(a) No later than five business days after receipt of any application related to regulatory requirements, the director of building, planning and zoning shall either:

(1) Approve the application and issue the requested permit; or

(2) Notify the applicant as to whether the submitted documents meet the requirements of a complete application.

(b) Except as otherwise provided in this article, time spent by the city determining whether an application is complete shall count toward the total 30 days for plan review or inspection.

(1) If the director of building, planning and zoning determines that the application is not complete, the applicant shall be provided written notice identifying the items that are not complete.

(2) The 30-day time period is tolled when the application is rejected as incomplete. If within 30 days after the city has provided notice that the application is incomplete the applicant submits revisions to address the identified deficiencies, the director of building, planning and zoning shall have an additional five business days to review the application for completeness.

(c) Upon notification to the applicant that a complete application has been accepted, the city shall also notify the applicant as to whether the personnel employed or contracted by the city will be able to provide regulatory action within 30 days for plan review or provide inspection services within two business days of receiving a valid written request for inspection.

(d) If the city determines that the personnel employed by the city cannot provide regulatory action or inspection services within the time frames required under paragraph (b) of this section, the applicant shall have the option of retaining, at its own expense, a private professional provider to provide the required plan review or inspection in accordance with the provisions of this article. If the applicant elects to utilize the services of a private professional provider, the regulatory fees associated with such regulatory action shall be reduced by 50 percent and such reduced amount shall be paid to the city in accordance with the city's policies.

(e) If the city determines that the personnel employed by the city can provide regulatory action or inspection services within the time frames required under paragraph (b) of this section, a convenience fee not to exceed the full amount of the regulatory fees associated with such regulatory action shall be paid to the city in accordance with the city's policies. Upon payment in full of the convenience fees associated with the complete application, the applicant may nevertheless choose to retain, at its own expense, a private professional provider to provide the required plan review or inspection, subject to the requirements set forth in this article.

(f) If the city states its intent to complete the required plan review within the time prescribed by paragraph (b) of this section, or any extension thereof mutually agreed to by the applicant and the city, and the city fails to complete such plan review in the time prescribed by paragraph (b) of this section, or any extension thereof mutually agreed to by the applicant and the governing authority, the local governing authority shall issue the applicant a project initiation permit.

(1) The local governing authority shall be allowed to limit the scope of a project initiation permit and limit the areas of the site to which the project initiation permit may apply but shall permit the applicant to begin work on the project, provided that portion of the initial phase of work is compliant with applicable codes, laws, and rules.

(2) If the plans submitted for permitting are denied for any deficiency, the time frames and process for resubmittal shall be governed by subparagraphs (1) through (3) of paragraph (b) of section 10.4 below.

(3) Any delay in the processing of an application that is attributable to a cause outside the control of the city or through fault of the applicant shall not count toward days for the purposes of this article.

(g) Any plan review or inspection conducted by a private professional provider shall be no less extensive than plan reviews or inspections conducted by city personnel.

(h) The person, firm, or corporation retaining a private professional provider to conduct a plan review or an inspection shall be required to pay to the city the same regulatory fees which are required by either paragraph (c) or (d) of this section, as applicable.

History

The history line the source prints at the end of the section.

(Ord. No. 2021-10, § 1, 6-28-2021)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fort-oglethorpe/zoning/appendix-a-chapter-8-article-10-10.2@2026-03-26-e8f1112ce1

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.