT APPROVAL

Each site plan shall carry the following certificates printed or stamped on the plat.

a. Signed approval from the County Health Department (if septic tanks will be allowed by the Governing Body).

b. Certificate of Project Approval, to read as follows:

CERTIFICATE OF PROJECT APPROVAL

All applicable requirements of the Rome-Floyd County Unified Land Development Code relative to the project approval having been fulfilled, approval is hereby granted by the Rome-Floyd County Building Inspection Department, subject to further compliance with all provisions of said Development Code.

________________________________________ Chief Building Inspector Date______________________ This “Certificate of Project Approval” shall expire 6 months from the date of approval if a Development Permit has been issued but development activity has not been commenced.

2.4. DEVELOPMENT PLANS

2.4.1. GENERAL REQUIREMENTS

a. Persons seeking to undertake development activity shall not commence or proceed until development plans are approved and the Chief Building Inspector issues a Development Permit. The process for approval of a development permit is presented in Section 2.5 below.

b. The development plans for a project shall conform in all respects with the requirements of this Development Code, and shall contain each of the plans in this Section as appropriate to the project, including:

(1) Erosion and Sediment Control Plan

(2) Grading Plan

(3) Storm water Management Plan

(4) Street Improvement Plan

(5) Buffer/Landscaping/Tree Conservation Plan

(6) Public Utility Plan

c. All development plans and supporting studies shall be prepared by or under the supervision of a professional engineer registered in Georgia.

2.4.2. EROSION AND SEDIMENT CONTROL PLAN

a. Plans must be prepared to meet the erosion and sedimentation control requirements of Section 6 of this Development Code or through the use of more stringent, alternate design criteria which conform to sound conservation and engineering practices. Conformance with the minimum requirements may be attained through the use of design criteria in the current issue of the Manual for Erosion and Sediment Control in Georgia; or through the use of alternate design criteria that conform to sound conservation and engineering practices. The erosion and sediment control plan shall consider the interrelationship of the soil types, geological and hydrological characteristics, topography, watershed, vegetation, proposed permanent structures including roadways, constructed water ways, sediment control and storm water management facilities, local ordinances and State laws.

b. Data Required for Erosion and Sediment Control Plan:

(1) Narrative or notes, and other information: Notes for narrative to be located on the site plan in general notes or in erosion and sediment control notes.

(2) Description of existing land use at project site and description of proposed project.

(3) Name, address, and phone number of the property owner and the developer.

(4) Name and phone number of 24-hour local contact who is responsible for erosion and sediment controls.

(5) Size of project, or phase under construction, in acres.

(6) Activity schedule showing anticipated starting and completion dates for the project.

Include the statement in bold letters that “the installation of erosion and sediment control measures shall occur prior to or concurrent with land-disturbing activities.”

(7) Storm water and sedimentation management systems storage capacity, hydrologic study, and calculations, including off-site drainage areas.

(8) Vegetative plan for all temporary and permanent vegetative practices, including species, planting dates, and seeding, fertilizer, lime and mulching rates. The vegetative plan should show options for year round seeding.

(9) Detail drawings for all structural practices. Specifications may follow guidelines set forth in the Manual for Erosion and Sediment Control in Georgia.

(10) Maintenance statement: “Erosion and sediment control measures will be maintained at all times. Additional erosion and sediment control measures will be installed if deemed necessary by on-site inspection.”

c. Maps, drawings and supportive computations shall bear the signature/seal of a registered or certified professional in engineering, architecture, landscape architecture, land surveying or erosion and sediment control. The certified plans shall contain:

(1) Graphic scale and north point or arrow indicating magnetic north.

(2) Vicinity map showing location of project and existing streets.

(3) Boundary line survey.

(4) Delineation of disturbed areas within project boundary.

(5) Existing and planned contours, with contour lines drawn with an interval in accordance with the following:

Map Scale Ground Slope Contour Interval 1 inch = 50 ft.

or larger scale Flat 0-2% Rolling 2-8% Steep 8% + Every 2 feet Every 5 feet Every 10 feet

(6) Spot Elevations:

(a) For sites smaller than 1 acre in size, show the direction of drainage and spot elevations at all breaks in grade and along drainage channels or swales at selected points not more than 100 feet apart.

(b) For sites of 1 acre and larger with slopes of less than 2 percent, show contours at intervals or not more than 2 feet and spot elevations at all breaks in grade along drainage channels and swales at selected points not more than 100 feet apart.

(7) Adjacent areas and features such as streams, lakes, residential areas, etc. which might be affected should be indicated on the plan.

(8) The limits of the 100-year flood plain and the flood way.

(9) Proposed structures or additions to existing structures and paved areas.

(10) The limits of any required greenway adjacent to state waters.

(11) Delineated 100-foot horizontal greenway along designated trout streams, where applicable.

(12) Location of erosion and sediment control measures using coding symbols from the Manual for Erosion and Sediment Control in Georgia.

d. Maintenance of all soil erosion and sediment control measures, whether temporary or permanent, shall be at all times the responsibility of the property owner.

2.4.3. GRADING PLAN

a. Grading plans shall identify existing and proposed topographic contour lines at the interval required for erosion and sediment control plans, above.

b. Grading plans shall outline any area that is required to remain undisturbed, such as a natural buffer (see “buffers” and Article 6) or greenway (see “greenways” under Article

6) and shall identify and describe the protective fencing or staking to be placed surrounding such area.

c. If the property contains any area of special flood hazard (the 100-year flood plain), grading plans in and around the flood plain shall be designed in conformance to all requirements relating to Flood Damage Prevention under Article 6 of this Development Code.

2.4.4. BUFFER PLAN

A buffer plan shall be prepared for any structural buffer required in accordance with the specifications and standards contained in Article 6 of this Development Code. Plans shall not be required for natural buffers, which are to be shown on the grading plan. The plan shall show:

a. All grading and construction details for earthen berms, walls and fences that are proposed as part of the visual screen.

b. A planting plan showing the location and type of proposed plant materials.

c. Typical cross-sections of the buffer illustrating the improvements proposed and typical location of vegetation. At least one cross-section shall be provided for each.

2.5. DEVELOPMENT PERMIT

2.5.1. RESPONSIBILITY

a. No person shall conduct any pre-construction, land-disturbing and/or development activity involving more than 0.4 acres without first obtaining a development permit from the Chief Building Official to perform such activity, unless exempted under other sections of this code. (See Article 6.13.)

b. Any person proposing development shall first submit to the Building Inspection Department an application for a Development Permit, including all civil design and construction drawings required by this Development Code.

c. The Building Inspection Department is responsible for administering and coordinating the review process for issuance of development permits. The Building Inspection Department shall forward a copy of the Development Permit application, including the civil design and constructions drawings for the project, to the Planning Department, Public Works Department and other departments, the Soil and Water Conservation District, the Georgia Department of Transportation or others as appropriate, for their review and comment. The Building Inspection Department shall provide all comments to the applicant for resolution, and shall issue the Development Permit when all requirements of this Development Code are met.

d. Approval of plans by the City or County shall not imply or transfer acceptance of responsibility for the application of the principles of engineering, architecture, landscape architecture or any other profession, from the professional, corporation or individual under whose hand or supervision the plans were prepared.

e. The completion of inspections and authorization for work continuation shall not transfer responsibility for the quality of the work performed or materials used from the owner, nor imply or transfer acceptance of responsibility for project design or engineering from the professional, corporation or individual under whose hand or supervision the plans were prepared.

f. No development permit shall be interpreted to relieve any owner of the responsibility of maintaining full compliance with all applicable codes, ordinances, and other regulations.

Any development permit issued in error or in contradiction to the provisions of this Development Code shall be considered to have been null and void upon its issuance.

g. Liability

(1) The approval of an erosion and sediment control plan or other plans under the provisions of this Development Code, the issuance of a development permit, or the compliance with any other provisions of this Development Code shall not relieve any person from the responsibility for damage to any person or property otherwise imposed by law nor any liability upon the Governing Body or the Coosa River Soil and Water Conservation Commission for damage to any person or property.

(2) The fact that any activity for which a development permit has been issued results in injury to the property of another shall neither constitute proof of nor create a presumption of a violation of the standards provided for in this Development Code or of the terms of the Development Permit.

2.5.2. DEVELOPMENT ACTIVITIES AUTHORIZED

A development permit shall be issued to authorize all activities associated with development activity regulated by this Code, including, but not limited to, clearing and grubbing, grading and the construction of such improvements as streets, surface parking areas and drives, storm water drainage facilities, sidewalks, or other structures permanently placed on or in the property except for buildings, signs, or other structures requiring the issuance of a building permit.

2.5.3. PROCESS FOR APPROVAL OF DEVELOPMENT PERMIT

An application for a development permit may proceed simultaneously with an application for site plan approval, but may not be issued prior to project approval of such plan by the Building Inspection Department.

a. The application for a Development Permit shall be submitted to the Building Inspection Department and must include the following:

(1) Application for a development permit shall be submitted to the Building Inspection Department, requesting review for issuance of a Development Permit.

(2) Six copies of:

(a) The civil design and construction drawing prepared in conformance with the specifications and standards in this Development Code.

(b) Site plan requesting or reflecting project approval by the Building Inspection Department.

(3) Payment of any Development Permit fee, as established from time to time by the Governing Body.

b. The application will be checked for completeness within 5 business days of its submission. Incomplete applications will be returned to the applicant.

c. Upon receipt of a complete Development Permit application, the Building Inspection Department shall refer the soil erosion and sediment control plan to the Coosa River Soil & Water Conservation District for its review and approval or disapproval concerning the adequacy of the erosion and sediment control plan. No Development Permit will be issued unless the plan has been approved by the District, and any variances and bonding, if required, have been obtained.

d. The applicant may be required by the Building Inspection Department to secure development approval from other agencies if they are affected by the development.

Development approval may be required from but not limited to:

(1) The Planning Department

(2) The Public Works Department

(3) The Public Utilities Department

(4) Fire Department

(5) County Health Department

(6) Coosa River Soil and Water Conservation Commission District

(7) Georgia Department of Transportation

(8) Georgia Department of Natural Resources

(9) U.S. Army Corps of Engineers

(10) U.S. Environmental Protection Agency

e. Upon receipt of comments from other departments, the Building Inspection Department shall forward all comments related to compliance with this Development Code, conditions of zoning approval, and other regulations or ordinances, as appropriate.

f. The applicant shall be responsible for compliance with all codes, regulations and zoning requirements and for the satisfaction of all of the comments received from the various departments and agencies.

2.5.4. REQUIRED PERFORMANCE SURETY.

a. If the applicant has had two or more violations of previous development permits, the Development Code or the Georgia Erosion and Sedimentation Act, as amended, within three years prior to the date of filing of the application under consideration, the Chief Building Official shall refer the Development Permit to the Governing Body.

(1) The Governing Body may deny the Development Permit application; or,

(2) The Governing Body may require the applicant to post a performance bond in the form of government security, cash, irrevocable letter of credit or any combination thereof up to, but not exceeding, $3,000.00 per acre (or fraction thereof) of the proposed land-disturbing activity, prior to issuing the Development Permit. If the applicant does not comply with this Development Code or with the conditions of the Development Permit after issuance, the Governing Body may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land disturbing activity and bring it into compliance.

2.5.5. ISSUANCE OF DEVELOPMENT PERMIT

a. Following satisfaction of all comments, receipt of approvals from all affected agencies and receipt of all bonds, the Chief Building Inspector shall issue a Development Permit authorizing development activities to begin based on the approved civil design and construction drawings.

b. No Development Permit shall be issued unless the erosion and sediment control plan has been approved by the Coosa River Soil and Water Conservation District and has been affirmatively determined that the plan is in compliance with all requirements of this Development Code. If the Development Permit is denied, the reason for denial shall be furnished to the applicant. (See Article 6.13.)

c. If the tract is to be developed in separate and distinct phases, then a separate Development Permit may be required for each phase. (See Article 6.13.)

d. The Development Permit may be suspended, revoked, or modified as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in title is not in compliance with the approved erosion and sediment control plan or that the holder or his successor in title is in violation of this Development Code. A holder of a Development Permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the Development Permit. (See Article 6.13.)

2.5.6. EXPIRATION OF DEVELOPMENT PERMIT

a. A Development Permit shall expire if the development activity described in the permit is not begun within 6 months from the date of issuance.

b. The Chief Building Inspector may renew any development permit that has expired with the concurrence of the respective Public Works Department, within 6 months of expiration. If a Development Permit has expired for more than 6 months, the applicant shall be required to apply for a new Development Permit under the Development Permit approval process of this Development Code.

2.6. FLOOD AREA PERMIT

2.6.1. PERMIT REQUIRED

If development or construction is proposed within or affecting an area of special flood hazard, approval of a flood area permit application shall be required. An application for a flood area permit may be included with and reviewed as part of a Development Permit application.

2.6.2. APPLICATION PROCESS FOR A FLOOD AREA PERMIT

a. Application for a flood area permit shall be made to the Building Inspection Department on forms furnished by them prior to any development activities.

b. The application for a flood area permit is to include the following:

(1) Plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in question.

(2) Location of existing or proposed structures, fill, storage or materials and drainage materials.

(3) Elevation in relation to mean sea level of the proposed lowest floor, including basement, of all buildings.

(4) Elevation in relation to mean sea level to which any nonresidential building will be flood-proofed.

(5) Certificate from a registered professional engineer or architect that any nonresidential flood-proofed building will meet the flood-proofing criteria in Article 6 of this Development Code.

(6) Description of the extent to which any watercourse will be altered or relocated as a result of proposed development.

c. An application for a flood area permit shall be processed in the same manner as a Development Permit.

2.7. DRIVEWAY APPROVAL

a. No curb shall be changed or removed, and no driveway connected to a public street, or on, or across a public right-of-way, or public property shall be repaired or installed without first having the written approval of the Public Works Department.

b. Applications may be made at the Public Works Department.

c. Approval shall expire for work not started within 90 days or completed within 6 months of the date of approval.

2.8. BUILDING PERMITTING

2.8.1. APPROVAL OF TECHNICAL CODES AND SUPPLEMENTS FOR

ENFORCEMENT

The building codes adopted and enforced by the City of Rome and Floyd County shall include those mandated by the State of Georgia; and may include those approved by the State. Building Codes may be revised from time to time as mandated or approved by the State.

2.8.2. PROCEDURES TO OBTAIN A BUILDING PERMIT

A building permit issued by the Chief Building Official is required in advance of the initiation of construction, erection, moving or alteration of any building or structure unless such construction, erection, moving or alteration is exempted from permitting requirements by the Building codes that have been adopted and are enforced by the City of Rome and Floyd County. No building permit shall be issued and no building shall be erected on any lot in the city or county unless access has been established in accordance with this Development Code. No building permits shall be issued before approval of the final plat. All structures shall comply with the requirements of this Development Code, whether or not a building permit is required.

a. Procedure for approval.

The Chief Building Official shall be responsible for administering and enforcing the Building Codes of the City and County.

(1) Prior to issuance of a building permit the owner shall have received a Development Permit if required by this Development Code.

(2) Zoning verification shall be obtained from the Planning Department. The following shall be attached to the Zoning Verification Application:

(a) For a single-family detached or two-family dwelling, a plat of the lot showing the outline of the principal building and minimum building setback lines for the lot or an affidavit signed by the owner and stating that the site complies with the provisions of this Code concerning the placement of the dwelling

(b) For multi-family or nonresidential building, the site plan upon which was granted project approval by the Planning Commission.

(c) A street address number assigned by the appropriate local government department as required by 43-4-14 Official Code of Georgia Annotated.

(3) Application for a building permit shall be made to the Chief Building Official. The application shall include.

(a) Application on the form furnished by the Chief Building Official, requesting issuance of a building permit.

(b) A copy of the zoning verification approved by the Planning Department.

