(a) The surface asphalt shall be placed over the binder asphalt as soon as possible, but no more than ten days after placing the binder, to avoid rainwater infiltration and to prevent damage from truck traffic. The time may be extended at the director of public works' discretion to deal with unusual circumstances, so long as the road continues to meet the structural requirements of this regulation. (1) The geotechnical engineer will test the thickness and compaction by obtaining cores every 500 feet, or a minimum of three cores. (2) Areas that do not meet the requirements shall be removed and replaced. As an option, at the developer's discretion, the geotechnical engineer can be present during construction to check the laydown thickness and temperature of the asphalt and to conduct nuclear density tests after compaction. In this case, coring will be reduced to three cores or one every 2000 feet. In any case, a minimum of three cores will be required. (b) The surface asphalt shall meet the requirements of Sections 400, 402, and 828 of the Georgia Department of Transportation "Standard Specifications Construction of Transportation Systems" (latest edition). The minimum design thickness of the surface asphalt shall be one and one-half inches. (c) Asphalt thickness tolerances. (1) The average thickness of the asphalt (binder plus surface) shall be greater than or equal to the design thickness, with no individual test more than one-eighth-inch less than the design thickness. (2) Areas deficient in thickness shall be evaluated by additional coring at 100-foot intervals to determine the area of deficient thickness. (3) Deficient areas shall be corrected.