Skip to content
Georgia Commons
Menu

Fulton County · Zoning Ordinance

Fulton County Zoning Ordinance

This document is shown whole, as one text: its source does not cut it into sections.

About this text

  • As published by Municode, current through 2026-08-05
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Part 5 of 5. This text is long, so its page prints it in parts, in the source's order. A link to one of its paragraphs leads to the part that holds it.

7. Standard informational signs. Each lot may display two standard informational signs without a permit, except that during a political election, each lot may display no more than

six standard informational signs during the period 90 days before the date of the election and the final

determination on each ballot issue or candidate.

8. Internal development signs. Internal development signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. Includes

but is not limited to signs such as parking lot information, directional, safety signs, and signs delineating internal sub-components of the over all development. Internal directional signs shall not exceed ten square feet in area and four feet in height.

D. Office-institutional and apartment-office districts (O-I and A-O) (article VIII, section 8.1 and Appendix A, Fulton County Zoning Resolution).

1. Freestanding signs.

a. One maximum 32 square foot, freestanding sign shall be permitted for each street on which the lot has less than 500 feet of

frontage. The sign shall have a maximum height of ten feet, may be externally illuminated, and shall not have changeable copy.

b. One maximum 64 square foot, freestanding for each street on which the lot has 500 or more linear feet of frontage. If the lot has two or more entrances on a street on which it has frontage, the one maximum 64 square foot sign may be substituted by two single-faced freestanding signs not to exceed 32 square feet. The sign shall have a maximum height of ten feet, may be externally illuminated, and shall

not have changeable copy. No more than two signs shall be allowed per frontage over 500 feet.

2. Wall sign. Wall signs are permitted on street-facing walls (including windows and doors). Businesses without a street on which there is frontage,

but which have exterior entrances to the building, are entitled to one wall sign on the exterior wall of the business where the primary entrance is located. Wall sign(s) shall not exceed

the smaller of five percent of the applicable wall area or 100 square feet, confined to the upper 30 feet of the facade. Wall signs shall not have changeable copy unless approved as a marquee sign. Each place of business is allowed a maximum of two wall signs. Only one sign is allowed

per wall. Wall signs shall face public streets and/or pedestrian-parking areas.

3. Internal freestanding signs. Internal freestanding signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. The freestanding sign shall not exceed 20 square feet in area and six feet in

height and shall not be legible by the traveling public from a public rightof-way.

4. Window signs. Not more than three window signs per unit shall be allowed and shall not be larger than four square feet or cover more than

25 percent of the area of each window in which a sign is placed, whichever is less. Such signs shall not be illuminated, except that one window

sign may be illuminated. Window signs shall not be counted toward the wall sign total square footage.

5. Awning/canopy signs. Awning/canopy signs may be displayed. A permit is required. The signs shall be deducted from allocated wall sign area.

The area of the sign shall not exceed ten percent of the area of the awning or canopy.

6. Flags. Each lot may display no more than three flags and/or flagpoles.

Flagpoles shall not exceed 20 feet in height. Flag size shall not be more than 20 square feet.

7. Standard informational signs. Each lot may display two standard informational signs without a permit, except that during a political election, each lot may display no more than

six standard informational signs during the period 90 days before the date of the election and the final

determination on each ballot issue or candidate.

8. Banners. Banners shall be allowed for a period not exceeding 14 days with no more than three such 14-day periods being permitted per calendar year per lot. In the case of lots which contain multiple businesses,

each business shall be allowed a banner. Banners shall not be more than 32 square feet. No banner shall be mounted so as to extend above the horizontal plane of the roof where the building wall and roof meet and shall not extend more than five feet above grade when on the ground.

9. Projecting signs. In a multi-tenant office building, in addition to all other permitted signs, one projecting nonilluminated sign per entrance used shall be allowed to identify the location of each tenant's premises. Projecting signs shall adhere to the following: does not exceed three square feet in area; is uniform in size, material, color and shape and is placed in an equivalent location to other

such signs located on the same building; is suspended from the eave or soffit of the building; and maintains

a minimum of seven feet clearance between the bottom of the sign and the walkway below.

10. Internal development signs. Internal development signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. Includes

but is not limited to signs such as parking lot information, directional, safety signs and directional signs associated with hospitals and other emergency care facilities. Internal directional signs shall not exceed ten square feet in area and four feet in height except that signs associated with hospitals and emergency care facilities shall not exceed 20 square feet in area.

E. Commercial, industrial park, and mixed use districts (C-1, C-2, M-1A, MIX) (article IX, article X, section 10.1, article VIII, section 8.2, Fulton County Zoning Resolution).

1. Freestanding signs.

a. One maximum 32 square foot, freestanding sign shall be permitted for each lot which contains less than three acres.

b. One maximum 44 square foot, for each lot which contains three or more, but not more than 15 acres.

c. For lots that contain more than 15 acres, one maximum 64 square foot, freestanding for each street on which the lot has primary frontage and one 32 square foot, freestanding sign for each street on which the lot has secondary frontage. If the primary frontage of the lot is 500 linear feet or more and if the lot has two or more entrances on the street on which it has primary frontage, the

one maximum 64 square foot sign may be substituted with two single-faced freestanding signs not to exceed 32 square feet. The sign shall have a maximum height of six feet if 32 square feet or less and eight

feet if 64 square feet or less and may be externally illuminated.

No more than two signs shall be allowed per development unless there is a secondary frontage.

d. All signs shall have a maximum height of six feet if 32 square feet or less, a maximum

height of eight feet or less if greater than 32 square feet, may be internally lighted, and shall not have changeable copy, except in association with motor vehicle fuel pricing. Each sign may have not more than

four tenant panels if 32 square feet or less, or not more than six tenant panels if greater than 32 square feet.

e. Within the mixed use (MIX) district one maximum 32 square foot, freestanding sign or two single-faced freestanding signs not to exceed 16 square feet for each side of a platted residential component's entrance shall be permitted.

2. Wall signs. Wall signs are permitted on street-facing walls (including windows and doors). Businesses without a street on which there is frontage,

but which have exterior entrances to the building, are entitled to one wall sign on the exterior wall of the business where the primary entrance is located. Wall sign(s) shall not exceed

five percent of the applicable wall area or 100 square feet, whichever is smaller. Wall signs shall not have changeable copy unless approved as a marquee sign or in association with motor vehicle fuel pricing. Each place of business is allowed a maximum of two wall signs. Only one sign per business is allowed per wall.