(c) Two sets of building plans for principal multi-family or non-residential buildings prepared in conformance with this Development Code and the applicable building codes. Plans shall be prepared by or under the supervision of, or reviewed and approved by, an architect registered in Georgia, who shall sign and seal each sheet in the original set of drawings.

(d) The Governing Body has allowed County Health Department approval if an onsite sewage disposal system.

(e) Payment of the building permit application and review fee.

(f) Water meter receipt issued by the appropriate local department.

(g) For applications to move a site-built house, structure or building, the following additional information is required:

1) The name of the person performing the moving;

2) The origin and destination of the moving;

3) The names of the owners of the property from which the structure is removed and of the property to which it is moved;

4) A detailed outline of the route to be followed and the equipment to be used;

and

5) An estimate of the time involved, including time of the day when said operation shall be conducted.

6) Any application for a permit must be made at least 48 hours prior to the proposed moving.

7) In addition to a fee charged for permits, the mover of any site-built house, building or structure shall deposit with the Chief Building Official $400.00 for each structure, to be returned to the mover within 5 days after such moving if no damage is done to public property.

8) The Chief of Police shall furnish a police escort if he deems it necessary.

(4) The Chief Building Official will check the application for completeness at the time of submission. Incomplete applications will be returned to the applicant.

(5) For multi-family and non-residential buildings, within 2 weeks following receipt of a complete application, the Building Official shall indicate on 1 copy of the building plans or in writing all comments related to compliance of the building plans with this Development Code, applicable building codes, and any conditions of zoning approval.

(6) The owner shall be responsible for compliance with this Development Code and all building code requirements, regulations, and for the satisfaction of all of the comments of the Building Official.

(7) At such time as the owner has addressed the comments to the satisfaction of the Building Official and the State Fire Marshall, a building permit shall be issued for the structure.

(8) Plumbing, electrical and mechanical permits shall be issued separately by the Building Official or separately identified on the building permit. Such permits must be issued prior to commencement of work by each affected trade.

b. Standards for approval.

(1) Building permits shall be issued only on buildable lots of record, as defined in this Development Code.

(2) Building permits shall be issued in conformance with the adopted technical codes and supplements that constitute the Building Code and with this Development Code.

2.8.3. CERTIFICATE OF OCCUPANCY

a. It shall be unlawful to use or occupy or permit the use of any building, or structure, or premises, or part thereof hereafter created, erected, changed, converted, or wholly or partly altered or enlarged in its use or structure, until a certificate of occupancy shall have been issued stating that the building or structure or premises conforms to the requirements of the building codes and this Development Code.

b. If the property is served by an on-site sewage disposal system, the Certificate of Occupancy shall not be issued by the Chief Building Official until the Health Department has approved a septic tank and in return notifies the Chief Building Official that the system installed meets the County Health Department’s standards.

c. A temporary certificate of occupancy may be issued for a period not to exceed 6 months during alterations or partial occupancy of a building or structure pending its completion, provided that such temporary conditions and safeguards as will protect the safety of the occupants and the public are in place.

d. A certificate of occupancy shall be required for any of the following:

(1) Occupancy and use of a building or structure constructed or enlarged.

(2) Change in use of existing buildings to uses of a different classification.

(3) Any change in use of a nonconforming use, lot or structure.

(4) Permanent electric power may not be supplied to any structure until a Certificate of Occupancy has been issued. Electrical service shall be supplied by a temporary meter pack to be installed on the permanent meter socket until all phases of inspections have been satisfactorily completed.

e. A record of all certificates of occupancy shall be maintained by the Building Inspection Department and a copy shall be furnished upon request to any person.

2.9 BUILDING CONSTRUCTION

2.9.1. BUILDING PERMIT REQUIRED

a. Building permits for all structures or interior finishes are issued after meeting the applicable requirements of the fire prevention and life safety code and the various health and building codes. A permit is also required for the movement of any site-built house, structure or building.

b. For any structure served by an on-site sewage disposal system, a permit issued by the Floyd County Health Department shall be required prior to issuance of a Building permit.

Said permit may first require approval by the Floyd County Health Department of a plan showing the location of the sewage disposal system and other on-site improvements, in accordance with their regulations.

c. Building permits shall only be issued on lots of record, as defined in this Development Code.

2.9.2. BUILDING INSPECTION

a. Inspections shall be scheduled with the Chief Building Inspector at least 24 hours before the inspection is needed for all foundations and footings, and 48 hours prior to all other inspections. Requests for inspection should include the street address, lot number, building permit number, and type of inspection.

b. Required Inspections:

(1) Foundation. Verify minimum required building and setbacks, footing, trenches dug and reinforcing steel in place.

(2) Plumbing Connections. Water supply line and sewer lateral in slab foundation.

(3) Framing. Completion of all rough-ins and insulation is installed.

(4) Interior walls may not be covered until the following inspections are completed:

(a) Mechanical. Rough-ins complete with pressure test on gas line.

(b) Electrical. Rough-ins with neutral, ground, and service cable wired are completed.

(c) Plumbing. Rough-ins complete and all fixtures installed.

(d) Other inspections are completed as required by the Building Inspection Department as necessary to ensure compliance with all applicable codes.

(5) Final Inspection. Building is complete and ready to occupy.

2.9.3. CONSTRUCTION IN FLOOD AREA

Construction of a building for which a flood area permit was issued shall be governed by the following:

a. Upon placement of the lowest floor, or flood proofing by whatever construction means, or upon placement of the horizontal structural members of the lowest floor, whichever is applicable, it shall be the duty of the Development Permit holder to submit to the Chief Building Inspector a certification of the elevation of the lowest floor, flood proofed elevation, or the elevation of the lowest portion of the horizontal structural members of the lowest floor, whichever is applicable, as built, in relation to mean sea level.

b. Certification shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by such registered land surveyor or professional engineer. When flood proofing is utilized for a particular building, the certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by the professional engineer or architect.

c. Any work undertaken prior to submission of the certification shall be at the Development Permit holder’s risk.

d. The Chief Building Inspector shall review the floor elevation survey data submitted. The Development Permit holder immediately and prior to further progressive work being permitted to proceed shall correct deficiencies detected by such review. Failure to submit the survey or failure to make the corrections shall be cause to issue a stop-work order for the project.

2.10. TEXT AMENDMENTS

The Rome-Floyd County Development Code may be amended from time to time in whole or in part under the provisions of this section. For an amendment having application in both the city and the county to become effective, the Governing Bodies of both the City and County must approve it. For an amendment having on its face application only in the city to become effective, the Governing Body of the City only must approve it. For an amendment having on its face application only in the county to become effective, the Governing Body of the County only must approve it.

2.10.1. INITIATION

A Governing Body or the Planning Commission may initiate a proposed change to the text of the Rome-Floyd County Development Code by a majority vote of those voting.

2.10.2. TEXT AMENDMENT PROCESS

Before the Governing Bodies may take final action on a proposed text amendment, the Planning Commission shall hold a public hearing on the proposal.

a. Public Notice.

The public shall be notified of any proposed text amendments in the following manner.

(1) At least 15 days, but not more than 45 days prior to the public hearing, notice shall be given in a newspaper of general circulation within the county. The Planning Department shall prepare such notice, which shall state the time, place, and purpose of the hearing.

(2) For overlay district text amendments, the Planning Department shall give notice to each property owner, as such names and addresses appear on the County’s ad valorem tax records, whose property lies within the boundaries of such overlay district. The notice shall be mailed at least 5 days prior to the hearing and shall state the nature of the proposed amendment; and the time and place of the hearing.

b. Planning Commission Public Hearing.

The public hearing held by the Planning Commission for a text amendment shall be conducted in the following manner:

(1) The Chairperson, the Vice-Chairperson, or the Planning Commission’s designee, who shall act as the Presiding Official, shall convene the public hearing at the scheduled time and place.

(2) The Presiding Official shall call for each proposed text amendment to be presented to the Planning Commission.

(3) No person in attendance shall speak unless first formally recognized by the Presiding Official. Upon rising to speak each person shall state his or her name and home address. The Presiding Official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed text amendment. No less than 10 minutes shall be provided for all those speaking in support of a text amendment and no less than 10 minutes shall be provided for all those speaking against, unless such proponents or opponents take less time than the minimum allowed. Each side shall be afforded an equal minimum time period for presentation of data, evidence, and opinion.

(4) Following the public hearing on each text amendment, the Planning Commission at that time shall make its recommendation or take such other action as may be appropriate.

(a) A motion to recommend approval that receives an affirmative vote from a majority of the voting members present will be forwarded to the Governing Body as a recommendation for approval. A motion to recommend approval that receives a negative vote from a majority of the voting members present will be forwarded as a recommendation for denial, unless another motion receives a majority vote to approve.

(b) A motion to recommend denial that receives an affirmative vote from a majority of the voting members present will be forwarded to the Governing Body as a recommendation for denial. A motion to recommend denial that receives a negative vote from a majority of the voting members present will be forwarded as a recommendation for approval, unless another motion receives a majority vote to deny.

(c) A tie vote on a motion will be forwarded to the Governing Body as no recommendation with the actual vote transmitted.

(d) If no action is taken on an amendment, it will go forward to the Governing Body with no recommendation.

(e) A motion to postpone that receives an affirmative vote from a majority of the voting members present will result in action of the text amendment being deferred for a period of time as specified by the members of the Planning Commission.

However, where the governing body has initiated a text amendment, the planning commission shall act on the text amendment by the date specified by the governing body. At the discretion of the chair, a postponed text amendment request may be considered at a specially called meeting.

c. Governing Body Public Hearing.

(1) Each Governing Body shall conduct a public hearing to consider a text amendment at no later than its second scheduled meeting following the public hearing of the Planning Commission, except that no public hearing or vote shall be conducted by the County where the proposed amendment has on its face application only in the city, and no public hearing or vote shall be conducted by the City where the proposed amendment has on its face application only in the county.

(2) The Chairperson of each Governing Body or another person designated by the Governing Body shall act as Presiding Official.

(3) The Presiding Official shall submit each proposed amendment to the Governing Body. The Presiding Official shall read the recommendation of the Planning Department and shall present such other documentation, as he may deem pertinent.

(4) No person in attendance shall speak unless first formally recognized by the Presiding Official. Upon rising to speak each person recognized shall state his or her name and home address. The Presiding Official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed text amendment. No less than 10 minutes shall be provided for all those speaking in support of a text amendment and no less than 10 minutes shall be provided for all those speaking against, unless such proponents or opponents take less time than the minimum allowed. Each side shall be afforded an equal minimum time period for presentation of data, evidence, and opinion.

(5) During the public hearing, the members of the Governing Body may ask questions at any time. Time devoted to questions and answers will not be counted against any time limitations that have been imposed on presentations.

(6) Following the public hearing on the text amendment (or at the second reading), action shall be considered by vote of the Governing Body.

(a) A motion to approve or deny an amendment must be approved by an affirmative vote of at least a quorum of the members in order for the motion to be approved.

(b) If a motion to approve an amendment fails, the amendment is automatically denied. If a motion to deny an amendment fails, another motion would be in order.

(c) A tie vote on a motion for approval of an amendment shall be deemed a denial of the amendment. A tie vote on any other motion shall be deemed to be no action, and another motion would be in order.

(d) If no action is taken on an amendment, it shall be considered tabled and action deferred to the next regular meeting of the Governing Body.

(7) In taking action on an amendment, each Governing Body may:

(a) Approve, approve with changes, or deny the proposal; or

(b) Table the proposal for consideration at its next scheduled meeting; or,

(c) Refer the amendment back to the Planning Commission for further consideration.

d. Referral to Planning Commission for Further Consideration.

If the Governing Body refers an amendment back to the Planning Commission for further study:

(1) The Planning Department shall give public notice of the Planning Commission’s hearing for further consideration in the same manner as described above, and the Planning Commission shall conduct its additional public hearing and take action as described above.

(2) After the Planning Commission’s rehearing and recommendation on the referred amendment, the Governing Body shall follow the same procedure set forth above to consider the amendment.

2.10.3. STANDARDS FOR TEXT AMENDMENTS

The Planning Commission and each Governing Body shall consider the following standards in considering any proposal that would result in a change to the text of this Development Code, giving due weight or priority to those factors that are appropriate to the circumstances of each proposal:

a. Is the proposed amendment consistent with the purpose and intent of this Development Code as stated under Article 1?

b. Does the proposed amendment further, or is it compatible with the purpose and intent of the Comprehensive Plan?

c. Is the proposed amendment required to adequately address new or changing conditions or to properly implement the Comprehensive Plan?

d. Does the proposed amendment reasonably promote the public health, safety, morality, or general welfare?

2.10.4. EFFECT

a. Approval of a text amendment having application in both the city and the county shall be in full force and effect upon its approval by the Governing Bodies of both the City and the County or upon the stated effective date thereof, and shall thereupon apply to every property for which a use has not been established or for which a building permit or development permit may be subsequently requested. Approval of a text amendment having on its face application only in the city shall be in full force and effect upon its approval by the Governing Body of the City, or upon the stated effective date thereof and shall thereupon apply to every property in the city for which a use has not been established or for which a building permit or development permit may be subsequently requested. Approval of a text amendment having on its face application only in the county shall be in full force and effect upon its approval by the Governing Body of the County, or upon the stated effective date thereof and shall thereupon apply to every property in the county for which a use has not been established or for which a building permit or development permit may be subsequently requested.

b. For a property on which a use, building, structure, or other improvements existed in conformity with this Development Code prior to the effective date of a text amendment affecting the property, any such use, building, structure or other improvements no longer in conformance shall be governed under the provisions for nonconformities in Article 1 of this Development Code.

c. Construction of any use, building, structure, or other improvements for which a building permit has been issued in conformity with this Development Code prior to the effective date of a text amendment may continue to completion as though no change had occurred and, upon completion, shall be governed under the provisions for nonconformities in Article 1 of this Development Code, as applicable.

2.11. APPEALS

2.11.1. TYPES OF APPEALS

Persons may appeal to the Board of Adjustment for relief under the following circumstances:

a. When aggrieved by an action or an interpretation of an administrative official made under this Development Code.

b. When an exception is desired for a particular property from a certain requirement of this Development Code, as specified in this Section.

c. When compliance with the requirements of this Development Code would create a particular and unique hardship.

d. When the requirements for flood protection affect an historic structure.

2.11.2. INITIATION

a. All requests for relief shall be taken as an appeal to the Board of Adjustment, as provided in this Section.

b. If denied, an application for a hardship variance or special exception affecting the same property shall not be considered for a period of 12 months from the date of denial;

provided, however, that the Board of Adjustment may reduce the waiting period under extenuating circumstances or on its own motion.

2.11.3. APPEALS OF AN ADMINISTRATIVE DECISION

a. Appeals of an administrative decision to the Board of Adjustment may be initiated by any person aggrieved, or by an officer or department head of the City or County. Such appeal shall be initiated within 15 days of the action, or decision appealed from, by filing with the Chief Building Official a notice of said appeal specifying the grounds thereof.

b. The holder of or applicant for a Development Permit or a building permit may appeal any of the following actions taken by an administrative official:

(1) The suspension, revocation, modification or grant with condition of a Development Permit by the Chief Building Official upon finding that the holder is not in compliance with the approved erosion and sediment control plan or other approved plans.

(2) The determination by the Chief Building Official that the holder is in violation of Development Permit or building permit conditions.

(3) The determination by the Chief Building Official that the holder is in violation of any other provision of this Development Code.

c. Interpretations.

The Board of Adjustment, upon appeal of an aggrieved party or at the request of the Chief Building Official shall:

(1) Interpret the use of words or phrases within the context of the intent of this Development Code as pertinent to their jurisdiction.

(2) Determine the boundaries of the various zoning districts where uncertainty exists.

(3) Decide appeals from any order, determination, decision or other interpretation by the Chief Building Official or other person acting under authority of this Development Code, where a misinterpretation or misapplication of the requirements or other provisions of this Development Code are alleged.

