Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, he/she shall first make application to the planning and community development department and obtain the required permit for the work.
(1) Information required. Each application for a permit, with the required fee, shall be filed with the planning and community development department on a form furnished for that purpose, and shall contain a general description of the proposed work and its location. The application shall be signed by the owner, or his/her authorized agent.
The building permit application shall indicate the proposed occupancy of all parts of the building and of that portion of the site or lot, if any, not covered by the building or structure, and shall contain such other information as may be required by the director.
(2 ) Drawings and document specifications.
a. Requirements. Documents drawn to scale with sufficient clarity and detail to indicate the nature and character of the work, shall accompany the application for a permit. Such drawings and specifications shall contain information, in the form of notes or otherwise, as the quality of material where quality is essential to conformity with the construction codes.
b. Site drawings. A general site plan drawn at a legible scale which shall include, but not be limited to, the location of all buildings, setbacks, buffers, easements, exterior storage facilities, parking lots, roads, storm and sanitary sewer accesses, and adjacent property uses on the site or lot. The director may require a boundary line survey or site plan prepared by a qualified surveyor.
c. Building floor plan. A building floor plan drawn to a legible scale, which shall include, but not be limited to, rooms, doorways, corridors, exits.
d. Additional data. The director may require details, computations, stress diagrams, and other data necessary to describe the construction or installation and the basis of calculations. All drawings, specifications and accompanying data required by the director are to be prepared by a certified, licensed architect or engineer and shall be affixed with their official seal.
e. Design professional. The design professional shall be an architect or engineer legally registered under the laws of this state regulating the practice of architecture or engineering and shall affix his official seal to said drawings, specifications, and accompanying data, for the following:
1. All group and occupancies.
2. Buildings and structures three (3) stories or more high.
3. Buildings and structures five thousand (5,000) square feet or more in area.
Ord. ( No. 21-11, § l(Exh. A), 9-7-2021)