Wall signs shall face public streets and/or pedestrian-parking areas.

(Amended 5/7/08)

3. Wall signs, tenant over 50,000 square feet. A tenant that has over 50,000 square feet of gross floor space and has independent leased space within a shopping center shall be allowed wall signs not to exceed five percent of the applicable wall area or 300 square feet, whichever is smaller.

4. Menu sign. One menu sign as part of a drive-thru or drive-in facility. One menu sign shall be allowed per drivethrough lane.

5. Banner. Banners shall be allowed for a period not exceeding 14 days with no more than three such 14-day periods being permitted per calendar year per lot. In the case of lots which

contain multiple businesses, each business shall be allowed a banner.

Banners shall not be more than 32 square feet. No banner shall be mounted so as to extend above the horizontal plane of the roof where the building wall and roof meet, or shall not extend more than five feet above grade when on the ground.

6. Signs during construction. One additional sign shall be allowed during construction. The sign shall not be

internally illuminated. The sign shall be allowed beginning with the commencement of construction and ending with the issuance of a certificate of occupancy or installation of a permanent sign, whichever occurs first.

The sign shall not exceed the maximum freestanding sign allowed on the lot.

7. Out-of-store marketing device. Outof-store marketing devices shall be allowed, shall not exceed eight feet

in height, and shall not be illuminated except for illumination intrinsic to the device. No permit shall be required.

8. Flags. Each lot may display no more than three flags and/or flagpoles.

Flagpoles shall not exceed 20 feet in height. Flag size shall not be more than 20 square feet.

9. Entrance signs. In a multi-tenant commercial or office building, in addition to all other permitted signs, one projecting non-illuminated sign

per entrance used shall be allowed to identify the location of each tenant's premises. Projecting signs shall adhere to the following: does not exceed three square feet in area; is uniform in size, material, color and

shape and is placed in an equivalent location to other such signs located on the same building; is suspended from the eave or soffit of the building; and maintains a minimum of seven feet clearance between the bottom of the sign and the walkway below.

10. Window signs. Not more than three window signs per unit shall be allowed and shall not be larger than four square feet or cover more than

25 percent of the area of each window in which a sign is placed, whichever is less. Such signs shall not be illuminated, except that one window

sign may be illuminated. Window signs shall not be counted towards the wall sign total square footage.

11. Awning/canopy signs. Awning/canopy signs may be displayed. A permit is required. The area of the sign

shall not exceed ten percent of the area of the awning or canopy. The area of an awning/canopy sign shall be deducted from the allowable area of a wall sign. Changeable copy shall be allowed in association with motor vehicle fuel pricing.

12. Standard informational signs. Each lot having one business or residence may display two standard informational signs, and each lot having more than one business may display

four standard informational signs without a permit, except that during a political election, each lot may display no more than six standard informational signs during the period 90 days before the date of the election and the final determination on each ballot issue or candidate.

13. Projecting signs. In a multi-tenant commercial or office building, in addition to all other permitted signs, one projecting non-illuminated sign

per entrance used shall be allowed to identify the location of each tenant's premises. Projecting signs shall adhere to the following: does not exceed three square feet in area; is uniform in size, material, color, and

shape and is placed in an equivalent location to other such signs located on the same building; is suspended from the eave or soffit of the building; and maintains a minimum of seven feet clearance between the bottom of the sign and the walkway below.

14. Internal freestanding signs. Internal freestanding signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. The freestanding sign shall not exceed 20 square feet in area and six feet in

height and shall not be legible by the traveling public from a public rightof-way.

15. Internal development signs. Internal development signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. Includes

but is not limited to signs such as parking lot information, directional, safety signs and directional signs associated with hospitals and other emergency care facilities. Internal directional signs shall not exceed ten square feet in area and four feet in height except that signs associated with hospitals and emergency care facilities shall not exceed 20 square feet in area.

F. Industrial districts (M-1, M-2) (article X, sections 10.2 and 10.3 of the Zoning Resolution of Fulton County).

1. Billboards. Within industrial districts (M-1 and M-2), freestanding signs shall not exceed 672 square

feet and shall be located according to the following standards:

a. Along, and oriented toward, state numbered primary routes or national highways only;

b. At least 500 feet from all residential or AG-1 zoning districts;

c. Minimum 100-foot setback from right-of-way;

d. Minimum of 1,500 feet from any other billboards or freestanding sign, except standard informational signs;

e. The lot on which the billboard is located shall have sufficient area to accommodate the fall zone, and excepting the sign, no buildings, structures, or appurtenances shall be contained in the fall zone;

f. Be in compliance with applicable height standards for the district in which located.

2. Freestanding signs.

a. One maximum 32 square foot, freestanding sign shall be permitted for each street on which the lot has up to and including

500 feet of frontage. The sign shall have a maximum height of 20 feet and shall not have changeable copy.

b. One maximum 64 square foot, freestanding sign shall be permitted for each street on which the lot has more than 500 linear feet and up to 1,000 linear feet of frontage. The sign shall

have a maximum height of 20 and shall not have changeable copy.

c. One maximum 72 square foot, freestanding sign shall be permitted for each street on which the lot has more than 1,000

linear feet of frontage (excludes spin sites and out-parcels). The sign shall have a maximum height of 20 feet and shall not have changeable copy.

d. One maximum 32 square foot, freestanding sign per sign site or out-parcel which is identified on a site plan approved pursuant to a single zoning case.

The sign shall have a maximum height of eight feet and shall not have changeable copy.

3. Wall signs. Wall signs are permitted on street-facing walls (including windows and doors). Businesses without a street on which there is frontage,

but which have exterior entrances to the building, are entitled to one wall sign on the exterior wall of the business where the primary entrance is located. Wall sign(s) shall not exceed

five percent of the applicable wall area or 180 square feet, whichever is smaller. Wall signs shall not have changeable copy unless approved as a marquee sign. Notwithstanding the foregoing, an anchor tenant that has over 50,000 square feet of gross floor space within a shopping center shall be allowed wall signs not to exceed five percent of the applicable wall area or 300 square feet, whichever is smaller. Each place of business is allowed a maximum of two wall signs.

Only one sign is allowed per wall.

Wall signs shall face public streets and/or pedestrian-parking areas.