(4) Interpret such other provisions of this Development Code as may require clarification or extension in specific or general cases.

d. An appeal of an administrative decision stays all legal proceedings in furtherance of the action appealed from, unless the officer or department head from whom the appeal is made certifies to the Board of Adjustment, after the notice of appeal shall have been filed, that by reason of facts stated in the certificate a stay would cause imminent peril to life or property. In such case, proceedings shall not be stayed otherwise than by a restraining order which must be granted by a court of competent jurisdiction.

e. A decision of the Board of Adjustment shall be final unless the aggrieved party requests an appeal before and/or adjudication by the City or County Attorney in an effort to resolve appeals, prior to going to court. Only a court of competent jurisdiction may hear such appeals.

2.11.4. SPECIAL EXCEPTIONS

a. General limitations on relief.

Special exceptions shall be limited to relief from the following requirements of this Development Code:

(1) Minimum building setbacks.

(2) Maximum building height.

(3) Minimum lot width.

(4) Public street frontage.

(5) Buffers and screening.

(6) Signage, in accordance with a uniform sign plan.

(7) Parking requirements.

b. Standards for approval.

A special exception may be granted upon a finding that the relief, if granted, would not cause substantial detriment to the public good or impair the purpose and intent of the Development Code.

c. If denied, an application for a special exception affecting the same property shall not be reconsidered for a period of 12 months from the date of denial; provided, however, that the Board of Adjustment may reduce the waiting period under extenuating circumstances or on its own motion.

d. In no case shall a special exception be granted from the conditions of approval imposed on a property through a zoning change granted by the Governing Body.

2.11.5. HARDSHIP VARIANCES

a. General.

(1) Relief from the application of the provisions of this Development Code may be granted by the Board of Adjustment upon a finding that compliance with such provision will result in a hardship to the property or owner that is substantially unwarranted by the protection of the public health, safety, or general welfare, and the need for consistency among all properties similarly zoned.

(2) Such relief may be granted only to the extent necessary to alleviate such unnecessary hardship and not as a convenience to the applicant nor to gain any advantage or interest over similarly zoned properties.

b. Standards for approval.

A hardship variance may be granted in whole or in part, or with conditions, in such individual case of unnecessary hardship upon a finding by the Board of Adjustment that:

(1) There are extraordinary and exceptional conditions pertaining to the particular piece of property in question because of its size, shape, or topography; or,

(2) The application of the Development Code to this particular property would create an unnecessary hardship; or,

(3) There are conditions that are peculiar to the property which adversely affect its reasonable use or usability as currently zoned.

c. If denied, an appeal for a hardship variance affecting the same property shall not be reconsidered for a period of 12 months from the date of denial; provided, however, that the Board of Appeals and Adjustments may reduce the waiting period under extenuating circumstances or on its own motion.

d. In no case shall a hardship variance be granted for any of the following:

(1) A condition created by the applicant, including the result of an unwise investment decision or real estate transaction.

(2) A change in the conditions of approval imposed through a zoning change granted by the Governing Body.

(3) Reduction of a minimum lot size required by a zoning district.

(4) A use of land or building or structures that is not permitted by the zoning district that is applicable to the property.

(5) Any increase in the number of dwelling units or nonresidential building floor area otherwise permitted by the zoning district that is applicable to the property.

2.11.6. FLOOD PROTECTION VARIANCES

a. Flood protection variances may be approved for the reconstruction, rehabilitation, or restoration of a building listed on the National Register of Historic Places or the State Inventory of Historic Places provided that the proposed reconstruction, rehabilitation, or restoration will not result in the building losing its historical designation.

b. In passing a flood protection variance, the Board of Adjustment shall consider all technical evaluations, all relevant factors, all standards specified in other sections of this Development Code relating to flood damage prevention, and the:

(1) Danger that materials may be swept onto other lands to the injury of others;

(2) Danger to life and property due to flooding or erosion damage;

(3) Susceptibility of the facility and its contents to flood damage and the effect of such damage on the individual owner;

(4) Importance of the services provided by the facility to the community;

(5) Necessity of the facility to a waterfront location, in case of a functionally dependent facility;

(6) Availability of alternative locations, not subject to flooding or erosion damage, for the proposed use;

(7) Compatibility of the use with existing and anticipated development;

(8) Relationship of the use to the comprehensive plan and flood plain management program for that area;

(9) Safety of access to the property in times of flood for ordinary and emergency vehicles;

(10) Expected heights, velocity, duration, rate of rise and sediment transport of the flood waters and the effects of wave action, if applicable, expected at the site; and

(11) Costs of providing governmental services during and after flood conditions, including maintenance and repair of public utilities and facilities such as sewer, gas, electrical and water systems, and streets and bridges.

c. Upon consideration of the factors listed above, and the purposes of this Development Code, the Board of Adjustment may attach such conditions to the granting of the variance as it deems necessary to further the purposes of flood damage prevention.

d. Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result.

e. Conditions for variances are as follows:

(1) Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief; and in the instance of a historical building, a determination that the variance is the minimum necessary so as not to destroy the historical character and design of the building.

(2) Variances shall only be approved upon:

(a) Showing of good and sufficient cause;

(b) Determination that failure to grant the variance would result in exceptional hardship; and

(c) Determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expenses, create nuisances, cause fraud on or victimization of the public, or conflict with existing laws or Development Codes.

(3) Any applicant to whom a variance is granted shall be given written notice specifying the difference between the base flood elevation and the elevation to which the building is to be built and stating that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation.

(4) The Chief Building Official shall maintain the records of all appeal actions and report any variances to the Federal Emergency Management Agency upon request.

2.11.7. PROCESS FOR GRANTING APPEALS

a. Upon receiving a notice of an appeal, the Chief Building Official shall assemble such memos, papers, plans, or other documents as may constitute the record for the appeal or as may provide an understanding of the issues involved.

b. An application for an appeal shall include such descriptions, maps or drawings as needed to clearly illustrate or explain the action requested. The Chief Building Official may request such additional information from the appellant as necessary to provide a full understanding of the appellant’s request.

c. Once the record has been assembled, Chief Building Official shall schedule the appeal for consideration at the next scheduled Board of Adjustment for which adequate public notice can be given.

d. Public Notice.

(1) Notification to the General Public.

(a) At least 15 days, but not more than 45 days, prior to the public hearing, notice shall be published in a newspaper of general circulation within the county. The Building Inspection Department shall prepare such notice, which shall state the time, place, and purpose of the hearing.

(b) A request for a special exception, hardship variance, or flood protection variance shall be heard at a public hearing only upon:

1) The published notice, in addition to the requirements above, shall include the location of the property, the present zoning classification of the property, and the nature of the requested action; and

2) At least 15 days prior to the public hearing, the Chief Building Official shall post a sign or signs of not less than 6 square feet stating “Zoning Action Pending. For further information please contact the Rome-Floyd County Planning Department at (phone number) or (e-mail address).”One such sign shall be placed in a conspicuous location along each street frontage of the subject property. If the property has no street frontage, the sign shall be placed on each street from which access will be gained to the property.

(2) Notice to Surrounding Property Owners.

If the request is for a special exception, hardship variance, or flood protection variance, notice shall also be given to surrounding property owners as follows:

(a) At least 5 days prior to public hearing, the Chief Building Official shall cause a notice to be mailed to all persons owning property located adjacent to or across the street from the property that is the subject matter of the request.

(b) The notice shall state the time, place, and purpose of the hearing by the Board of Appeals and Adjustments. The written notice shall be mailed to the property as such names and addresses appear on the County’s ad valorem tax records.

e. Any appellant wishing to withdraw an appeal prior to the meeting of the Board of Adjustment shall file a written request for such withdrawal with the Chief Building Official. The appeal shall thereupon be removed from the Board’s agenda and the request shall have no further effect.

f. Board of Adjustment Public Hearing.

(1) The Chairperson, Vice-Chairperson, or the Board of Adjustments’ designee, who shall act as the Presiding Official, shall convene the public hearing at the scheduled time and place.

(2) The Presiding Official may administer oaths and compel the attendance of witnesses by subpoena.

(3) The Chief Building Official shall submit the assembled record of the appeal to the Board of Adjustment. The Chief Building Official, or other appropriate party if the appeal was taken from an administrative action or interpretation, shall provide such information or explanation as appropriate to the circumstances of the appeal.

(4) At the hearing, any party may appear in person or by agent or by attorney. No person in attendance shall speak unless first recognized by the Presiding Official. Upon rising to speak each person recognized shall state his or her name and home address.

The Presiding Official may place reasonable limits on the number of persons who may speak for or against a request, on the time allowed for each speaker, and on the total time allowed for presentation of the request. No less than 10 minutes shall be provided for all of those speaking in support of the request and no less than 10 minutes shall be provided for of those speaking against, unless such proponents or opponents take less time than allowed. If reasonable time limitations permit, any member of the general public may speak at a hearing. However, the appellant and nearby property owners shall be afforded the first opportunity to speak.

(5) The appellant shall be allowed to speak first in order to present the request. Others in support of the request may then speak, followed by those in opposition to the request.

The appellant will then be allowed time for rebuttal. Rebuttal must be limited to points or issues raised by opponents to the request at the hearing.

(6) During the public hearing, the members of the Board of Adjustment may ask questions at any time. Time devoted to questions and answers will not be counted against time limitations that have been imposed on presentations.

(7) At the meeting, following presentation of the appeal, action shall be taken by vote of the Board of Adjustment.

(a) A motion to approve or deny an appeal must be approved by an affirmative vote of at least 3 members in order for the motion to be approved.

(b) If a motion to approve an appeal fails, the appeal is automatically denied. If a motion to deny an appeal fails, another motion would be in order.

(c) A tie vote on a motion for approval of an appeal shall be deemed a denial of the appeal. A tie vote on any motion shall be deemed to be no action, and another motion would be in order.

(d) If no action is taken on an appeal, it shall be considered tabled and action deferred to the next regular meeting of the Board of Adjustment.

(8) In taking action on an appeal, the Board of Adjustment may:

(a) Approve, approve with changes, or deny the request; or,

(b) Table the appeal for consideration at its next scheduled meeting; or,

(c) Allow withdrawal of the appeal at the request of the appellant.

2.12. TEMPORARY SUSPENSION OF PERMITTING

Upon submission of a valid application for a zoning change or for the granting of an appeal on a property, no permits shall be issued nor shall any actions be undertaken on the property that may be affected by the outcome of such application.

Article 3. Zoning Districts

3.1. PURPOSE OF ARTICLE 3

This Article describes the specific uses to which land and structures may be put in the various zoning districts, and includes special requirements in order for certain uses or structures to be allowed. District regulations such as lot size, building setbacks, residential floor area and structure height are included.

3.2. ZONING MAP

3.2.1. OFFICIAL ZONING MAP

a. The boundaries of the various zoning districts shall be shown on a set of parcel specific, tax maps collectively entitled “Zoning Districts Maps, Rome-Floyd County, Georgia” and adopted on the respective dates of adoption for this ordinance, and as subsequently amended thereafter from time to time in conformance with this code.

b. The “Zoning Districts Maps, Rome-Floyd County, Georgia” is adopted as the Official Zoning Map(s) and is hereby made a part of this Code, and all notations, references and other information shown on it shall be a part of this Code.

c. The Official Zoning Map(s), as adopted by the governing body and subsequently amended from time to time by its action, shall be maintained by the Rome/Floyd County Planning Department.

The Official Zoning Map(s) shall be stored and maintained in an electronic database. So stored and maintained, the Official Zoning Map(s) shall be the final authority as to the current zoning status of all land, water, buildings, and structures within the county.

On a quarterly basis the Official Zoning Map(s) shall be printed. All printed maps shall be identified by the following words:

“Zoning District Maps, Rome-Floyd County, Georgia: This is the Official Zoning Map(s) referred to in Article 3.2.1. of the Rome-Floyd County, Georgia, Unified Land Development Code, as of ___________ (date).”

3.2.2. CHANGES TO OFFICIAL ZONING MAP

a. Changes Due to Map Amendment.

No changes of any nature shall be made to the Official Zoning Map(s) except in conformity with amendments to the map approved by the governing body.

b. Changes Due to Annexation.

Where city limit boundaries change by virtue of annexation, the following provisions shall apply:

(1) Land area incorporated through annexation shall retain its existing zoning classification until an application for rezoning is filed for rezoning with the Planning Department.

(2) Any application for a building permit or development permit will be processed in the customary fashion as it would have been prior to annexation.

c. Notification upon Amendment.

Following the approval of a zoning map amendment by the Governing Body, the Clerk shall transmit a copy of the amendment to the Planning Director. If the action was to rezone property, the Planning Director shall cause the Official Zoning Map to be amended to show the change.

3.2.3. INTERPRETATION OF BOUNDARIES

a. The boundaries of the districts as shown on the Official Zoning Map shall be determined on the basis of the legal descriptions associated with approved zoning petitions, or, lacking such legal descriptions, on the basis of the location of the boundary as depicted on the Official Zoning Map along with any dimensions shown.

b. Where uncertainty exists with respect to the boundaries of districts as shown on the Official Zoning Map, the following rules shall apply:

(1) Unless otherwise indicated, the district boundary lines are center lines of streets or railroads or such lines extended, property lines or such lines extended, a line lying in the center of a stream or drainage way, or the city limits of Rome.

(2) Where district boundary line parallels a street right-of-way or discernible topographic feature but no dimension is given, the distance shall be scaled from the Official Zoning Map.

(3) Where a district boundary line divides a lot that is of single ownership at the time of the effective date of this Code, the zoning classification of the larger portion may be interpreted to extend into smaller portion for a distance of no more than 10 feet.

(4) In the event the exact location of a boundary cannot be determined by the foregoing methods, the Board of Adjustment shall, upon application, determine the location of the boundary.

(5) Where a public road, street, alley or other right-of-way is officially vacated or abandoned, the regulations applicable to the property to which it is reverted shall apply to such vacated or abandoned road, street, alley or right-of-way.

3.3. ZONING DISTRICTS

3.3.1. ESTABLISHMENT OF DISTRICTS

a. Zoning districts established:

A-R Agricultural Residential S-R Suburban Residential HT-R High Density Traditional Residential LT-R Low Density Traditional Residential D-R Duplex Residential M-R Multifamily Residential N-O-C Neighborhood Office Commercial O-I Office Institutional C-C Community Commercial C-B-C Central Business Commercial H-C General Heavy Commercial L-I Light Industrial H-I Heavy Industrial U-M-U Urban Mixed Use P-D Planned Development

b. Permitted uses.

Principal and accessory uses permitted by right or as special uses are shown in Section

3.4 – List of Permitted Uses.

c. Density, lot width, setback, and height standards.

Applicable density, lot width and setback standards are contained in Section 3.5 – Lot Size, Density, and Setbacks and Section 3.6 – Structure Heights.

d. Residential cluster overlays, neighborhood office commercial and planned developments.

e. Application and Hearing Procedures Procedures for filing rezoning, subdivision or site approvals are contained in Article 2 – Procedures.

f. Restrictions Regarding Particular Uses.

Applicable standards regarding specific uses, regardless of the zoning district where they are located are contained in Article 4 – Restrictions Regarding Particular Uses.

g. Sign Standards.

Applicable regulations are contained in Article 5 – Sign Regulations.

h. Buffers, Landscaping, Tree Protection and Parking Standards.

Applicable regulations are contained in Article 6 – Subdivision and Project Standards.

i. Construction Development Standards.

Standards regarding site grading, flood hazard areas, erosion control, installation of streets, drainage, public utilities and building construction are contained in Article 6 - Subdivision and Project Standards.

3.3.2. PURPOSE OF ZONING DISTRICTS

a. A-R Agricultural Residential

(1) The A-R Agricultural Residential District is established to provide areas for agricultural and forestry uses and residential development.

(2) Manufactured and mobile homes are permitted with limitations throughout the A-R District outside the City of Rome. A Special Use Permit is required within the City.

b. S-R Suburban Residential

(1) The S-R Suburban Residential District is established for three levels of residential development (in addition to all forms of agricultural crop production and forestry):

(a) In areas where public sanitary sewer and public water are not available, the S-R District is established to provide areas of primarily low density residential development of 1 unit per acre.

