Sec. 7.6. Final plat approval.

About this text

  • As published by Municode, current through 2026-03-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Final plat approval shall be obtained by the subdivider as the preliminary plat or portions of it are constructed or included in the posted surety. The final plat shall conform substantially to the preliminary plat as approved; and if submitted in portions, each portion shall conform to all requirements of these standards.

(b) The subdivider shall submit seven paper copies of the proposed final plat and a digital PDF to the building, planning and zoning department.

(c) The final plat shall contain all of the information which as required on the preliminary plat except the topographic contour lines shown on the preliminary plat and shall be drawn in compliance with all the appropriate laws of the state which govern the recordation of subdivision plats.

(d) The following certification shall be presented along with the final plat:

(1) Certification by a registered state land surveyor (seal affixed) of the accuracy of the survey and plat and the placement of all required monuments.

(2) Certification by the director of building, planning and zoning that the subdivider has complied with one of the following alternatives:

a. Constructed all roads, streets and other required improvements delineated in chapter 7 in accordance with the specifications and requirements of the city; or

b. Deposited cash or certified check, or posted a surety bond or irrevocable letter of credit with the director of building, planning and zoning director of building, planning and zoning in an amount sufficient to ensure completion of all required improvements.

(3) Certification by the subdivider showing that the applicant is the legal owner of the land, and that he formally dedicates all streets, roads and rights-of-way for public use.

(4) State department of transportation certification of approval must be included for the proposed project if the project abuts any state or federal right-of-way.

(5) Certification by the subdivider that all lands considered for development do not fall within the 100-year floodplain. If any part of the development falls within a floodplain or floodprone area, then the certification shall state that the following requirements shall apply:

a. The director of building, planning and zoning has established that:

1. The nature of the land use (i.e., recreational areas) would not lend itself to damage by water inundation to an appreciable extent;

2. The area will be filled or improved in such a manner to prevent such periodic inundation; or

3. Minimum floor elevations are required to prevent damage to buildings and structures.

b. The director of building, planning and zoning will require whatever additional engineering information he or she deems necessary to make a decision on any area of questionable drainage. Lakes, ponds and similar areas will be accepted for maintenance only if sufficient land is dedicated as a public recreation area, or if such area constitutes a necessary part of the drainage control system. Such park land will be subject to approval by the city council.

(e) When the plat has been approved by the director of building, planning and zoning, the following actions are required:

(1) One copy with the approval of the director of building, planning and zoning certified therein shall be returned to the subdivider to be used for filing with the clerk of the court as the official plat of record.

(2) Within ten working days from the date of final approval, the subdivider shall record the final plat in the office of the clerk of court.

(3) One copy containing all required certifications shall be retained by the director of building, planning and zoning, and one copy of the original tracing shall be given to the subdivider for his records.

(4) The director of building, planning and zoning must consider a final plat within 30 working days after the submission of the final plat. Failure of the director of building, planning and zoning to act on a final plat submission within these 30 working days shall be considered as approval of such submission. If the plat is disapproved, grounds for such disapproval shall be stated in writing by the director of building, planning and zoning and shall be stated in writing on two copies of the plat.

(5) One copy of the plat shall be retained in the director of building, planning and zoning's office, and one copy shall be returned to the subdivider at the time of the disapproval.

(f) Approval of a final plat by the director of building, planning and zoning shall not constitute automatic acceptance by the public of the dedication of any street or other public way or ground. However, after approval of the final plat and the construction of streets shown thereon, the director of building, planning and zoning public works director may recommend to the city council that it accepts these streets as public roads and take over their perpetual maintenance. After obtaining this approval, if the subdivider requests that the city council accept these streets as public streets, then the city council shall accept these streets as public roads and take over their perpetual maintenance.

History

The history line the source prints at the end of the section.

(Ord. No. 2021-10, § 1, 6-28-2021)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fort-oglethorpe/zoning/appendix-a-chapter-8-article-7-7.6@2026-03-26-9569b13939

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Fort Oglethorpe Zoning Ordinance, Sec. 7.6 (Appendix A, Chapter 8, Article 7). Final plat approval | Georgia Commons