4. Menu sign. One menu sign as part of a drive-thru or drive-in facility. One menu allowed per drive-through lane.

5. Banner. Banners shall be allowed for a period not exceeding 14 days with no more than three such 14 day periods being permitted per calendar year per lot. In the case of lots which contain multiple businesses,

each business shall be allowed a banner. Banners shall not be more than 32 square feet. No banner shall be mounted so as to extend above the horizontal plane of the roof where the building wall and roof meet or shall not extend more than five feet above grade when on the ground.

6. Signs during construction. One additional sign shall be allowed during construction. The sign shall not be

internally illuminated. The sign shall be allowed beginning with the commencement of construction and ending with the issuance of a certificate of occupancy or installation of a permanent sign, whichever occurs first.

The sign shall not exceed the maximum freestanding sign allowed on the lot.

7. Out-of-store marketing device. Outof-store marketing devices shall be allowed, shall not exceed eight feet

in height, and shall not be illuminated except for illumination intrinsic to the device. No permit shall be required.

8. Flags. Each lot may display no more than three flags and/or flagpoles.

Flagpoles shall not exceed 20 feet in height. Flag size shall not be more than 20 square feet.

9. Projecting signs. In a multi-tenant commercial or office building, in addition to all other permitted signs, one projecting non-illuminated sign

per entrance used shall be allowed to identify the location of each tenant's premises. Projecting signs shall adhere to the following: does not exceed three square feet in area; is uniform in size, material, color and

shape and is placed in an equivalent location to other such signs located on the same building; is suspended from the eave or soffit of the building; and maintains a minimum of seven feet clearance between the bottom of the sign and the walkway below.

10. Window signs. Window signs are allowed without a permit and shall not occupy in the aggregate more than

25 percent of the window area. Window signs shall not be counted towards the wall sign total square footage.

11. Awning/canopy signs. Awning/canopy signs may be displayed. A permit is required. The signs shall be deducted from allocated wall sign area.

The area of the sign shall not exceed ten percent of the area of the awning or canopy. The area of an awning/ canopy sign shall be deducted from the allowable area of a wall sign.

12. Standard informational signs. Each lot having one business may display two standard informational signs, and each lot having more than one business may display four standard informational signs without a permit, except that during a political election, each lot may display no

more than six standard informational signs during the period 90 days before the date of the election

and the final determination on each ballot issue or candidate.

13. Internal freestanding signs. Internal freestanding signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. The freestanding sign shall not exceed 20 square feet in area and six feet in

height and shall not be legible by the traveling public from a public rightof-way.

14. Internal development signs. Internal development signs (signs not visible from a public right-of-way) are permitted adjacent to internal road(s) serving the development. Includes

but is not limited to signs such as parking lot information, directional and safety signs. Internal directional signs shall not exceed ten square feet in area and four feet in

height.

(Res. No. 08-0238, 5-7-08; Amd. No. 10-0679, pts.

1, 2, 7-7-10; Amd. No. 11-0478, 6-1-11; Res. No.

11-0743, 9-7-11; Res. No. 12-0556, 7-11-12)

33.26 Severability.

Should any article, section, clause, or provision of this article be declared by a court of competent jurisdiction to be invalid, such action shall not affect the validity of the ordinance as a whole or any part hereof other than the part so declared to be invalid, it being the intent of the county that each article, section, clause, and provision hereof be severable.

(Res. No. 08-0238, 5-7-08)

ARTICLE XXXIV. DEVELOPMENT

REGULATIONS

34.1 Scope and intent.

This article includes a variety of development related regulations which are designed to insure that development, and infrastructure additions and improvements are provided in the best interest of the health, safety and welfare of the citizens of Fulton County, and to assure that development regulations and review procedures are standardized and equitably applied.

34.2 Compliance.

Any land disturbance activity or any development activity must comply with the development standards of Fulton County along with any other

applicable local or state regulations. Compliance with the provisions of this article, and actions to bring about compliance with this article shall be in accordance with administrative guidelines of the Environment and Community Development Department. (Amended 11/3/93, 2/7/01)

34.3 Appeals.

The Director of the Environment and Community Development Department shall administratively consider variance appeals to

article XXXIV in accordance with article XXII, Appeals. (Amended 11/3/93, 2/7/01)

34.4 Permit and sign-off requirements.

These standards acknowledge or establish Fulton County requirements for permits for development of properties within the unincorporated area of Fulton County. All development shall comply with these and other requirements including, but not limited to, the Fulton County Tributary Buffer Ordinance, the Fulton

County Tree Preservation Ordinance and Administrative Guidelines, the Fulton County Sediment and Erosion Control Ordinance, and the Georgia Metropolitan Area River Protection Act.

34.4.1 Land disturbance permit prerequisites.

Prior to the issuance of a land disturbance permit or the issuance of a certificate of occupancy for each phase of development, the following documents shall be submitted to the Director of the Environment and Community Development Department for approval. (Amended 11/3/93, 2/7/01)

A. Site plan. A site plan which meets or exceeds the requirements contained herein and the Environment and Community Development Department administrative guidelines, and incorporates the following therein: (Amended 2/7/01)

1. A certified boundary description based on a survey of the entire property.

2. A graphic representation of those conditions of zoning which can be graphically represented. This is not intended to require that conditions of zoning be written-out on a site plan.

3. Zoning case number and other relevant file numbers.

B. Grading plan with phasing.

C. Erosion and sediment control plan. A separate sheet depicting erosion and sediment control measures as required by the State of Georgia.

D. Landscape/tree protection plan. A detailed landscape or tree protection plan for all required buffers, landscape strips, tree protection zones, and screened areas. If project completion does not coincide with an appropriate planting season, or if water prohibitions are in effect, a performance bond may be posted to delay planting until an appropriate time approved by the Fulton County Arborist.

(Amended 3/6/91, 03/03/04)

E. Storm water management plan. (Name Changed 7/7/93)

1. Evaluate the downstream ditch stability and bank erosion protection potential of existing downstream conveyance system. Provide all

necessary documentation to the Department of Public Works, Storm Water Management Section at construction drawing phase.

2. Contact the Department of Public Works, Storm Water Management Section to arrange an on-site evaluation as to the location of storm water facility, discharge path of

detention/retention pond and other downstream constraints.

3. The design discharge at the outlet of drainage system shall not result in velocities that equal/exceed the erosive velocity or the existing receiving channel/draw, unless dissipation and erosion protection measures are placed at the outlet. Said

documentation shall be provided to the Department of Public Works, Storm Water Management Section.

4. Provide downstream analysis of the flood discharge timing effect on the existing conveyance systems due to each storm frequency.