(b) In areas where public water is available, but not public sanitary sewer, minimum 20,000 square foot lots are required.

(c) In areas where sanitary sewer and public water are available, the S-R District is established to provide moderately dense, primarily single-family residential development with minimum 7,200 square foot lots.

(2) Manufactured home subdivisions are deemed appropriate in the S-R Residential District within the city and county. Manufactured homes on single parcels outside an established subdivision are permitted in this district except where a Special Use Permit is required:

(a) Within the city; and

(b) Within those portions of the county consisting of a land development project in which two or more lots are created in, along with streets and utilities needed to support construction of buildings on the lots.

(3) Attached single-family dwelling as defined in Article 8 may be considered appropriate as infill development if the design is compatible with the surrounding neighborhood in terms of scale, height, roof pitch, provision of parking, and orientation toward the street. Such development, if approved by Special Use Permit, must meet the standards listed in Article 4.1.28.

c. HT-R High Density Traditional Residential

(1) The HT-R Traditional Residential District is established to provide opportunities for higher density single family residential averaging 4-7 units per acre. The HT-R District development patterns and architectural styles are reflective of the residential neighborhoods established before the 1940’s. Streets were developed along a grid pattern with neighborhoods conveniently located to local shopping areas. Although these are older areas of the community, it is envisioned that this zoning district is also appropriate for new single family development built in this “neo-traditional” style.

(2) Manufactured homes are not considered appropriate in the HT-R District.

(3) Duplexes may be considered appropriate as infill development if the design is compatible with the predominant development pattern of the surrounding neighborhood.

(4) Attached single-family dwelling as defined in Article 8 may be considered appropriate as infill development if the design is compatible with the surrounding neighborhood in terms of scale, height, roof pitch, provision of parking, and orientation toward the street. Such development, if approved by Special Use Permit, must meet the standards listed in Article 4.1.28.

d. LT-R

(1) The LT-R Traditional Residential District is established to provide opportunities for lower density single-family residential averaging 1-4 units per acre. The LT-R District development patterns and architectural styles reflect the residential neighborhoods established before and/or during the 1940’s, 50’s, and early 60’s.

Streets were largely developed along a grid pattern with sidewalks and neighborhoods conveniently located to local shopping areas. Although these are older neighborhoods of the community, it is envisioned that this zoning district is also appropriate for new single-family development built in “neo-traditional” style in accordance with current new urbanism concepts.

(2) Manufactured housing units are not considered appropriate within the Low Density, Traditional Residential District.

(3) Duplexes may be considered appropriate as infill development if the design is compatible with the predominant development pattern of the surrounding neighborhood.

(4) Attached single-family dwelling as defined in Article 8 may be considered appropriate as infill development if the design is compatible with the surrounding neighborhood in terms of scale, height, roof pitch, provision of parking, and orientation toward the street. Such development, if approved by Special Use Permit, must meet the standards listed in Article 4.1.28.

e. D-R Duplex Residential

(1) The Duplex Residential District is established to provide a location for two attached residential units with a maximum density of 10 - 14 units per acre.

(2) The Duplex-Residential District includes only single-family detached, single-family attached, and two-family attached (duplex) residential units.

(3) The Duplex District is intended to allow for an intermediate density of residential that blends easily with nearby single family residential units. Such units, if effectively sited, are deemed to be suitable buffers between single family residence (S-R or T-R) and higher density. Multifamily Residential (M-R), Office/Institutional (O-I), and/or Neighborhood Office Commercial (N-O-C) uses. Attached single-family dwelling as defined in Article 8 may be considered appropriate as infill development if the design is compatible with the surrounding neighborhood in terms of scale, height, roof pitch, provision of parking, and orientation toward the street. Such development, if approved by Special Use Permit, must meet the standards listed in Article 4.1.28.

f. M-R Multi-Family-Residential

(1) The M-R Multifamily Residential District is established to provide a location for attached units with densities of 10-14 units per acre. Multifamily development includes duplexes, triplexes, apartments of 4 units or more, town-homes, condominiums, and manufactured home parks. The M-R district is designed for areas served by publicly provided sanitary sewer.

(2) The M-R District is intended to accommodate higher density attached residential development that blends easily with nearby single-family units. M-R District developments such as duplexes, triplexes, town homes, and low density apartment complexes are considered appropriate in proximity to the S-R and T-R residential districts, if effectively sited, landscaped, buffered, and adequate provisions for access and open space are made.

(3) A wide range of multifamily densities and dwelling types may also be appropriate in large-scale mixed use developments or as a residential re-use option in obsolete commercial centers.

(4) Manufactured home parks are allowed as an M-R District use with restrictions, but are not considered appropriate options in proximity to a single-family subdivision development or as re-use options for commercial properties.

(5) A residential cluster option is a use allowed by Special Use Permit with restrictions in the M-R District, but must meet all development standards and criteria for a multifamily residential development.

g. N-O-C Neighborhood Office Commercial

(1) The N-O-C Neighborhood Office Commercial District is established to accommodate modestly sized professional offices and retail services in close proximity to and in harmony with nearby residential properties.

(2) The N-O-C District is designed for locations where existing residential is no longer the most appropriate use due to conflicts from nearby non-residential uses and traffic.

This district is also appropriate for small-scale retail/office in newly developed planned residential areas.

(3) The N-O-C District recognizes the need to protect adjacent residential uses, thus the basic character of the N-O-C District encourages a compatible mixture of residential, office, and specialty retail types of land uses. This district is identified as one in which the physical character and design of existing and proposed new structures play an important role in assuring compatibility with existing residential development.

Review of building design, uses, buffers, landscaping, lighting, and parking are recognized as essential for the establishment and maintenance of the character of the district. Uses that create issues with noise, traffic, or odors are not permitted in this district.

(4) Areas zoned N-O-C are not intended to be moderate-to-large retail or office centers.

(5) Businesses that prepare and serve food are limited to custom service restaurants that do not create smoke, noise, or undue congestion. No drive-in windows are permitted.

(6) Beauty shops and barber shops in this district shall have no more than two (2) chairs or operator stations. Hours of operation shall be limited to 8: 00 a.m. to 8:00 p.m., Monday through Saturday. Tanning salons, nail care, massage, and skin care services;

boutiques; or other uses customarily associated with beauty shop and barber shops businesses shall not be permitted in this zoning district (NOTE: Adopted by the County, not by the City).

(7) New buildings in the N-O-C District may not exceed 2,500 square feet. However, pre-existing residential structures that exceed this building maximum, may be considered for rezoning to N-O-C,

(8) Uses are limited to services that generate no more than 150 vehicular trips per day.

(9) The residential character and design of existing and proposed new structures are required to be maintained.

(10) No front or side yard parking is permitted.

(11) Review of building design, uses, buffers, lighting, and parking is required. Such reviews shall be accomplished by a Special Review Panel consisting of the Director of Planning, Historic Preservation Director, and Chief Building Official or their designee(s) as required.

(12) Signage shall be in accordance with Article 5-Sign Regulations, and should be designed to have minimal impact on neighboring residential properties.

(13) Window displays or other displays of work are not permitted to be visible from the exterior of the building.

(14) Landscaping similar to that of residential properties between the non-residential and residential uses, or

(15) New structures:

(a) New structures shall utilize the shapes and proportions common to single-family residential architecture as guides to the architectural design, and alterations of or additions to existing structures.

(b) The rhythm or pattern of placement of windows, doors, chimneys, gables, dormers, roof pitch, offsets in the walls, and other elements should also be considered by the Review Panel as in creating residential compatibility.

h. O-I Office Institutional

(1) The O-I Office Institutional District is established to provide for both private and public administrative and professional offices and on sites greater than those permitted in the N-O-C District.

(2) The O-I District is established to provide for institutional uses such as hospitals, clinics, churches, schools, cemeteries, etc., occurring in the more densely developed areas of Rome-Floyd County (the S-R and T-R zoning districts). This is due to the potential for conflicts between the institutional uses and densely developed residential neighborhoods.

(3) Within this district the sale, wholesale, storage or processing of merchandise is not permitted, except as accessory uses to the primary O-I uses. Areas zoned to this classification are not intended to be commercial or industrial centers.

(4) The district is intended primarily to be located along major streets, but it can also be located in an area dominated by institutions such as a college where a wide range of land uses is required.

i. C-C Community Commercial

(1) The C-C Community Commercial District is established to provide a location for a full-range of retail and office development serving the general needs of the community. The C-C District is considered inappropriate for heavier commercial uses that border on being more “light industrial” in nature, and thus more appropriate for the H-C or L-I District.

(2) It is the intent of the C-C District to promote a streetscape that encourages buildings to be moved forward adjacent to the front yard setback line and the edge of the required landscape improvements. This site design improves the benefits derived from the required landscaping and the overall image of the commercial corridor.

j. C-B-C Central Business Commercial

(1) Within C-B-C Central Business Commercial District the most intensive use of land is permitted in combination with a variety of commercial and residential uses. The district is intended to serve as the central headquarters for economic and administrative activity in the community. The district is designed to have uses that are centrally located and compact so that maximum convenience is afforded the users and occupants of the district.

(2) It is the intent of the C-B-C District to be pedestrian friendly. Structured parking is encouraged over surface parking lots. There are no yard setbacks to encourage buildings to locate adjacent to the property line and utilize on-street or structured parking to the greatest extent possible.

(3) In the C-B-C District residential use is encouraged above commercial operations in existing buildings, as well as within new, free-standing high-rise residential buildings.

Commercial store fronts in existing buildings shall be maintained in both form and function and shall not be converted to residential use.

(4) The CBC zoning district may also be used in the unincorporated areas where the availability of water, sewer, transportation routes and other services and utilities make high density, mixed used development possible.

k. H-C Heavy Commercial

(1) The H-C Heavy Commercial District is established to provide for the sales and service of commercial uses that are not considered as compatible with traditional retail sales and services allowed in the C-C District.

(2) Uses within the H-C District border on being more “light industrial” in nature. These are uses such as major car repair or service, auto painting and body shops, construction contractors, large trucks, manufactured home, boat or heavy equipment sales, and retail home improvement stores with outside storage, etc.

l. L-I Light Industrial

(1) The L-I Light Industrial District is intended to provide areas for light manufacturing uses that primarily involve finishing, or assembly of previously manufactured goods.

The district is also intended to provide for the location of wholesaling or warehousing uses, as well as office uses.

(2) The L-I District excludes manufacturing or industrial uses that emit noxious odors, dust, fumes, gas, noise, or vibration outside of any building on the premises. It also excludes hazardous materials such as those materials involving bulk storage of gasoline or toxic chemicals.

(3) This district is designed for industrial and warehousing uses that do not have a detrimental effect upon adjoining residential or commercial developments.

m. H-I Heavy Industrial

(1) The H-I Heavy Industrial District is intended for the location of primarily heavy manufacturing uses with restrictions on noxious odors, dust, fumes, gas, noise, or vibration.

(2) Due to the potential for uses in the H-I District to handle materials that are potentially hazardous, emit smoke, dust or odors, or require large transport services, a 5 acre minimum lot size is required.

n. P-D Planned Development

(1) The P-D Planned Development District is established for two purposes. First it provides a district for addressing specific site and building design issues for and needs created by large scale residential, commercial, office, institutional or industrial uses. Secondly, it allows for more flexible placement, mixture, arrangement and orientation of residential, office institutional, commercial and/or industrial uses. This provides for accompanying flexibility in the subdivision of land and the grouping of open space and accessory facilities.

(2) Uses or developments that are subject to the requirements of the P-D Planned Development District are:

(a) Buildings that exceed 70,000 square feet, this does not include industrial space if the persons employed (b) and the vehicular trips generated (c) per site are not exceeded.

(b) Operations that would employ over 200 persons.

(c) Developments that generate over 10,000 vehicle trips per day.

(d) Residential development involving over 250 units or in excess of 300 acres.

(e) Mixed use developments: developments that desire to provide a mix of residential, office, commercial and/or industrial uses.

(3) Application requirements.

Developments that are subject to the P-D Planned Development District are required to follow normal submission requirements, zoning and subdivision approvals and construction standards as outlined in other sections of the Code.

(4) Site requirements

(a) Single-Purpose Development.

1) Defined: A single purpose development is one that involves only one type of general land category such as retail, industrial, institutional, or residential development. A single purpose development may be one building or multiple buildings.

2) As a requirement of zoning, a single purpose development is required to submit the following information (in addition to that which is required in other sections of the Code).

a) Overall compatibility of development with adjacent land uses.

b) Traffic management plan and a street continuation plan (if applicable).

c) Orientation of building(s) to the public rights-of-way.

d) Parking lot configuration and orientation to the street.

e) Non-residential building(s) exterior treatment and signage plans.

f) Proposed outside storage and treatment of buffers and landscaping.

g) Hours of business operation and service vehicle routing plan.

h) Any other information that is deemed useful in determining the proposed use’s impact on surrounding properties and the community as a whole.

(b) Mixed use developments.

1) Defined. A mixed use development is a development that provides a mix of residential, office, commercial and/or industrial uses under a unified plan of development.

2) Development standards.

a) Overall standards: Lot densities, lot areas, widths, and setbacks are to be established as conditions of zoning approval for each Planned

Development.

b) Residential densities. The maximum dwelling units permitted is 6 units per acre. In calculating permitted residential densities, land devoted to non-residential uses and road rights-of-way may not be included.

However, open space held in common may be included in the calculations of densities.

c) Open space. Within the residential portion of the development, 20% of the land must be preserved in open space, half of which is usable open space for active or passive recreation use. Said open space shall be held in common by a legally constituted homeowners association with the

financial capability to maintain the open space. For the purposes of calculation, open space does not include any public rights-of-way but does not include lakes, walking trails, and active recreation areas.

d) Compatibility. On-site land uses developed at the perimeter of the site shall be developed in a manner that is compatible with adjacent offsite land uses.

e) Enclosure of uses. All uses except off-street parking and loading shall be located and maintained entirely within completely enclosed structures.

3) Protection of residential uses.

Where a mixture of residential and non-residential uses are proposed for a site, or where a non-residential use is proposed on property adjoining a residential use, plans shall provide for protection of the residential use to ensure a suitable living environment.

a) Increased separation between residential and non-residential uses,

b) Placement of parking areas to minimize noise and screen the view of vehicle movements,

c) Use of vegetative screening,

d) Location within the structure or on the lot of a use causing adverse impact so as to minimize the impact,

e) Use of building alterations or special equipment or devices to minimize adverse impacts,

f) Landscaping similar to that of residential properties between nonresidential and residential uses, or

g) Placement of signs to minimize impact of residential uses.

4) Site plan requirements.

a) Mixed use development site plans shall contain the same information requested for single purpose development.

b) In addition to the requirements above, the following are required:

1. Streets rights-of-way,

2. Proposed building sites,

3. Uses proposed for buildings,

4. General drainage improvements.

5. Proposed reservations of dedications for streets and other public facilities, and

6. A contour map of the site.

c) Written report.

A written report, including photographs or other relevant illustrations or information, may be submitted:

1. To explain features that cannot be shown adequately on the site plan;

2. To explain the means by which compatibility between a mixture of uses shall be ensured; or,

3. To illustrate the existing architecture on which the proposed design is based.

o. U. M. U. Urban Mixed Use

(1) The UMU district is established to accommodate intensive development, including infill development, and to provide for relatively high density residential, commercial, and office/institutional uses in a pedestrian friendly, urban environment. The district may be appropriate in areas that are adjacent and peripheral to the CBC district.

(2) The uses allowed in the UMU district are similar to the uses allowed in the CBC district and are shown in Table 3.2.

