Fort Oglethorpe · Zoning Ordinance
Appendix A - UNIFIED DEVELOPMENT CODE / Chapter 1 - GENERAL PROVISIONS / Article 8 - ADMINISTRATION
Sec. 8.2. Required action; time period.
About this text
- As published by Municode, current through 2026-03-26
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
In each case in this development code where the issuance of a permit or other action by any official of Fort Oglethorpe, Georgia, is required and a time period for such action is specified by this development code or by applicable state law, then the failure of the official responsible for same to take such action or issue such permit shall be deemed an approval of the matter or the issuance of the permit, as the case may be. If at any place in the development code an action is required by any such official and no time frame is provided herein, then such timeframe shall be deemed to be 45 days and the failure to act to either approve or deny same shall be deemed an approval of the matter or the issuance of the permit, as the case may be.
History
(Ord. No. 2021-10, § 1, 6-28-2021)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.