5. All natural streams within the limit of the project must be stable and be expected to remain stable under ultimate development or provide appropriate erosion protection for the streams subject to the approval of the Department of Public Works, Storm Water Management Section.

6. Evaluate the downstream effect from storm water management structures and the development, hydrologichydraulic engineering studies shall extend downstream to a point where

the proposed development represents less than ten percent of the total watershed to this point.

7. The result of the extended downstream point analysis (ten percent point) shall be included in the hydrologic study submitted with the storm water management plan.

Said documentation is subject to approval by the Department of Public Works, Storm Water Management Section.

8. Provide detention/retention as maybe required by Fulton County subject to the approval of the Department of Public Works.

9. The development site shall be graded in such a manner that the surface runoff does not affect down stream lots, flow through lots shall be collected and conveyed in appropriate storm drainage system. Documentation shall be provided at construction drawing phase.

10. Water intake and discharge points in a single-family residential development to be a minimum of 15 feet from any existing or proposed

residential structure and to be at a minimum of five feet above and/or five feet below any existing or proposed buildable area. (Added 9/1/ 99)

F. Other plans, as applicable.

1. Water and waste water plans.

a. Water and waste water systems constructed under the jurisdiction of Fulton County government shall abide by the department of public works.

b. Fulton County Public Works/ government does not guarantee the availability of water or waste water capacity.

c. Matters pertaining to septic systems shall be determined by the Fulton County Board of Health.

d. The project being proposed shall utilize one geographical information system (GIS) monument as the development's benchmark.

Furthermore, the developer shall abide by all provisions of the Fulton County nMonument Resolution,o as established by the Department of Public Works.

e. Matters pertaining to pump stations shall be pre-reviewed by the Department of Public Works, Engineering Support Services Division, with regards to current policy, prior to the submittal of project design drawings.

f. All appropriate fees shall be paid by the developer prior to the issuance of any land disturbance permits.

g. The developer is required to extend the water pipe line system across the entire length of road frontage, within the right-of-way.

h. At the time of design review, the Department of Public Works, Engineering Support Services Division may require the developer to connect (loop) the project to the adjoining property, for flow enhancement of the public water system.

i. Rerouting of existing water pipe lines and/or waste water pipe lines shall be pre-approved by the Department of Public Works, Engineering Support Services Division, prior to the submittal of project design drawings.

j. As part of the project, the developer is required to network the waste water pipe line system to all upstream properties.

k. Easements dedicated to Fulton County government shall abide by all established standards.

All easements shall be obtained and approved by the Department of Public Works, Engineering Support Services Division.

l. Conflicts, with other review disciplines of Fulton County government shall be submitted to and resolved by the Department of Public Works, Engineering Support Services Division.

2. Profiles of roads and sewers.

3. Traffic signs and striping.

4. Standard construction details.

5. Proposed permanent stormwater management plan.

6. A traffic impact mitigation plan which details an owner's or developer's plan to address the number of trips that their development will produce when such development is within one mile of a roadway operating at a level of service D or lower as established by the Department of Public Works. This plan shall include, but is not limited to roadway improvements including costs and other proposals such as providing transit access, transit use incentives, car/van pooling, bicycle path construction, internal sidewalk construction, and lunch trip reduction, which when combined mitigate the traffic impact of the proposed development and shall also include a time table for the construction/ implementation of improvements and who will be financially responsible for them.

(Added 4/3/02)

G. Permits, agreements, studies as applicable.

1. An approved curb cut permit from the Georgia Department of Transportation or the Fulton County Development Services Department.

2. Board of health approvals.

3. Right-of-way dedication.

a) Property owners be required to dedicate at no cost to Fulton County, along the entire frontage, sufficient right-of-way to provide a minimum 10.5 foot

shoulder behind any required project improvement subject to the approval of the director of public works.

4. Off-site transportation improvement funds and agreements.

5. Fire department approval.

6. Sanitary sewer pre-treatment approval.

7. Siltation Study. (Added 3/4/92, Amended 7/7/93, 11/3/93, 2/7/01)

a. At the discretion of the Director of the Environment and Community Development

Department, submit prior to the issuance of a land disturbance permit and prior to recording of the final plat for each phase of development, base siltation studies of any water bodies located on the development site and on adjacent properties. Said studies shall identify, for removal by the applicant, prior to recording of the final plat for each phase of development, all

siltation resulting from the development. (Amended 2/7/ 01)

b. At the discretion of the Director of the Environment and Community Development

Department, prior to the recording of the final plat for the final phase of development,

submit a performance bond for the removal of any siltation resulting from the development. The performance bond shall remain on file in the Environment and Community Development Department until release of the occupancy certificates for a minimum of 90 percent of all residences permitted pursuant to the development or three years from the date of the first certificate of occupancy, whichever is earlier. (Amended 2/7/01)

34.4.2 Prerequisite to occupancy permit inspection. The Public Works Department and/or the Inspections and Zoning Enforcement Department shall notify the Environment and Community Development Department in writing of holds on the issuance of a certificate of occupancy

on a project. (Amended 11/3/93, 2/7/01)

A. Single-family residential. Before a certificate of occupancy may be considered by the Environment and Community Development Department for any dwelling located in a subdivision, the items listed under pBp., below, must have been

signed-off on by the Environment and Community Development Department as complete for that phase of the subdivision in which a dwelling is located.

(Amended 2/7/01)

B. All structures except single-family residential. Before a certificate of occupancy may be considered for a structure, including the first of several structures within a development, the following must have been signed-off on as complete by the Environment and Community Development Department:

(Amended 2/7/01)

1. Required landscaping.

2. Required buffers.

3. Required tree protection measures.

4. Required walls and fences.

(Amd. No. 09-0766, pt. 3, 8-5-09) 34.4.3.7(g) Siltation study. See section 34.4.1(G)(7) (Moved 7/7/93) (Ord. No. 18-0340, Att. A, 5-16-18)

34.5 Site improvement standards.

These standards shall regulate site improvement, and the provision of amenities related to site improvement.

34.5.1 Off-street parking. Property owners shall provide and maintain off-street parking throughout construction. Parking on any lot other than the lot for which a building permit is issued must be approved for a temporary parking lot by the Environment and Community Development Department. (Amended 11/3/93,

2/7/01)

34.5.2 Interparcel access. Interparcel access shall be provided to adjacent properties upon determination by the Director of the Environment and Community Development Department that such access is in the best interest of the

public health, safety or welfare. (Amended 11/3/ 93, 2/7/01)

34.5.3 Sidewalks/curb and gutters. (Amended 11/03/93, 02/07/01, 03/03/04, 04/05/06) Sidewalk, curb and gutter shall be provided for all development projects as determined by the Department of Environment and Community Development.