(3) No building setbacks or landscaping requirements shall apply, and a buffer requirement of no less than 20 feet shall apply only where adjacent properties are zoned for residential uses. The height limitation for structures shall be 100 feet. No minimum lot size or lot width shall apply. Each lot shall abut a street that has been opened and accepted for public maintenance; that has been designated by the City or County as a private street; or whose construction has been guaranteed, as provided under Article 6.4.6 of this Code; for a distance of no less than 26 continuous feet.

(4) In order to efficiently utilize limited land resources, structured parking shall be provided wherever it is feasible. Shared parking arrangements shall be encouraged.

(5) Sidewalks and streetscapes shall be provided along all street frontages to promote attractive, safe, and convenient pedestrian access. Multi-purpose trails or other pedestrian walkways may also be appropriate to ensure connectivity.

(6) Loading areas, material handling areas, and waste containers shall be located, screened or enclosed so that they are not visible from streets, sidewalks and other public areas. The design of such facilities shall be approved by the Building Official.

(7) The UMU zoning district may also be used in the unincorporated areas where the availability of water, sewer, transportation routes and other services and utilities make high density, mixed use development possible.

3.4 LIST OF PERMITTED USES

a. Principal and accessory uses that are permitted by right, permitted by right but with limitations, and uses permitted as special uses are shown on the following tables:

(1) Table 3-1 shows all such uses for the residential and agricultural districts.

(2) Table 3-2 lists all such uses for the districts that are primarily nonresidential in nature.

b. In P-D Planned Development District uses that are permitted are specified as part of the zoning approval for each development.

c. The following permitted uses herein identified and listed are not intended to be exhaustive, but only representative of those uses permitted in each Zoning District. It shall be the responsibility of the Planning Director and Chief Building Official to concur in any additional uses not herein specifically identified as permitted uses. Any use not shown in the following Table of Permitted Uses that cannot be concurred upon shall be brought before the Planning Commission for final resolution, and shall require a Special Use Permit. Uses that are specifically prohibited are listed in Article 4.

List of Permitted Principal and Accessory Uses Table 3-1. Residential and Agricultural Districts Use is permitted by right………………………● Use is permitted by right with limitations.…….♦ Use may be permitted as a Special Use……………○ Use is not permitted……………………space is empty

PRINCIPAL USES A-R S-R HT-R LT-R D-R M-R See Also

Parking - See under 6.86.

Agriculture and Related Business 1 Agricultural Production - Crops ● ● a 2 Agricultural Production - Livestock ● ○ a 2 Agricultural Production - Concentrated Animal Feeding Operations ♦ ○♦ 4.1.1 a 213 Agricultural Production - Hogs ○ 4.1.1 a Riding Stable ♦ ♦ 4.1.1 a Farm Distillery, Brewery, or Winery ○ 4.2.16 7 Agricultural Services (except veterinarian office) ● a 8 Forestry ● ● ● a Portable Sawmill - temporary ♦ ♦ 4.1.1 a Residential a Site-Built Single-Family Detached Dwelling ● ● ● ● ● a Site-Built Single Family Attached Dwelling ○ ○ ○ ● 4.1.28 Mobile Home or Manufactured Home on individual lot ♦1 ♦2 4.1.12 a Two-Family Dwelling (Duplex) ○ ○ ○ ○ ● ● a

Manufactured Home Subdivision ♦ ♦ 4.1.12 a Zero-Lot Line Single-Family Detached Dwelling ● ● ● ● a Multi-Family Dwelling ● a Townhome or Three-Family Dwelling ♦ 4.1.23 a Manufactured Home Park ♦ 4.1.12 a Residential Cluster Development ○ 4.1.32 a 8052 Convalescent Home (1-4 persons) ○3♦ ○♦ ○♦ ○♦ ♦ 4.1.18 a 8052 Convalescent Home (5-15 persons) ○3♦ ○♦ ○♦ ○♦ ♦ 4.1.18 a 8052 Convalescent Home (16 or more persons) ♦ 4.1.18 a Fraternity or Sorority Hall ♦ 4.1.11 a Group Residence (1-4 persons) ○♦ ○♦ ○♦ ○♦ ♦ 4.1.13 a Group Residence (5-15 persons) ○♦ ○♦ ○♦ ○♦ ♦ 4.1.13 a Group Residence (16 or more persons) ♦ 4.1.13 a 8051 Nursing Home (1-4 persons) ○♦ ○♦ ○♦ ○♦ 4.1.18 a 8051 Nursing Home (5-15 persons) ○♦ ○♦ ○♦ ○♦ 4.1.18 a 8051 Nursing Home (16 or more persons) ♦ 4.1.18 a Personal Care Home, Individual or Family (1-4 persons) ♦ ♦ ♦ ♦ ♦ 4.1.13 a 836 Personal Care Home, Group (5-15 persons) ○♦ ○♦ ○♦ ○♦ ♦ 4.1.13 a 836 Personal Care Home, Congregate (16 or more persons) ♦ 4.1.13 a 836 Retirement Community ○♦ ○♦ ○♦ ○♦ ○♦ 4.1.18 a

702 Rooming or Boarding House (1-4 persons) ○♦ ○♦ ○♦ ○♦ 4.1.13 c 702 Rooming or Boarding House (5-15 persons) ○♦ ○♦ ○♦ ○♦ 4.1.13 c 702 Rooming or Boarding House (16 or more persons) ○♦ 4.1.13 c

1 Special use permit also required in the City 2 Special use permit also required in the City, and a special use permit also required in the County within those portions of the County consisting of land development project in which two or more lots are created, along with the streets and utilities needed to support construction of buildings on the lots, except where such development is specifically designed for manufactured homes 3 Where served by sanitary sewer

PRINCIPAL USES A-R S-R HT-R LT-R D-R M-R See Also

Parking - See under 6.86.

Offices Temporary Sales Office for a Subdivision ♦ ♦ ♦ ♦ 4.1.22 b 741 Veterinary, Large Animal ♦ 4.1.25 b 742 Veterinary, Small Animal ♦ ♦ 4.1.25 b Retail Services 701 Bed and Breakfast Inn - (1-10 rooms) ● ○ ○ ○ ♦ 4.1.11 c Cemetery, Commercial ● ○ ○ ○ ● Communication Tower ○ ○ 4.1.5 835 Day Care, Group Home (7-18 persons) ○ ○ ○ c 7992 Golf Course - (Commercial) ♦ ○ 4.1.16 c 7997 Golf, Tennis, Yacht or Country Club, Private ○ ○ ○ ○ 4.1.16 c Golf, Tennis, Yacht or Country Club, Commercial ○ ○ ○ ○ 4.1.16 c Fishing Lake, Commercial ● ○ ○ ○

752 Kennel, Pet Grooming or Training ♦ ♦ 4.1.25 c Kennel, Boarding and Breeding ♦ ♦ 4.1.25 c 782 Lawn and Garden Services ● ○ c Recreational Facility - Commercial ♦ 4.1.16 Recreational Vehicle Park or Campsite ○ ○ ● 4.1.33 Recreational Vehicle Park of Campground (City Only) ○ ○ ○ 4.1.33 702 Rooming or Boarding House ○ ○ ○ ○ c

7032 Sporting or Recreational Camp or Farm Retreat, Commercial

○ ○ Retail Sales Agricultural Produce grown on the premises ● ●4 Feed and Tack and Saddles ● ○ General Store - 2500 square feet or less ○ ○ Semi-Public Uses and Utilities Athletic Playfields ♦ ○ ○ ○ ♦ 4.1.16 d Carnival, Fairgrounds, Rodeo, Horse Show, Shooting and Special Events of Community Interest ♦ ♦ 4.1.16 d Cemetery, Non-Profit ● ● ○ ○ ● 866 Churches or Places of Worship ♦ ♦ ○ ○ ♦ 4.1.3 d 864 Civic Clubs, Veterans or other Social Organizations ♦ ○ ○ ○ ♦ 4.1.4 d Communication Tower ○♦ ○♦ 4.1.5 d

Community Garden (County Only) ● ● ● ● ● ● Community Garden (City Only) ○ ○ ○ ○ ○ ○ Community Recreation Facility ○ ○ ○ ○ ♦ 4.1.16 d Neighborhood Recreation Center or Swimming Pool ○ ○ ○ ○ ○ ♦ 4.1.16 d Outdoor Special Events Venue (City Only) ○♦ ○♦ 4.1.16

Park, Passive ● ● ● ● ● d 821 School, Kindergarten, Elementary and Secondary ○ ○ ○ ○ ● d Solar Farm ● ○ 4.2.17 491-493 Utility Company Substation ○ ○ ○ ○ ○ Wedding Chapels & Indoor Special Events Venue (City Only) ○♦ ○♦ 4.1.16 Special Events Venue (County) ○♦ ○♦ 4.1.16

4 Special use permit required in the City

ACCESSORY USES A-R S-R HT-R LT-R D-R M-R See Also

Parking - See under 6.86.

Accessory Apartment ○♦ ○♦ ○♦ ○♦ 4.1.29 Accessory Uses Normally Incidental to Principal Use ♦ ♦ ♦ ♦ ♦ ♦ 4.2 Agricultural Production - Private Gardens ● ● ● ● ● ●

Community Gardens (County only) ● ● ● ● ● ● Community Gardens (City only) ○ ○ ○ ○ ○ ○ Customary Accessory Uses to a Dwelling ♦ ♦ ♦ ♦ ♦ ♦ 4.2.3 835 Day Care, Family Home (6 or less persons) ● ● ● ● ● Guest House ♦ ♦ ♦ ♦ ♦ 4.2.3 Home Office ♦ ♦ ♦ ♦ ♦ ♦ 4.2.3 Keeping Chickens within the City Limits of Rome ○ ○ ○ ○ 4.2.3.0 Kennel, Non-commercial ♦ ♦ ♦ ♦ 4.2.3 Residential Business ♦ ♦ ♦ ♦ ♦ ♦ 4.2.3 Personal Horse Stable ♦ ♦ 4.2.3 Private Recreational Facility ♦ ♦ ♦ ♦ ♦ 4.2.3 Private Use Airport ♦ ○ 4.2.10 Private Use Heliport ♦ ○ ○ 4.2.10 Solar Panel Array ● 4.2.17 Solar Panel Installation ● ● ● ● ● ● 4.2.17 Hobby Farms ● ♦ 4.1.1f Wildlife Park or Zoo ○ 4.1.1f List of Permitted Principal and Accessory Uses Table 3-2. Nonresidential Districts5 Use is permitted by right………………………● Use may be permitted as a Special Use….…….○ Use is permitted by right with limitations.…….♦ Use is not permitted…………………………....space is empty

PRINCIPLE USES N-O-C6 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

Agriculture and Related Business Farmer’s Market ○ ○ ○ ○ ○ ○ ○ Live Stock Pavilion or Farmers' Market ♦ ♦ 4.1.1 c Temporary or Portable Sawmill ♦ 4.1.1 Residential Site-Built Single-Family Dwelling ● a Two-Family Dwelling Duplexes ○7 a Multi-Family Dwelling ○ ● ●8 a Townhome or three family dwelling (triplex) ○ 4.1.23 a High-Rise Residential (see Central Business Commercial District)

○ ● ● a Loft Dwelling (see Central Business Commercial District)

● ● ● 6.8.1b Manufactured Home Park ○ 4.1.12 a 8025 Convalescent Home (5-15 persons) ♦ ♦ 4.1.18 a 8025 Convalescent Home (16 or more persons) ♦ ♦ 4.1.18 a Fraternity or Sorority Residence Hall ♦ 4.1.11 a Group Residence (5-15 persons) ♦ 4.1.13 a 5 See Article 4- restrictions regarding particular uses, for specific requirements that apply to uses permitted by right but with limitations.

6 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

7 As adaptive reuse existing building only 8 As adaptive reuse existing building only

PRINCIPLE USES N-O-C9 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

Group Residence (16 or more persons) ♦ 4.1.13 a 8051 Nursing Home (5-15 persons) ♦ ♦ 4.1.18 8051 Nursing Home (16 or more persons) ♦ ♦ 4.1.18 a 836 Personal Care Home, Group (5-15 persons) ♦ ♦ 4.1.13 a 836 Personal Care Home, Congregate (16 or more persons) ♦ ♦ 4.1.13 a 702 Rooming or Boarding House (5-15 persons) ○♦ ○♦ 4.1.13 c 702 Rooming or Boarding House (16 or more persons) ○♦ ○♦ 4.1.13 c Offices 872 Accounting, Auditing, or Bookkeeping Office

● ● ● ● ● ● ● ● b 731 Advertising Agency ● ● ● ● ● b 62 Brokerage for Securities or Commodities ● ● ● ● ● b 15-17 Building Contractor or Construction Firm Office (no storage of machinery or equipment)

● ● • • ● ● • b 861-863 Business, Professional or Trade Membership Organization Office

● ● ● • • ● ● b 484 Cable Television Operation ● ○ ○ ● ● • b 732 Credit Reporting or Collection Agency ● ● ● ● ● ● b 736 Employment or Personnel Agency • ● ● ● ● ● ● b 736 Employment or Personnel Agency With Day Labor Hiring Center

● ● ● ● ● 871 Engineering, Architectural or Other Professional Office

● ● ● ● ● ● ● b General Business Office ● ● ● ● ● ● ● b 808 Home Health Care Company ● ● ● ● b 63 Insurance Company Carrier ● ● ● ● ● ● ● ● b 67 Investment Company or Trust ● ● ● ● ● b 781 Landscape Architect ● ● ● ● ● ● ● ● b 9 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

PRINCIPLE USES N-O-C10 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

81 Legal Services Office ● ● ● ● ● b 874 Management and Public Relations Service ● ● ● ● ● b 801-804 Medical or Dental Offices or Clinics (not veterinary)

● ● ● ● ● b 807 Medical or Dental Laboratory ● ● ● ● ● ● b 865 Political Organization Office ● ● ● ● b 65 Real Estate Office ● ● ● ● ● b 873 Research, Development or Testing Service ● ● ● ● b 7338 Secretarial or Court Reporting Service ● ● ● ● ● b 62 Security or Commodity Broker ● ● ● ● ● b 792 Theatrical Production Agencies ● ● ● ● b Utility Business Office ● ● ● ● ● ● b 741 Veterinarian, Large Animal ♦ ♦ 4.1.25 b 742 Veterinarian, Small Animal ○ ♦ ♦ ♦ ♦ 4.1.25 b Retail Services Adult Entertainment Uses ♦ ♦ 4.1.20 c Air or Ground Courier Drop-Off Station ○ ● ● ● ● ● c 4729 Airline Ticket Office ● ● ● ● ● c Ambulance Service ○ ● ● ● c 7996 Amusement Park ● ● c 7993 Amusement Parlor ● ● ● ● c 7999 Amusement or Recreational AttractionIndoor

○ ○ ● c 7999 Amusement or Recreational AttractionOutdoor ♦ ♦ ♦ 4.1.16 c Appliance Repair Service ♦ ♦ ♦ 4.1.17 c 752 Automobile Parking Lot, Commercial ♦ ♦ ♦ 4.1.2 Automobile Parking Structure, Commercial ♦ ♦ ♦ 4.1.2 10 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

751 Automotive Rental Agency ♦ ♦ ♦ ♦ 4.1.2 c

PRINCIPLE USES N-O-C11 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

753 Automotive Repair Shop ♦ ♦ 4.1.2 c 7549 Automotive Service Business (excluding Repair) ♦ ♦ ♦ 4.1.2 c Automotive, Tire Re-treading and Recapping ♦ ♦ 4.1.2 c Automotive Upholstery Shop ♦ ♦ ♦ 4.1.2 c 60 Bank, Savings and Loan or Credit Union ● ● ● ● ● ● c 724 Barber Shop (City) ● ● ● c 723 Beauty Shop (City) ● ● ● c 724 Barber Shop (County) ● ● ● ● c 723 Beauty Shop (County) ● ● ● ● c 701 Bed and Breakfast Inn - Historic District Only (1-10 rooms) ♦ 4.1.11 c 793 Bowling Center ● ● c 734 Building Maintenance or Pest Control Service

● ● ● c 41 Bus or Taxi Service or Terminal ● ○ ● ● 824 Business or Vocational School ● ● ● c 738 Business Service Establishment, Miscellaneous

● ● ● ● ● c 7542 Carwash ♦ ♦ ♦ 4.1.2 c 5812 Catering Service ○ ● ● ● c Cemetery, Commercial ● ● 7336 Commercial Art or Graphic Design Service ● ● ● ● ● c 737 Computer Programming, Repair or Data Processing Service

● ● ● ● ● ● c 61 Credit Agency or Loan Establishment ● ● ● ● c Crematories ○ ○ ○ ○ c 791 Dance Studios or Schools ○ ● ● ● ● ● c 835 Day Care Center (19 or more persons) ○♦ ♦ 4.1.9 c 11 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

835 Day Care Group Home (7-18 persons) ○ ♦ ○ 4.1.9 c

PRINCIPLE USES N-O-C12 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

7331 Direct Mail Advertising Service ○ ● ● ● ● c Dry Cleaning Plants ♦ ♦ 4.1.10 c 762 Electrical Repair Shops ● ● ● c 473 Freight Agency or Shipping Coordinator ● ● ● c 726 Funeral Home ○ ● ● c 735 Furniture or Equipment Rental Establishment ● ● ● c 7992 Golf Course-Par 3, 9, or 18 Holes (Commercial)

○ ♦ 4.1.16 c Golf , Miniature (Commercial) ♦ ♦ 4.1.16 c Golf or Baseball Driving Range (Commercial) ♦ ♦ 4.1.16 c 7997 Golf, Tennis, Yacht, or Country Club, Private ♦ 4.1.16 c 7991 Health Club or Fitness Center ● ● ● ● ● c 809 Health Services Facility ● ● ● ● c 809 Health Services Facility with pharmacy ● ● ● ● c 806 Hospital ● ● ● ○ c 701 Hotel or Motel, rooms only ● ● ● ● c 701 Hotel or Motel with full service restaurant ● ● ● ● ● c 701 Hotel or Motel with full service restaurant and lounge

● ● ● ● c Indoor Athletic Training or Fitness Facility ● ● ● Interior Designer (no merchandise for sale on premises)

● ● ● ● ● c Interior Designer or Decoration (with merchandise for sale on premises)

○ ● ● ● c Jewelry Repair ● ● ● ● c Kennel, Boarding and Breeding ♦ ♦ ♦ 4.1.25 c 752 Kennel, Pet Grooming ♦ ♦ 4.1.25 c 12 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

Kennel, Pet Training ♦ ♦ ♦ 4.1.25 c

PRINCIPLE USES N-O-C13 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

721 Laundry, Dry Cleaning or Garment Services (but excluding coin operated establishment)

● ● ● c 7215 Laundry or Dry Cleaning, Coin Operated ● c 782 Lawn and Garden Services ● ● ● c Linen and Diaper Services, Garment Pressing and Repair

● ● ● c 781 Motion Picture or Video Tape Production ● ● ● ● c 7832 Motion Picture Theater (except Drive-in) ● ● ● ● c 7833 Motion Picture Theater, Drive-In ○ ● c 783 Ornamental Shrub or Tree Service ● ● ● c Performing Arts Theater ● ● ● ● c 829 Personal Enrichment School or Tutoring ● ● ● ● ● c 729 Personal Services, Miscellaneous ● ● ● c 7334 Photocopying and Duplicating Services ○ ● ● ● c 722 Photographic Studio, Portrait ♦ ♦ ♦ ♦ ♦ 4.1.15 c 7335 Photography Service, Commercial ● ● ● ● c 483 Radio or TV Broadcast Station ○ ● ○ ○ ● c Radio or TV Repair ● ● ● c Communication, Radio, or TV Transmission Tower ○♦ ○♦ ○♦ ○♦ ♦ ♦ 4.1.5 c 7033 Recreational Vehicle Park or Campground ○ ○ 4.1.33 7699 Repair Shops, Miscellaneous (not automotive) ♦ ♦ ● ● 4.1.17 c 764 Re-upholstery or Furniture Repair Shop ● ● ● c 702 Rooming or Boarding House ○ ○ c 725 Shoe Repair Shop ● ● ● • c 794 Sports Facility, Commercial ○ ○ c 481 Telecommunications Switching Station ○ ○ ○ ● ● ● 13 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

482 Telegraph Office ● ● ● ● c

PRINCIPLE USES N-O-C14 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

Title Pawn business15 ● ● ● ● ● 472 Travel Agency or Tour Operator ♦ ● ● ● ● c 784 Video Tape Rental Store ● ● ● ● 763 Watch, Clock or Jewelry Repair Shop ● ● ● ● 7692 Welding Repair Shop ● ● Retail Sales Agriculture Produce grown on the premises ● 5831 Alcohol Pouring Establishment ● ● ● 56 Apparel and Accessory Stores ● ● ● 572 Appliance Stores ● ● ● ● 551 Automobile Sales and Service ○ ♦ 4.1.2 c 552 Automobile Sales, Used Only, No Service ♦ ♦ c Automobiles Sales, Used Only ○ ♦ 4.1.2 c 554 Automobile Service Station ○ ♦ ♦ 4.1.2 c 553 Automotive Parts and Supply Store ♦ ♦ ♦ 4.1.2 c Automotive, Tire Store ♦ ♦ ♦ 4.1.2 c 546 Bakery, Retail ♦ ● ● c 555 Boat Dealers ♦ ♦ ♦ 4.1.2 c 5942 Book Store, New Dealers and Newsstands ♦ ● ● ● ● 4.2.1 c 5946 Camera and Photographic Supply Stores ● ● ● c 596 Catalog Sales or Direct Selling Office ● ● ● c Communication Tower ♦○ ♦○ ♦○ ♦○ ♦ ♦ 4.1.5 5734 Computer or Computer Software; Sales & Service

● ● ● • c 5731 Consumer Electronics Store ● ● ● c 14 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

15 With the footnote: “Business operation only, with no repossessed vehicles received, parked, stored, displayed, or sold from any property within the NOC district.

PRINCIPLE USES N-O-C16 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

554 Convenience Gas Station ● ● ● ○ c Custom Order or Specialty Shop ♦ ♦ ♦ 4.1.7 c 591 Drug Store (pharmacy) ♦ ● ● ● 4.2.1 c Farm and Other Equipment Sales and Service ○ ● ● ● c Feed and Seed Store ● ● ● ● c 53 General Merchandise Store ● ● ● • c 5747 Gift, Novelty, and Souvenir Shop ♦ ● ● ● c 54 Grocery or Specialty Food Store (except Bakery) ○ ● ● ● ● c 525 Hardware Store ● ● ● ● c 5945 Hobby, Toy, and Game Shops ● ● ● c 571 Home Furniture or Furnishings Store ● ● ● c 5944 Jewelry Store ● ● ● c 592 Liquor Store ● ● c 598 LP Gas or Fuel Oil Dealer ● ● ● c 5948 Luggage and Leather Goods Store ● ● ● c 521 Lumber and Other Building Materials Dealers ● ● ● c 527 Manufactured Home Sales Lot ● ● c Mobile Food Vehicle Park ○ ○ 4.1.31 559 Motor Vehicle Dealers, Miscellaneous ○ ♦ ♦ 4.1.2 c 557 Motorcycle Sales and Service ○ ♦ 4.1.2 c Medical Supply Sales & Service ○ ● ● ● ● ● 5736 Musical Instruments Store ● ● ● c 523 Paint, Glass, or Wallpaper Store ● ● c 526 Plant Nursery, Lawn and Garden Supplies ● ● ● c Plumbing, Electrical, and Heating Equipment Dealers

● ● ● c Preparing Food for Sale on Premises ○ ● ● ● c 16 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

PRINCIPLE USES N-O-C17 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

5735 Record and Video Tape Sales ● ● c 556 Recreational Vehicle Dealer ♦ ♦ 4.1.2 c 5812 Restaurant, Custom Service (not fast food) ○ ● ● ● 4.1.8 c 5812 Restaurant, Fast Food ● ● ● ● c 599 Retail Stores, Miscellaneous ● ● ● c 5949 Sewing, Needlework, and Fabric Stores ○ ● ● ● c Shopping Center ○ ● c 5941 Sporting Goods Store and Bicycle Shop ● ● ● c 5943 Stationary Store ● ● ● ● c 593 Used Merchandise Store ● ● ● ● c Flea Market ● c Industrial, Transportation and Storage Airline or Air Courier Company - Storage, Transfer, or Maintenance Facility ● ● e Airport ● ● Air Transportation, Non-scheduled ● ● Boat Docks, Marina, and Waterfront Recreation

● ● ● Cargo Packing and Crating Company ● ● e Construction Contractor-with Machinery, Equipment, and Storage ♦ ♦ 4.1.6 b Junkyard ♦ 4.1.2 Mini-Warehouses ● ● e Mini-Warehouses18 ○♦ ○♦ ○♦ 4.1.30 Mini-Warehouses, Unincorporated County ○ ● ● e Motor Freight Truck Terminal ● ● e Mold-poured concrete products ○♦ ♦ ♦ ● 4.2.15 17 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

18 As adaptive reuse of existing building only

PRINCIPLE USES N-O-C19 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

Outdoor Storage Yard ○ ♦ 4.2.9 Petroleum Bulk Storage or Stations ○ Quarrying or Mining ○ 4.1.15 Gravel Pit ○ ○ ○ ♦ 4.1.15 Railroad Lines, Yards and Stations ○ ● Recycling Center ● Recycling Drop-off Center ○ ● ● ● Sawmill ● Solid Waste Landfill ○ 4.2.1 & 6.19 Solid Waste Transfer Station ♦ 4.1.21 Temporary Vehicle Storage (county) ○ ● ● 4.1.2.i Trucking and Courier Services (except air) ● c Warehousing or Indoor Storage Facility (not including Mini-Warehouses)

● ● e Wholesale Trade-Administrative or Sales Office Only

● ● ● ● ● ● ● e Wholesale Trade-Sales Operation including Storage and Transfer

● ● e Manufacturing Apparel and Other Fabric Products ● ● 6.19 e Artisan or Crafts Manufacturing ● ● ● ● ● Bakery, Industrial ● ● 6.19 e Bottling Works ● ● 6.19 e Broom and Brush Manufacture ● ● 6.19 e Chemicals and Allied Products ● 6.19 e Cleaning Products, Household and Industrial ● 6.19 e Distillery or Brewery ● Electronic Equipment and Components (except Computer Equipment)

● ● 6.19 e 19 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

PRINCIPLE USES N-O-C20 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

Fabricated Metal Products (except Machinery and Transportation Equipment

● 6.19 e Food and Kindred Products ● ● 6.19 e Furniture and Fixtures ● ● 6.19 e Industrial, Commercial Machinery and Computer Equipment

● ● 6.19 e Lampshade Manufacture ● ● 6.19 e 31 Leather Products (not including Tanning and Finishing)

● ● 6.19 e 24 Lumber and Wood Products (except Furniture)

● 6.19 e 39 Miscellaneous Manufacturing Industries (not refinery)

● ● 6.19 e 26 Paper and Allied Products ● 6.19 e 29 Petroleum-Related Industries (not refinery) ● 6.19 e 38 Precision Instruments ● ● 6.19 e 33 Primary Metals Industries ● 6.19 e 37 Printing and Publishing ● ● ● 6.19 e Research Testing or Laboratory ○ ● ● 6.19 e 30 Rubber and Plastics Products ● 6.19 e 32 Stone, Clay, Glass and Concrete Products ● 6.19 e 22 Textile Mill Products ● 6.19 e 21 Tobacco Products ● 6.19 e 37 Transportation Equipment ● ● 6.19 e Umbrella and Cane Manufacture ● ● 6.19 e Semi-Public Uses and Utilities Athletic Playfields ○ 4.1.16 d Carnival, Fairgrounds, Rodeo, Horse Show, Shooting and Special Events of Community Interest ♦○ ♦ 4.1.16 d Cemetery, Non-Profit ● ● 20 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

PRINCIPLE USES N-O-C21 O-I C-C UMU C-B-C H-C L-I H-I See Also

Parking - See under 6.86.

866 Churches or Places of Worship ♦ ♦ ♦ ♦ ♦ ○ 4.1.3 d 864 Civic, Social or Fraternal Organization ♦ ♦ ♦ ♦ ♦ 4.1.4 d Communication Tower ♦○ ♦○ ♦○ ♦○ ♦ ♦ 4.1.5 Community Garden (County Only) ● ● ● ● ● ● Community Garden (City Only) ○ ○ ○ ○ ○ ○ Community Recreation Facility ♦ ♦ ♦ ♦ ♦ ♦ 4.1.16 d Governmental Administration Buildings ● ● ● ● ● ● ● d 823 Library ● ● ● ● d Neighborhood Recreation Center or Swimming Pool ♦ ○ ♦ ♦ 4.1.16 d 84 Nonprofit Museum or Art Gallery ● ● ● ● ● d Outdoor Special Events Venue (City Only) ♦○ ♦○ 4.1.16 Park, Passive ● ● ● ● ● 48 Post Office ● ● ● ● d Sanitary Sewer Treatment Plant ○ ○ ● 4.1.19 32 Stone, Clay, Glass and Concrete Products ● 6.19 e 822 School, College ● ● ● ● d 821 School, Elementary and Secondary ○ Solar Farm ○ ● 4.2.17 Utility Company Substation ♦ ♦ ♦ ♦ ♦ ♦ ♦ 4.1.24 Wedding Chapels and Indoor Special Events Venues (City Only) ♦ ♦ 4.1.16 458 Private Use Heliport ○ ○ ○ ○ ○ 4.2.10 21 See Article 3-Section 3.3.2(g), regarding Neighborhood Office Commercial development standards.

ACCESSORY USES

N - O - C O - I C - C U - M - U C - B - C H - C L - I H - I See Also Parking - See under 6.86.

Accessory Apartment ○ ♦ 4.1.29 Accessory Uses Normally Incidental to Principal Use ♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ 4.2 Accessory dwelling in connection with a non -residential use ○ ○ ○ ○ ○ ○ ○ Accessory retail services in connection with an office, institution, hotel or motel, high - rise apartment, etc.

♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦ 4.2.11 Automotive Rental and Lease as Accessory Use to Service Station ♦ ♦ ♦ 4.2.4 Brew Pub ● ●

● 4.2.16 Customary Accessory Uses to a Dwelling ♦ ♦ ♦ ♦ 4.2.3 Community Gardens (County only) ● ● ● ● ● Community Gardens (City only) ○ ○ ○ ○ ○ Craft or Micro -Distillery, Brewery, or winery ● ●

● 4.2.16 835 Day Care Center (19 or more persons) ♦ ♦ ♦ ♦ ♦ ♦ ♦ 4.1.9 c 835 Day Care, Family Home (6 or less persons) ● ● 835 Group Day Care Home (7 -18 persons) ● ● ● ● ● ● ● c Guest House ♦ 4.2.3 Home Office ♦ ● ♦ ♦ ♦

● 4.2.3 Residential Business ♦ ● ♦ ♦ ♦

● 4.2.3 Manufacturing or Fabrication Uses ♦ ♦ ♦ ♦ 4.2.6 Night Watchman Residence ○ ○ ○ ○ ○ ○

○ 4.2.7 a Outdoor Display Area ♦ ♦ ♦ ♦ ♦ ♦ 4.2.8 Outdoor Storage Yard ♦ ♦ ♦ ♦ 4.2.9 Private Recreation Facility ♦ ♦ 4.2.3 458 Private Use Heliport ○ ○ ○ ○

○ 4.2.10 Solar Panel Array ● ● ● ● ● ●

● 4.2.1 7 Solar Panel Installation ● ● ● ● ● ● ●

● 4.2.1

3.5. LOT SIZE, DENSITY AND SETBACKS

3.5.1. MINIMUM LOT SIZE

Every property upon which a principal use may be located shall meet or exceed the following requirements for its respective zoning district except that the Minimum Lot Size (square feet) requirements in column three of Table 3-3 shall have application only in the city; everything else in Section 3.5.1 shall remain the same. Exception: the Minimum Lot Size (square feet) requirements in column three of Table 3-3 shall not apply to a subdivision of land in designated Redevelopment Districts in the City of Rome.