When required, sidewalk, curb and gutter shall be constructed in accordance with the Department of Public Works Standard Plans (also known as Standard Details).

34.5.4 Detention/retention. On-site storm water detention facilities shall not be located within any required buffer or landscape strip. Detention

facilities shall not be located within parking or loading areas unless approved by the department of public works. A minimum 20-foot wide landscape strip planted to buffer standards shall be provided around the exterior of the detention area

outside of the access easement or as may be approved by the Fulton County Arborist. (Added 3/6/91) (Amended 07/07/93, 04/05/95, 11/03/04)

34.5.5 Compliance with tree preservation ordinance. Prior to applying for a land disturbance permit, the owner shall arrange with the county

arborist, through the Director of the Environment and Community Development Department, for an on-site evaluation of existing specimen trees and stands of trees, and an evaluation of buffers and tree protection zones. At a minimum, the tree density requirements prescribed by the Fulton County Tree Preservation Ordinance Administrative Guidelines shall be provided and permanently maintained. (Added 4/7/93, Amended 11/3/ 93, 2/7/01)

34.5.6 Subdivision access. Any subdivision of land for single family that has new roads providing direct access to the lots within the subdivision shall be limited to newly constructed internal

roads. (Added 9/4/91)

34.5.7 Minimum setback for new street. The right-of-way for new streets must be located a minimum of 50 from any peripheral property line adjoining AG-1 and residentially zoned property unless interparcel access is required. (Added 12/ 4/91)

34.5.8 Arborist notification. Contact the Director of the Environment and Community Development Department, prior to the application for a land disturbance permit, to arrange with the

county arborist an on-site evaluation of existing specimen trees/stands, buffers, and tree protection zones within the property boundaries and otherwise to ascertain compliance with the Tree

Preservation Ordinance. (Added 12/4/91, Amended 4/7/93, 11/3/93, 2/7/01)

34.5.9 Dams. All dams within the jurisdiction of Fulton County shall comply with the provisions of the Safe Dam Act and Rules of Georgia Department of Natural Resources.

34.5.10 Development in or near a transmission line easement. (Added 8/4/99, Amended 06/04/14)

A. Definitions. Words and phrases used in this article shall have the meanings set forth in this section. Words and phrases not defined in this section, but defined in the Zoning Resolution of Fulton County, shall be given the meanings set forth in such resolution. All other words and phrases shall be given their common, ordinary meaning, unless the context clearly requires otherwise. Section headings or

captions are for reference purposes only and shall not be used in the interpretation of this article.

Consultation zone. An area within 500 feet from a transmission line easement.

Development permit. For the purposes of the consultation zone requirements, any permit for activity that involves construction, grade modification, excavation, blasting, land clearing, or the deposit of earth, rocks or other materials that places an

additional load upon the soil. Construction that involves work totally within an existing building footprint, such as residential remodeling projects, is specifically exempted from these consultation zone

requirements.

Environmental justice working group. A board of commissioners established group of key personnel from Fulton County departments and agencies whose activities relate to or impact environmental justice

matters.

New construction. Construction after June 2, 2014 of a structure intended for human occupancy, and includes the construction of a new structure, the construction of an addition to an existing structure and the reconstruction of a portion of an existing structure. The term excludes an addition to or the reconstruction or replacement of a structure existing on June 2, 2014 used for:

1. Single-family residential use;

2. Townhouse use;

3. Duplex, triplex or quadruplex use;

4. Multi-family residential use;

5. Mobile home residential use; or

6. Nonresidential buildings occupied by human beings.

Person. Any individual, firm, joint venture, entity, partnership, corporation, association or cooperative.

Planning area. The area within 300 feet of a transmission line easement.

Restricted pipeline area. The area within 40 feet of a transmission line easement and the area within a transmission line easement.

Transmission line. See article III, section 3.3.20.

Use requiring evacuation assistance. A land use which includes the following:

1. Congregate living;

2. Convalescent services;

3. Detention facilities;

4. Day care services (commercial);

5. Hospital;

6. Medical offices exceeding 5,000 square feet of gross floor area;

7. Private primary educational facilities;

8. Private secondary educational facilities;

9. Public primary educational facilities;

10. Public secondary educational facilities; and

11. Retirement housing development.

B. Consultation zone.

1. Consultation zone distance.

a. A consultation zone is hereby established for any parcels within 500 feet from a transmission line easement.

2. Consultation zone notification.

a. At application for a development permit, zoning or use permit, Fulton County staff shall notify the individual that they

are within the consultation zone, explain the relevant application procedures, and provide contact information for the applicable pipeline operator(s).

This same procedure shall be followed whenever an individual inquires about development regulations or zoning restrictions for property within the consultation zone.

b. A complete application for a development permit, zoning or use permit within a designated consultation zone must include written verification from the applicant that:

1. Applicant has contacted the pipeline operator(s) and has provided them with documentation detailing the proposed development type and place of the activity; and

2. The pipeline operator(s) has reviewed the documents;

3. The written verification required by this section can be in any form acceptable

to the director of the department planning and community services, including electronic communications, so long as it is clear that the pipeline operator(s) has received and

reviewed documentation showing the proposed information concerning any impact the activity will have upon the integrity of the transmission line(s).

The verification should include all comments received from the operator or a notice from the operator indicating that the operator has no comments;

4. If the operator does not respond within 30 days after being contacted and provided information by the developer pursuant to b.1. above, then the director of planning and community services may waive the requirement for written verification given under b.3. above.

C. Planning area.

1. Whereas a proposed use within a consultation zone requires notification to and a review by the pipeline operator(s), additional procedures are

required in planning areas based upon characteristics of the transmission line(s) and potential for impact to people and property. Planning areas are hereby established within 300 feet of transmission line(s) easement.

2. Application process within a planning area.

a. At application for a development permit, zoning or use permit, Fulton County staff shall notify the individual that they

are within the planning area and explain the relevant requirements.

b. Development within the planning area shall meet the requirements under section D (Development near a transmission line) below.

c. The plat must provide a note that all existing transmission lines or transmission line facilities through the residential or commercial development have

been shown, or that there are no known transmission lines or transmission line facilities within the limits of the residential or commercial development.

d. The location of all transmission lines and related easements shall be shown on all preliminary plat, zoning, building, and record plat maps when proposed development is within the planning area.

D. Development near a transmission line.

1. A use requiring evacuation assistance is prohibited in a structure intended for human occupancy that

is located within the 300-foot planning area. This prohibition does not apply to a structure that is located

between 40 and 300 feet of a pipeline if the Fulton County Environmental Justice Working Group determines, after receiving a recommendation from the fire marshal, that:

a. The structure has a performance-based design that provides an adequate time period for occupant evacuation to a

safe place in the event of a transmission line leak or fire associated with the transmission line, after considering:

1. The requirements of the current adopted edition of the National Fire Protection Association 101 Life Safety Code and International Fire Code;

2. The site and structure design;

3. The structure's building materials;

4. The structure's distance from the transmission line;

5. The use of radiant energy barriers;

6. Access to the site and the structure by emergency responders;

7. Available on-site resources for emergency responders;

8. The topography and other natural features;

9. The use of the structure;

and

10. The evacuation capability of the occupants.

b. The structure incorporates a system for the early detection and notification of a transmission

line leak, if the fire chief determines that an appropriate system is commercially available.

2. A person may not build new construction within 125 feet of a transmission line easement unless the fire marshall determines that:

a. The new construction has a performance-based design that provides a minimum one-hour time period for occupant evacuation

to a safe place in the event of a transmission line leak or a fire associated with the transmission line, in accordance with the current adopted edition of

the National Fire Protection Association 101 Life Safety Code and International Fire Code;

and

b. The new construction incorporates a system for the early detection and notification of a

transmission line leak, if the fire chief determines that an appropriate system is commercially available; or

c. The new construction complies with the standards for construction near a transmission line prescribed by the Fire Criteria

Manual.

3. A person may not place a structure or excavate within a restricted pipeline area. This prohibition does not apply to:

a. The transmission line or an appurtenance;

b. A facility that produces, consumes, processes, or stores the product transported by the

transmission line, including a power generation facility;

c. A utility line that crosses the restricted pipeline area, including an appurtenance to the line;

d. A utility service connection;

e. A road;

f. A surface parking lot; or

g. A structure or excavation that the director determines does not disturb the transmission line or impede its operation. The director in his/her determination shall consult Appendix A - Appropriateness of Proposed

Land Uses within a Transmission Line Easement and section 4. below, to assist in the final determination.

4. Before a person may place a road, surface parking lot, structure, utility line or otherwise excavate in a restricted pipeline area, the person must:

a. Deliver to the director a certification by a registered engineer stating that the proposed construction activity and structure are designed to prevent disturbing the transmission line or impeding its operation; and

b. Provide notarized documentation that the pipeline or trans mission line easement owner

has been notified of the proposed development activity.

5. If a proposed use is subject to any required determination in sections 1 through 4 above, the county's response and the results of the review will be provided to the applicant

within ten business days of the county's acceptance of the complete application package. The office of planning and community services in collaboration with Fulton County Fire and Rescue shall determine when such submissions are deemed complete.

E. Platting transmission lines/pipelines.

1. A developer shall determine whether a transmission line crosses a proposed development.

2. A developer shall depict on the plat a restricted pipeline area, if any.

3. A residential lot that is less than one acre in size may not include a restricted pipeline area.

4. A person may not place a structure or excavate within a restricted pipeline area. This prohibition does not apply to:

a. The transmission line or an appurtenance;

b. A facility that produces, consumes, processes, or stores the product transported by the

transmission line, including a power generation facility;

c. A utility line that crosses the restricted pipeline area, including an appurtenance to the line;

d. A utility service connection;

e. A road;

f. Surface parking lot; or

g. A structure or excavation that the director determines does not disturb the transmission line or impede its operation.

5. Before a person may place a road, surface parking lot, or utility line in a restricted pipeline area, the person must:

a. Deliver to the director a certification by a registered engineer stating that the proposed construction activity and structure are designed to prevent disturbing the transmission line or impeding its operation; and

b. Provide notarized documentation that the pipeline or transmission line easement owner has been notified of the proposed development activity.

F. Severability. Should any article, section, clause, or provision of this article be declared by a court of competent jurisdiction to be invalid, such action shall not affect

the validity of the ordinance as a whole or any part hereof other than the part so declared to be invalid, it being the intent of the county that each article, section, clause, and provision hereof be severable.

G. Effective date. This ordinance shall be in full force and take effect from and after the date of its final passage and approval.

H. Savings. Nothing contained herein shall in any manner be deemed or construed to alter, modify, supersede, supplant or otherwise nullify any other ordinance of the county or the requirements thereof whether

or not relating to or in any manner connected with the subject matter hereof, unless expressly set forth herein.

APPENDIX A - Appropriateness of Proposed Land Uses within a Restricted Pipeline Area The purpose of this table is to increase awareness and encourage early communication among key stakeholders when considering changes to an existing land use or new land use development within an existing restricted pipeline area.

This table provides a list of common land use activities and is only meant to provide guidance to those tasked with determining whether the proposed land use is acceptable or not. There will be variances in the application of these rules from operator to operator based on site-specific conditions, operator practices, and evolving safety regulations and concerns. Therefore, this table should be referenced only for general informational purposes. Stakeholders should consult with the appropriate pipeline operator for acceptable land uses within a restricted pipeline area.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Agriculture - (Seasonal Agricultural Crops - excludes orchards and vineyards) Yes, but consent is required Activities related to the growing of crops or the raising of animals need no consent, provided the activity does not involve installation of permanent structures or an increase or decrease in the cover over the transmission line. Facilities such as underground and overhead irrigation systems must be reviewed for compatibility.

With prior approval from the transmission line operator, grass and certain types of shrubs or seasonal crops may be permitted within the right-ofway (ROW), provided that the plantings do not interfere with the maintenance, inspection and operation of the transmission line and related facilities.

Airstrip - Private (perpendicular crossing to transmission line) Yes, but consent is required Permission to use the easement for an airstrip may be granted, provided it is for the private use of the property owner, and does not involve any increase or decrease in the cover over the transmission line or the installation of any permanent structures, including paving, on the easement.

These airstrips are considered to be dirt. This use can lead to a decrease in ground cover.

Airports - Public No These runways are constructed of concrete. Therefore, the need for access for transmission line maintenance and

emergency response activities preclude this use. In addition, most airports have restricted access for security reasons.

All-Terrain Vehicle (ATV) Use No Occasional use such as farm equipment may be acceptable.