Table 3-3 Minimum Lot Size Zoning District Use or Density (sq. ft. per unit unless otherwise noted) Minimum Lot Size (square feet) Minimum Lot Width Major Sts. (feet) Minimum Lot Width Other Sts. (feet) A-R Public water and sewerage 7,200 150 60 Public water, private sewerage 20,000 150 80 Private water and sewerage 1 acre 150 150 Other uses None None None S-R Single Family Residential:

Public water and sewerage 7,200 150 60 Public water, private sewerage 20,000 150 80 Private water and sewerage 1 acre 150 150 D-R Single Family and Two Family Residential:

Public water and sewerage 8,500 150 80 Public water, private sewerage 1 acre 150 100 Private water and sewerage N/A N/A** N/A Other uses None None None

HT-R 5000 5000 150 60

4000 8000 160 80

LT-R 12,500 12,500 150 60

D-R - 12,500 12,500 160 80 M-R Multifamily 14 units/acre 1 acre 300 150 Tri/Duplex – 4000*** 12,000 N/A** 100/80 Townhomes*** 1 acre N/A** 18 M.H. Park 6*** See Article 4 Residential Cluster – 10 units/acre 1 acre (43,560 sq. ft.) N/A** 100/80

N-O-C 10,000 10,000 90 90

O-I N/A 20,000 300**** 150

C-C Residential See M-R District Non-residential 30,000 300**** 150 C-B-C none none 26 26 UMU None 26 26

H-C N/A 30,000 300**** 150

L-I N/A 30,000 300**** 150

H-I N/A 5 acres 300 N/A P-D Densities and lot sizes established as part of zoning approval for each Planned Development *Unless specified elsewhere in this code

**Development that is not permitted along major streets ***Specific standards are found in Article 4 of this code ****Minimum lot width may be reduced to 150 feet if shared access is provided with adjacent lot

3.5.2. MINIMUM PRINCIPAL BUILDING SETBACKS

All principal buildings on a lot shall be set back from the rights-of-way lines and property lines bounding the lot no less than the distances shown on the following table:

Table 3-4 Minimum Setback - Principal Buildings Front Zoning District Major Street* All Other Streets Side Rear A-R 60 40 10 25 S-R Single Family or Duplex 40 25 7 25 Zero-Lot Line N/A ** 25 10 ft. btw.

Buildings 0 along internal lot line 20 D-R Single Family & Two Family Residential N/A** 20 5 0 along internal lot line 20

HT-R & LT-R***

Single Family & Two Family Residential N/A** 20 5 20 Zero-Lot Line N/A** 20 10 ft. btw.

Buildings 20 M-R Multifamily 20 20 30 30 Tri/Duplex N/A** 25 15 25 Townhomes N/A** 20 20**** 25 Manf. Home Park 40 40 40 40 Residential Cluster N/A** 25 15 25

N-O-C*** 20 20 10 20

O-I 20 20 10 25 C-C 20 20 15 30 C-B-C None None None None UMU None None None None H-C 40 30 20 30 L-I 40 30 20***** 30*****

H-I 100 N/A 200***** 200*****

P-D Setbacks established as part of zoning approval for each Planned Development

*Residential lots shall not be platted to front directly on the right-of-way of a major arterial, unless adequate provisions for access have been established.

**Development that is not permitted along major streets ***If the adjacent property on both sides is developed with a similar use, new construction or infill development shall provide a setback equal to the average setback on the adjacent properties ****Individual townhouse units may provide 0 feet side yard separation, but end units must provide 20-foot side yards on the periphery of the lot.

*****No setback required where adjacent to rail line. For parcels zoned H-I, side and rear setbacks shall be the same as for the L-I district when adjacent to other H-I properties.

3.6. STRUCTURE HEIGHTS

3.6.1. MAXIMUM STRUCTURE HEIGHTS

The maximum height of all structures in each zoning district (except as provided in the subsections below) shall be as follows:

Table 3-5 Maximum Structure Height – Principal Buildings Zoning District Maximum Building or Structure Height (feet) A-R 45 S-R 45 D-R 30

HT-R 45

LT-R 45

M-R 45

N-O-C 35

O-I 45 C-C 45

C-B-C 75

U-M-U 100

H-C 45 L-I 45 H-I 60 P-D Height established as part of zoning approval for each Planned Development

3.6.2. EXCEPTION TO HEIGHT RESTRICTIONS

The following structures are exempt from the height limitations:

a. Agricultural buildings such as but not limited to barns, silos, windmills, grain elevators, and other farm structures, but not including dwellings.

b. Cooling towers, gas holders, or other industrial structures where required as part of the manufacturing process.

c. Church spires, belfries, cupolas, domes, monuments, water towers, observation towers, commercial radio and television transmission towers, windmills, chimneys, smokestacks, derricks, conveyors, communication towers, and TV reception antennae.

Article 4. Restrictions Regarding Particular Uses

4.1. PRINCIPAL USES

The following specific requirements apply to each of the following uses in all zoning districts where each use is permitted with limitations.

4.1.1. AGRICULTURAL AND FORESTRY

a. Concentrated animal feeding operation

(1) All livestock buildings or feeding enclosures shall be set back not less than 100 feet from any property line.

(2) Chicken broiler houses and other covered animal feeding operations are included in the definition of animal feeding operation to the extent that they must meet set back requirements and that their waste by-products must be disposed of in a timely and environmentally acceptable manner.

(3) Minimum parcel size is 10 acres.

(4) There shall be at least 5,000 square feet of fenced area not covered by the principal structure for each animal unit, excluding poultry. (See Definitions) All confined animal feeding operations shall comply with the requirements of the Georgia Department of Natural Resources Environmental Protection Division and the U. S.

Department of Agriculture Rules and Regulations for Water Quality (July 6, 1999) relating to animal waste disposal.

b. Livestock sales pavilions, operated in accordance with state and county health department regulations, are required to be located at least 50 feet from any property line.

c. Riding stable:

(1) Lot must be at least 5 acres.

(2) Structures shall be located at least 50 feet from any property line.

d. Temporary or portable sawmill:

(1) Shall not exceed a period of six months.

(2) Such use must be at least 200 feet from any property line.

e. Tenant dwelling for persons employed on land used for bona fide agricultural purposes may not be rented for any other purposes but to provide housing for persons employed by agricultural operations upon the same parcel of land; except that such dwellings that were built prior to the adoption of this Ordinance may be rented.

4.1.2. AUTOMOTIVE, TRUCK, BOAT AND TRAILER SALES AND SERVICE

a. Automotive parking lot or parking garage, commercial may include gasoline pumps if located entirely within the principal structure.

b. Automobile repair and paint shops

(1) CITY: Such use shall not be permitted within 300 feet of any property used for school, park, playground, day care home or center, nursing home, convalescent home, personal care home, or hospital; or within 300 feet of any residentially zoned property.

COUNTY: Such use shall not be permitted within 300 feet of any property used for a school, park playground, or hospital.

(2) All activities shall be carried on entirely within an enclosed building.

(3) CITY: Damaged vehicles shall be stored within a storage area that meets the criteria outlined in Article 4.1.2 i.

COUNTY: Such use shall not be established on a lot that is either adjacent to or directly across the street from any residentially zoned property.

c. Automobile and truck salvage and retail sales.

(1) Automotive salvage operations where parts are to be retailed or wholesaled as usable replacement parts are permitted provided they are properly screened from view on all sides by a solid fence a minimum of eight feet tall.

d. Automotive Service Business and Automobile Service Station.

(1) Auto repair shall not be permitted.

(2) Gasoline pumps and other service facilities shall be set back not less than 15 feet from the right-of-way line.

(3) All activities and storage of tires, parts, etc. shall be carried on entirely within an enclosed building.

(4) No inoperable vehicles shall be stored on the site for more than 24 hours.

(5) Such use in a P-D District shall not be constructed until the primary structure has been constructed.

e. Automobile, boat, truck and trailer sales, lease and rentals All parking areas shall be clearly marked, and no unit shall be parked within the setback areas of the district.

f. Automobile wash service A paved area shall be located on the same lot for the storage of vehicles awaiting service equal to one-third of the practical hourly capacity of the wash machines.

g. Automobile wrecking or junkyards

(1) Such use shall be enclosed by a fence or wall not less than eight (8) feet in height that provides total visual screening. Such screening shall be maintained in good condition and meet the standards established for buffers in Article 6.

(2) The storage of vehicles shall be on asphalt, concrete or gravel. Vehicles shall be arranged in rows and not stacked upon one another.

(3) No such activity may be conducted within 100 feet of any property line or 200 feet of any property zoned or used for residential purposes. The incidental sale of auto parts removed from cars on the site shall be permitted.

h. Retail automobile parts and tire store

(1) Unless elsewhere permitted within the district, there shall be no dismantling of vehicles on the premises to obtain auto parts.

(2) Unless elsewhere permitted within the district, the only auto part installation that shall be permitted in connection with this use shall be the installing of tires and the installation of minor maintenance or accessory parts.

(3) Unless elsewhere permitted within the district, major auto repair shall not be permitted in connection with this use.

i. Storage yards for damaged or confiscated automobiles

(1) This use shall be enclosed by a fence or wall at least eight (8) feet in height that provides total visual screening. Such screening shall be maintained in good condition and meet the buffer standards of Article 6 – “Site Design Standards.”

(2) The storage of vehicles shall be on an all-weather treatment such as asphalt, concrete or gravel. Vehicles shall be arranged in rows and not stacked upon one another.

(3) No such activity may be conducted within 100 feet of any property line or 200 feet of any property zoned or used for residential purposes. The incidental sale of auto parts removed from cars on the site shall be permitted. (CITY ONLY)

(4) No dismantling, repair, or other such activity shall be conducted unless otherwise permitted in the district.

(5) No automobiles shall be held longer that the expiration of its current registration period. (CITY ONLY)

(6) No vehicle shall be held longer than sixty (60) days from its arrival on the property. (COUNTY ONLY)

4.1.3. CHURCHES AND OTHER RELIGIOUS FACILITIES

a. When abutting a residentially zoned district, any building or structure shall be set back not less than 50 feet from any side or rear property line.

b. No parking area shall be established within 20 feet of a residential zone

c. For new construction on undeveloped ground the site must be at least one acre in size and have frontage on a public street of at least 100 feet.

4.1.4. CIVIC, SOCIAL AND FRATERNAL ORGANIZATIONS

All structures shall be at least 50 feet from any property line, and parking.

4.1.5. COMMUNICATIONS, RADIO AND TV TOWERS

All towers must be set back from any adjacent (next to or across the street) lot or unrelated structure a distance equal to the height of the tower. Article 4.1.5 shall not have application to towers located in the county. 22

4.1.6. CONSTRUCTION CONTRACTORS

Storage of materials not within a building or structure shall be screened by a permanent fence, wall or approved planted buffer. Such screen shall be at least 6 feet in height or two feet higher than stored materials, whichever is higher. Such screen 22 Setbacks for communications, radio, and TV towers located in the county shall be established through a separate comprehensive ordinance of the County and not the ULDC.

shall also be in conformance with buffer standards in Article 6 – “Site Design Standards.”

4.1.7. CUSTOM ORDER AND SPECIALTY SHOPS

Such uses are allowed by right if less than 10,000 square feet and if the sales area is within a building and occupies more than 10,000 square feet of building floor area, it shall be permitted with limitations by special use permit.

4.1.8. CUSTOM SERVICE RESTAURANTS

A restaurant in this district shall be a custom service restaurant and shall be located in a pre-existing residential structure modified for such use.

4.1.9. DAY CARE AND KINDERGARTENS

a. The lot shall have access on an arterial or major collector.

b. There shall not be less than 30 square feet of indoor play area for each child at maximum enrollment, and not less than 100 square feet per child of outdoor play area, for the maximum number of children that will use the play area at any given time, but in no case less than 1/3 of the maximum enrollment.

c. A fence not less than 4 feet in height shall enclose the outdoor play area.

d. A circular drive shall be provided for off-street loading and unloading.

e. In P-D and C-B-C Districts the use shall be permitted only as accessory use to a primary use.

4.1.10. DRY CLEANING PLANTS

a. Dry cleaning plants using systems that make use of solvents rated at above 40 according to the Underwriters’ Laboratories, Inc. standard of classification known as class I systems shall be prohibited.

b. Dry cleaning plants that make use of solvents rated at more than 5 but less than 40 according to the Underwriters’ Laboratories, Inc. standard of classification, known as class II and III systems shall not be established in buildings with other occupancy.

They shall be established in buildings that are set back at least 20 feet from any side or rear property line and another building.

c. The applicant for such a plant shall certify in writing at the time of application that all the above conditions shall be met. Such dry cleaning plant shall comply with all of the requirements of the Life Safety Code NFPA No. 101.

d. Such plant shall be designed to operate in a manner that will not emit noise, smoke, odor, or objectionable waste materials.

4.1.11. LODGING

a. Bed and Breakfast Inn

(1) Permitted only in federally designated National Historic Register districts and the A-R District as a Special Use.

(2) Bed and Breakfast Inns are permitted to offer 1 to 10 units.

(3) Parking requirements are stated in Article 6 – Subdivision and Project Standards.

(4) Signs shall meet the sign standards of the district wherein the facility is located.

b. Fraternity and sorority houses and residence halls

(1) The use must be located within 1,000 feet of an accredited institution of higher education.

(2) In computing area required to determine dwelling unit densities, each six beds or fraction thereof shall be considered as 1 dwelling unit.

4.1.12. MANUFACTURED HOMES

These regulations shall govern the use and operation of all manufactured homes used for residential purposes and manufactured home communities within the County. It is the intent of these regulations to empower the Planning Commission, the fire department, the county health department, and the building inspection department to review the development of manufactured home sites and parks within the county for the purposes stated in this article.

a. Purpose.

These regulations are being promulgated to project the health, safety and general welfare of the citizens of the County. The County recognizes that manufactured housing meets the needs of many county residents for affordable housing.

b. General Standards.

(1) No mobile home shall be brought into the County after the effective date of this Development Code.

(2) Zoning requirements:

(a) A-R District: Manufactured and mobile homes are permitted with limitations within unincorporated Floyd County and only by Special Use Permit inside the City of Rome.

(b) S-R or P-D Residential Districts: Manufactured homes on individual lots are permitted only by special use permit within those portions of the county consisting of land development projects in which two or more lots are created, along with streets and utilities needed to support construction of buildings on the lots. In other portions of the county in said Residential Districts, manufactured homes are permitted with limitations. Manufactured homes on individual lots in the city are allowed only be special use permit. Manufactured home subdivisions are permitted with limitations.

(c) HT-R and LT-R Residential District: Manufactured homes on individual lots are not permitted.

(d) D-R Residential District: Manufactured homes on individual lots are excluded from the Duplex District. Manufactured home subdivisions are excluded from this zone.

(e) M-R Multifamily Residential District: Duplex manufactured homes are permitted. Manufactured home parks are permitted with limitations.

(f) Manufactured and mobile homes are prohibited from any historic district.

(3) Mobile home inspection.

No mobile home shall relocate from a site within the county without the following inspection. The cost of such inspection shall be the responsibility of the mobile home owner.

(a) Structural inspection by the Building Official to assure integrity of outside structural items such as windows, doors, and siding.

(b) HVAC inspection conducted by the Building Inspection Department:

1) Gas piping systems shall stand a pressure of six (6) inches mercury or three

(3) psi gauge for a period of not less than ten minutes without showing any drop in pressure.

2) When appliances are connected to the gas piping system, the entire system shall be pressurized to not less than ten (10) inches and not more than fourteen (14) inches water column and the appliance connections tested for leakage with soapy water or bubble solution.

(c) Electrical inspection shall be conducted by Building Inspection and shall meet the requirements of the latest edition of the National Electrical Code.

(d) Smoke detectors shall be installed and operational using the mobile home’s internal electrical wiring. At the minimum, a detector shall be located in the hallway(s) leading to the sleeping area(s). Detectors shall be Underwriter’s Laboratories approved and installed in accordance with the manufacturer’s instructions.

(4) An annual location decal is required and shall be filed by the owner of a manufactured or mobile home located in the county. The filing is at the office of the tax commissioner. Homes having filed for a homestead exemption in the property tax assessor’s office are excluded from such requirement.

(5) Permanent additions may be built onto any manufactured home or mobile home provided such addition or modification meets the requirements of the building code and the procedures outlined for developing a manufactured home park as applicable.

(6) Manufactured or mobile homes placed after the date of this article shall be required to have the following improvements at the manufactured or mobile home stand per the Manufactured Home Division of the Safety Fire Commissioner of the State of Georgia:

(a) Tiedowns: Each manufactured or mobile home shall be secured to ground anchors or other devices securing the stability of the manufactured or mobile home as outlined in the building code.

(b) Foundations: Foundations shall be installed in accordance with the standards set forth in the Georgia Installation Code for Manufactured Homes.

(c) Steps: Steps are required to be placed within 45 days of installation for all doors into the manufactured home and shall be at least 36 inches in width. If more than 3 steps are required, the steps shall be equipped with a hand railing.

The improvements shall comply with the provisions of the building code.

(d) Any manufactured or mobile home located within the county shall be skirted within 45 days of installation.

(e) Any manufactured home or mobile home located within the City must be placed on a masonry foundation, slab, or masonry piers with masonry curtain within 45 days of its installation. The towing tongue and wheels shall be removed.

(7) Any manufactured or mobile home that is damaged by fire, flood, explosion, wind or other catastrophe in any amount equal to or greater than 60 percent of its replacement value shall be removed and disposed of or repaired by the owner within 90 days after damage occurred unless a variance has been granted.

(8) Nonconforming manufactured or mobile home sites, parks, or subdivisions lawfully existing at the time of adoption of this regulation may be continued; but if such nonconforming use is discontinued for a period of 12 months, the manufactured or mobile home site, park, or subdivision shall be made to conform to the requirements of these regulations.

c. Exceptions:

An exception to the provisions of this article may be granted based on medical hardship by authorized staff of the Planning Commission. An application for exception shall contain an affidavit of a physician showing at present lodging facilities are inadequate and that a hardship condition exists requiring the use of a manufactured home for the health care of a dependent of the occupant of the premises. The application shall attach a separate statement by the applicant that he/she recognizes the exception, if granted, is to last only as long as the health condition exists.

An exception may also be granted in an area that has been officially declared a disaster area by federal, state, or local government. In such a case, an application for exception shall include a statement by the applicant that he/she is the owner of the premises; and that he/she recognizes the exception is temporary and shall last only until permanent housing can be repaired or replaced; no more than 180 days which period can be extended one time for 180 more days by Planning Department staff.

In either case:

(1) Any change in the status of the occupant(s) justifying the granting of an exception, shall be reported to the City of Rome/Floyd County Building Inspection and/or Planning Office within 30 days.

(2) The applicant shall also state that he/she shall cause the removal of manufactured home on the termination of the exception and that upon failure to do so irrevocably grants the Governing Body the right to use equipment to remove the manufactured home from the premises at the applicant’s expense.

(3) A manufactured home placed in this manner is not to be used as a rental property.

It must be removed at the expense of the property owner, once the special medical or other need for which a variance was granted no longer exists.

d. Manufactured and mobile homes on individual lots.

(1) Manufactured and mobile home situated on individual lots in the unincorporated county shall be required to meet the same location standards as other single-family units within the same zoning district.

(2) Health Department approval will be required for every manufactured home and/or mobile home on a lot not connected to public sewer systems. Lot size shall be approved by the Health Department using appropriate percolation and/or soil test data. No septic tanks shall be allowed if public sewerage is available. All dwellings shall connect to the public sewer when such sewer is within 300 feet of the property being subdivided.

(3) All lots shall comply with the Flood Damage Prevention provisions of this Development Code. Each lot shall have thereon a viable home-site above the 100- year flood plain.

(4) Any manufactured home or mobile home placed on an individual lot within the City shall be compatible with single-family dwellings on surrounding lots for a distance of 100 feet or one block in any direction in terms of roof pitch, exterior wall treatment, and orientation relative to the street frontage.

e. Where private sewerage disposal systems are to be placed in front yard areas, setbacks shall be established by the Floyd County Health Department but shall not be less than 40 feet.

f. Manufactured home subdivisions.

(1) Manufactured home subdivisions shall be required to meet all the development standards of this Code.

(2) Manufactured and mobile homes situated on individual lots shall be required to meet the same standards for location as single-family dwelling units. Prior to the placement of the manufactured or mobile home on the lot, the owner shall submit a plot plan or an affidavit signed by the owner to the building inspection department that indicated the site complies with the provisions of this ordinance concerning the placement of such homes.

(3) Any manufactured home placed on an individual lot in a manufactured home subdivision within the City shall be compatible with single-family dwellings on surrounding lots for distance of 100 feet or one block in any direction in terms of roof pitch, exterior wall treatment, and orientation relative to the street frontage.

g. Manufactured home parks:

(1) Approval of manufactured home parks:

Procedures for developing a manufactured home park shall follow the same standards as specified for site plan approval outlined in Article 2. This article relates to application submissions, approval processes, erosion and sediment control, design issues, grading, flood area management, etc.

(2) Site standards for manufactured home parks:

(a) Any park of 10 units or more must be located on a road classified as an arterial as specified in the county road maintenance register or otherwise be on a state highway. Said park shall have a minimum street frontage of 300 feet. Parks with less than 10 units shall be located on a major collector or higher functional street classification and have a minimum road frontage of 150 feet.

(b) Manufactured home parks shall front on a publicly maintained street.

(c) Manufactured home parks shall be served by a public water and sanitary sewer source. Any extension of public water lines shall be constructed in accordance with standards established by this Development Code for single-family dwellings. All water mains shall be at least 6 inches in diameter. Fire hydrants shall be readily accessible for fire department use. Hydrants shall be located so that each home or building in the park is within 500 feet of a hydrant.

(d) All manufactured home parks shall be served by a garbage collection system.

Collection facilities may be provided for the entire community or at individual lots within the each manufactured home park. The design for these facilities must be approved at the time of development plan approval.

(e) Each manufactured home shall be located on a lot having an area of 5,000 square feet and minimum building line width of 40 feet.

(f) Manufactured homes shall be separated from each other and from other buildings and structures by at least sixteen (16) feet. Porches and decks without tops or opaque roofs shall be excluded from this requirement.

(g) One accessory storage building is allowed on an individual lot. The maximum size shall not exceed 120 square feet.

(h) All structures shall be set back from any exterior property line of the manufactured home park by 40 feet.

(i) One or more recreation areas shall be provided within those manufactured home parks having 10 or more units. Such recreation area shall constitute a minimum of 5 percent of the space designated for residential lots. All such recreation areas shall be so designated on the development for the park and shall not be converted to use as a manufactured home lot. Recreation areas shall be so located as to be free of traffic and safety hazards. At least 50 percent of the recreational open space land shall be of a character suitable for active recreation, such as playgrounds or ball fields.

(j) All interior roadways are to be surfaced with a material such as asphalt, chert, gravel, etc., to a width of 12 feet for one-way streets or to a width of 18 feet for two-way streets and maintained by the manufactured home park owner.

(k) Areas not surfaced or built over shall be planted in grass or other suitable vegetative cover.

(l) Adequate security lighting shall be provided for the manufactured home park.

(m)The location of electrical cables, gas piping, and sewer lines buried underground shall be indicated by an above ground sign(s) or underground marker tapes identifying the proximity of the lines. A plot plan showing the asbuilt location of underground utility lines shall be provided to the Building Inspector.

4.1.13. PERSONAL CARE HOMES

a. In all single-family and two-family residential districts (AR, SR, LTR, HTR, DR), the square footage of an existing dwelling shall not be enlarged by more than 25% of the existing dwelling to affect the use of the structure as a personal care home, rooming or boarding house, or group residence. Exterior modification of an existing dwelling and provision of the required parking shall be consistent with the residential character of the surrounding neighborhood; i.e. in design, scale, and number of vehicles allowed.

b. In all single-family and two-family residential districts (AR, SR, LTR, HTR, DR), new construction shall be consistent with the residential character and scale of the surrounding neighborhood.

c. Personal care homes, rooming or boarding houses, and group residences shall maintain all applicable federal and/or state licenses and/or permits.

4.1.14. PHOTOGRAPHIC STUDIO

a. No commodities may be sold other than photographs of customers made by the studio and items accessory to and sold in conjunction with those photographs.

b. On-site film processing and printing is solely for the studio’s use.

c. No custom framing or other non-photography work may be performed as part of the business.

4.1.15. QUARRYING, MINING, AND SOFT MATERIAL EXTRACTION (City Only)

a. Quarrying and mining includes removal, extraction and/or processing of any dirt, sand, soil, clay, rock, gravel, minerals, gas, oil, or other fuels for sale or removal from the property in its extracted form, finished form, or as a component of another product.

Borrow pits are permitted where less than 1.1 acres of land will be disturbed.

b. Prior to initiation of mining activities an application for a Special Use Permit must be submitted to the Planning Commission. Such application must provide:

(1) Written stipulations that the activity will not have harmful impacts on the environment (air, water, natural landscape) neighboring residents and businesses, or to livestock.

(2) A specific site plan and time schedule for completion of mining operations.

(3) Information as to how the operation will be buffered and methods to assure that no harmful off-site impacts will occur.

(4) A transportation plan detailing routes to be used by vehicles serving the site, weight limits and traffic volumes.

(5) Information on hours of operation and procedures (on- and off-site) related to any on-site blasting that might occur.

(6) Adequate financial bonding for damages (to be determined by the governing body)

c. The removal area shall be completely enclosed with a fence not less than 6 feet in height.

d. An earthen berm shall be provided that shields all operations from ground level view along all property lines.

e. Drainage plans and a plan for the development of the site when the removal is completed shall be submitted with the application for a development permit.

f. This section shall not prohibit the removal of earth and rock and filling and grading in any district done for land development purposes, upon issuance of a development permit in accordance with this Development Code.

g. These uses shall be established only on a site of not less than 200 acres.

4.1.15. QUARRYING, MINING, AND SOFT MATERIAL EXTRACTION (County

Only)

a. Quarrying and mining

(1) “Quarrying and mining” includes removal, extraction and/or processing of any dirt, sand, soil, clay, rock, gravel, minerals, gas, oil or other fuels for sale or removal from the property in its extracted form, finished form or as a component of another product. Quarrying and mining shall not include “soft material extraction” as hereinafter defined. Quarrying and mining and soft material extraction shall not include borrow pits that are excavated areas where naturally occurring earthen materials are to be removed for use and ordinary fill at another location. Borrow pits as defined herein are not subject to regulation by this section.

(2) Prior to initiation of quarrying and mining activities, an application for a Special Use Permit must be submitted to the Planning Commission. Such application must provide:

(a) Written stipulations that the activity will not have any harmful impacts on the environment (air, water, natural landscape), neighboring residents and businesses, or to livestock.

(b) A specific site plan and time schedule for completion of mining operations.

(c) Information as to how the operation will be buffered and methods to assure that no harmful off-site impacts will occur.

(d) A transportation plan detailing routes to be used by vehicles serving the site, weight limits and traffic volumes.

(e) Information on hours of operation and procedures (on- and off-site) related to any on-site blasting that might occur.

(f) Adequate financial bonding for damages (to be determined by the governing body).

(3) The following additional objective criteria shall be considered when reviewing a request for a special use permit under Section 2-2-4(b):

(a) Will the mining have an adverse impact on nearby residential property, whether through noise, light, dust, run-off or other potential nuisance?

(b) Will the mining have an adverse impact on any rivers, streams or other bodies of water?

(c) Will the mining have an adverse impact on the groundwater recharge system or underground aquifers?

(4) The removal area shall be completely enclosed with a fence not less than six feet in height.

(5) An earthen berm shall be provided that shields all operations from ground level view along all property lines.

(6) Drainage plans and a plan for the development of the site when the removal is completed shall be submitted with the application for a special use permit.

(7) This section shall not prohibit the removal of earth and rock and filling and grading in any district done for land development purposes, upon issuance of a development permit in accordance with this Development Code.

(8) These uses shall be established only on a site of not less than 200 acres.

b. Soft material extraction

(1) “Soft material extraction” is the removal of soft materials wherein:

(a) Blasting and the use of explosives are not employed in the mining operation;

(b) Groundwater aquifers will not be encountered;

(c) Removal does not take place below the water table; and

(d) Such soft materials are limited to common clay and shale, ball clay, china clay, kaolin, umber, ochre, fuller’s earth, bentonite, barite, bauxite, sericite, sand and gravel.

(2) Soft material extraction shall not take place on parcels of less than one (1) acre and is permitted in H-I, L-I, A-R and H-C zoning districts with a special use permit.

(3) Prior to initiation of any soft material extraction activities, an application for a Special Use Permit must be submitted to the Planning Commission. Such application must provide:

(a) Written stipulations that the activity will not have any harmful impacts on the environment (air, water, natural landscape), neighboring residents and businesses, or to livestock.

(b) A specific site plan that includes:

1. a dimensional separation where soft material extraction shall not occur within fifty (50) feet of all property lines;

2. a 10-foot buffer, within the 50-foot dimensional separation, that shields all operations from ground level view on property lines that are adjacent to all zoning districts except A-R; and

3. a time schedule for completion of soft material extraction.

(c) Information to assure that no harmful off-site impacts will occur.

(d) A transportation plan detailing routes to be used by vehicles serving the site, weight limits and traffic volumes.

(e) Information on hours of operation and procedures (on- and off-site).

(f) Adequate financial bonding for damages (to be determined by the governing body).

(g) Drainage plans and a plan for the development of the site when the removal is completed shall be submitted with the application for a special use permit.”

4.1.16. RECREATION AND ENTERTAINMENT (City Only)

a. Special outdoor entertainment, concert, or event of community interest.

(1) General standards:

(a) Such activities shall not exceed 14 days and may not occur more often than twice in any calendar year.

(b) Adequate parking and traffic maneuvering space must be located on the same property as the special event.

(c) Such activities shall not be conducted within 100 feet from any property line.

(d) No programs involving music or amplified sound may be presented within 200 feet of any residential zoning district or residence.

(e) Central loudspeakers shall be prohibited.

(f) Lighting shall be established so that adjacent properties and roadways are not adversely affected and shall be in accordance with Article 6-“Site Design Standards.”

(2) Carnival, Rodeo, Horse Show, Community Fairs, Fairgrounds and Amusement Parks.

(a) All activities and buildings must be set back at least 200 feet from any property line.

(b) These uses shall not be permitted within 500 feet of the property line of an adjacent residence.

(c) Facilities shall be enclosed by a wall or fence not less than 5 feet in height.

(3) Outdoor Special Events Venues.

In addition to the requirements set forth above, the following additional requirements shall apply:

(a) Site plans shall be approved by the Planning Commission to ensure compatibility of the facility with the neighborhood in which it is located.

(b) Outdoor activity shall cease by 11:00 p.m.

(4) Golf Courses and Club Houses, Private Neighborhood Recreation Centers or Swimming Pools, Noncommercial Club or Lodge, Planetarium, aquarium, botanical gardens, and other natural exhibitions.

In addition to the requirements set forth in the section above, the following additional requirements shall apply:

Read this code where it is posted (county website (romega.us)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:floyd-county/zoning/whole@2026-11-23-520ecb9c8b

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Floyd County Zoning Ordinance (the whole text) | Georgia Commons