This use can lead to a decrease in ground cover.

Athletic Stadium (e.g., baseball field, football field, running tracks, etc.)

No Even fields with no permanent structures may define the area as a high consequence area (HCA), thus imposing additional integrity management requirements for the gas transmission line operator.

Automobile Wrecking Yards No Access for transmission line maintenance and emergency response activities preclude this use.

Blasting No Not allowed on easements or fee land where any transmission line facilities are installed. Exceptions are for construction of another approved activity, subject to transmission line operator's

engineering review for technique, size of holes, spacing, etc.

Blasting activities may cause stresses on nearby transmission lines which may lead to leaks.

Buildings No No type of permanent structure permitted. See also "Structures".

No structures are allowed because they interfere with emergency response, maintenance, inspection, and repair activities.

Campsites No This use may impose additional integrity management requirements for the transmission line operator. In addition, no fires would be allowed for safety reasons.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Canopies/temporary (Categorized as party tents, canvas awnings, or portable coverings for group gatherings) No This use could involve driving large stakes into the ground near the transmission line, exposing it to potential damage and future leaks.

Canopies/permanent (Categorized as weather and environmental shelters such as those over gas stations and emergency room/hospital entrances, and drivethrough covers for banks, pharmacies, fast-food restaurants, etc.)

No Structures may interfere with emergency response, maintenance, inspection, and repair activities. Canopies may entrap gases and vapors that could find ignition sources from vehicle or pedestrian activities. Concrete under canopies could cause gas to migrate to building in the event of a failure.

Carports, permanent No No type of permanent structure permitted. See also "Structures".

Access for transmission line maintenance, inspection, and repair activities preclude this use.

Catch Basins (Storm sewer inlet) No Access for transmission line maintenance, inspection, and repair activities preclude this use.

Cathodic Protection Devices Yes, but consent is required Cathodic protection facilities may be installed provided they are coordinated with other utilities and all interference problems are eliminated.

Their use should be approved by the transmission line operator's cathodic protection department.

To ensure adequate cathodic protection for all transmission lines, routine testing should be scheduled and performed by qualified personnel to prevent interference issues.

Cemetery No Access for transmission line maintenance, inspection, and repair activities preclude this use.

Concrete Slabs (Categorized as for foundation, typically poured for permanent structure, equipment, or storage location).

No Not recommended except where they may be installed to provide for transmission line protection from thirdparty damage (submit plans for review) or for easement across ROW (such as for driveways or roads). (See

also Roads, Driveways, Road Crossing, and Structures.)

Access for transmission line maintenance, inspection, and repair activities preclude this use.

Driveways Yes, but consent is required Transmission line operator engineering review required for all proposed streets, roads and driveways to ensure transmission line cover is adequate to support the load from the road crossing. Additional cover, concrete, or other forms of mechanical protection may be required to ensure the transmission line does not incur damage as a result of this use and traffic loads.

Dumps No This use would not allow transmission line operator easy access for transmission line maintenance, inspection, and repair activities.

Erosion Control Yes, but consent is required Structures or materials to prevent soil erosion due to wind or water may be located on the transmission line ROW provided: 1) They do not interfere with the installation, operation or maintenance of the transmission line.

2) The design has been approved by the transmission line operator's engineering and environmental departments. 3) The facilities have taken into account the effect of the environment of the area.

Placement of structures and material must allow for transmission line maintenance, inspection, and repair activities to be conducted by the operator, as well as allow for emergency response access.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Exploration - Geologic and Geophysical Yes, but consent is required Subject to proper indemnification and site cleanup. Must be approved by transmission line operator's operations or engineering department. Also see Blasting, Construction Equipment,

and Wells.

3D seismic studies, depth of cover, transmission line operating stress levels, and other factors must be considered. The vibrations used to create the sound waves for these exploration

activities are quite intense and may compromise the integrity of the transmission line, leading to leaks if not properly evaluated.

Fences - Parallel to ROW Yes, but consent is required (General) No masonry or brick fences are allowed. In addition, fences and transmission line should be separated by adequate distance to allow for potential future repairs. Adequate access to and around transmission line facilities must be maintained.

Fences must not interfere with access for transmission line maintenance, inspection, and repair activities.

Fences - Perpendicular to ROW Yes, but consent is required (General) No masonry or brick fences are allowed. Adequate access to and around transmission line facilities must be maintained. Transmission line company retains the right to require the installation of a gate in the fence with a corporation lock where

necessary to maintain such access.

Gates should be wide enough to allow transmission line operator's equipment to gain access for repairs and emergencies. Fence posts must not be

installed directly over transmission line. Fences should be installed to allow for easy removal during emergency response. One-call notification required for fence construction.

Fences must not interfere with access for transmission line maintenance, inspection, and repair activities. Additional requirements may be imposed to protect transmission line from damage during construction.

Flammable Material No Managed burns for controlling vegetation may be performed by organizations such as BLM or DNR or by farmers, but this activity must be coordinated with transmission line operator to ensure public safety. No combustible material is to be stored on the easement.

For safety reasons no flame or fire associated with an incineration process or with flammable material storage is

allowed due to the combustible material transported in the transmission lines.

Flood Control Yes, but consent is required Transmission line operator engineering review can be made to consider buoyancy and ensure transmission line is adequately protected.

Flooding Yes, but consent is required If there is a possibility of periodic flooding, buoyancy of transmission line must be considered.

Intentional flooding is prohibited because it can cause stresses on the transmission line leading to integrity

issues; buoyancy must be considered.

Golf Courses Yes, but consent is required May be allowed if no permanent structures are placed on ROW.

Cover must be adequate and must allow for maintenance, inspection, and repair activities.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Highways Yes, but consent is required Easements should be granted for highway construction although operator may request reimbursement for the cost of protecting, upgrading or

relocating the transmission line so that it complies with all applicable regulations and requirements. Where a highway is widened to take in an area where the transmission line operator has a prior ROW, the transmission line operator may require reimbursement for that portion of the work that falls in the area where the

company has prior rights.

Transmission Line cover must be adequate to support the load from the highway to ensure the transmission

line does not incur damage. Review by the transmission line operator's engineering group is required for all proposed streets, roads, and driveways to ensure transmission line cover is adequate to support the load from the road crossing. Additional cover, concrete, or other forms of mechanical protection may be required to ensure

the transmission line does not incur damage as a result of this use and traffic loads.

Hiking Trails Yes, but consent is required Provided reasonable access to facilities is maintained. See also Landscaping and Cuts and Fills.

Trails must be placed to allow transmission line maintenance, inspection and repair activities to be conducted.

Horseback Riding Trails Yes, but consent is required Provided adequate access to facilities is maintained. See also Cuts and Fills.

Trails must be placed to allow transmission line maintenance, inspection and repair activities to be conducted.

Incinerators No For safety reasons, no flame, fire, or flammable material is allowed.

Junk Yards No This use would not allow transmission line operators easy access for transmission line maintenance, inspection, and repair activities.

Landscaping Yes, but consent is required Provided reasonable access to transmission line facilities is maintained.

See Cuts and Fills for earthwork requirements. In addition, shrubs should not interfere with transmission

line patrolling or inspection activities.

See Tree Farms for tree limitations.

With prior approval from transmission line operator, flower beds, lawns, and gardens may be permitted within

the ROW, provided that the plantings do not interfere with the maintenance, inspection and operation of the transmission line and related facilities.

Leach Fields No (General) Piping leading to leach field may cross the transmission line (see Pipelines). The entire leach field must be outside of the ROW. Before being granted permit for piping, owner must show proof of permit that installation will meet all State and local water quality requirements.

Leach field would be subject to damage by passage of heavy equipment.

Therefore, repair activities preclude this use. Also, there are integrity concerns that water can cause transmission line corrosion and lead to failures.

Loading Ramps No See also Concrete Slabs Stresses on transmission line can lead to integrity issues; also, this use does not allow for transmission line maintenance and inspection activities.

Masonry Work No This use does not allow for access for transmission line emergency response and maintenance.

Mini-Golf Courses (putt-putt courses) No May be allowed with prior consent if no permanent structures are placed on ROW and green space for transmission line easement is included.

Use must not interfere with transmission line maintenance and inspection activities. This use may define the

area as a HCA, thus imposing additional integrity management requirements for the gas transmission line operator. In addition, no permanent

structures are to be placed on the

ROW.

Mobile Home Parks No Structures are not recommended because they interfere with transmission line emergency response, maintenance, inspection, and repair activities. Also, they increase the risk for transmission line operators.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Mobile Home - Single Unit No No permanent structure may be installed on ROW.

No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection, and repair activities. Also, they increase the risk for transmission line operators.

Model Airplanes Yes, but consent is required Model airplanes may be flown over the ROW, but no permanent facilities may be located on the ROW.

Transmission line operator must know of this activity to ensure there is no interference or danger when performing aerial leak patrols.

Orchards No Tree root structures may be deep and extend beyond tree canopies. These roots can be severe and damage transmission line coating, leading to corrosion and leaks.

Parking Yes, but consent is required A private property owner may park vehicles used in his work (such as farm equipment) on the transmission line ROW but not over the transmission lines. Use of the easement as a commercial or other publicly used

parking lot, whether paved or unpaved, should be discouraged and not be allowed without review. The transmission line company will not accept liability for damages to the parking

facility caused by the exercise of its rights under the easement, and reserves the right to prohibit vehicular parking on its easement at any time.

Transmission line companies conduct maintenance activities on a frequent basis. Parking vehicles on the ROW may interfere with some of these maintenance practices.

Parks Yes, but consent is required The ROW may be used as part of a park area, but permanent structures may not be located on the ROW. Specific plan review required.

Use must not interfere with transmission line maintenance and inspection activities. This use may define the

area as a HCA, thus imposing additional integrity management requirements for the transmission line operator. In addition, no permanent structures are to be placed on the

ROW.

Patios No No structures are allowed because they interfere with transmission line emergency response and repair activities and increase risk for transmission line operators.

Pipelines Yes, but consent is required Permits generally are granted for other pipelines to cross a transmission line ROW, provided: 1) Crossing is kept as close to a right angle as possible. 2) The crossing pipeline maintains clearance approved by operator above the transmission line below the

transmission line. Pipeline crossings above the transmission line should be strongly discouraged. 3) Installation makes provisions for future use of transmission line ROW. 4) Precautions are taken to protect both facilities from interference problems due to cathodic protection. 5) Crossing pipeline meets all Federal, State and local requirements with respect to safety

and environment. 6) Parallel encroachments are not allowed (See "Utilities Parallel").

Significant design, construction, and maintenance code activities are performed to ensure the safety of the public and employees near transmission lines. These design, construction, and maintenance activities also ensure the integrity of the transmission lines. Additional construction requirements may be imposed to protect the transmission line and allow future

maintenance activities to be performed.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Play Equipment Yes, but consent is required No permanent structure may be installed on ROW. Play equipment without embedded footings or foundations may be allowed.

Use must not interfere with transmission line maintenance and inspection activities. This use may define the

area as a HCA, thus imposing additional integrity management requirements for the transmission line operator. In addition, no permanent structures are to be placed on the

ROW.

Porches No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities. Also, they increase the risk for transmission line operators.

Power Lines Yes, but consent is required Power lines may be installed across the ROW provided: 1) Poles or towers are not located on the ROW. 2) Wires have adequate clearance to permit working on the transmission line. 3) Parallel encroachments of above or below ground power lines are not allowed (See "Utilities - Parallel"). 4) Power lines are not located within 200

feet of a blow-down stack. 5) Buried power lines meet transmission line operator standards.

Engineering review and field monitoring can be performed to ensure no corrosion issues develop and lead to failures.

Private Landowner Crossing of Transmission Line Yes, but consent is required Where a private landowner crosses the transmission line with a buried structure, a consent letter usually will be required. Permits usually will be granted for crossing provided: 1) Crossing structure is kept as close to a right angle as possible. 2) Crossing structure maintains at least one-foot clearance above the transmission line or two feet below the transmission line. Crossings above the transmission line should be strongly discouraged. 3) Installation makes provisions for future use of the ROW. 4) Precautions are taken to protect both facilities

from interference problems due to cathodic protection. 5) Crossing structure meets all Federal, State and local requirements with respect to safety

and environment. 6) Parallel encroachments are not allowed. (See "Utilities Parallel").

Additional construction requirements may be imposed to protect the transmission line and allow future maintenance activities to be performed.

Pumps No Failure of equipment could elevate risks; permanent structures do not allow for easy access for transmission line emergency response.

Pump Islands (Categorized as fuel pumps for automobile service stations - general transportation refueling stations) No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection, and repair activities. Also, they increase the potential consequences if a failure occurs.

Quarries and Strip Mining No Quarrying activities not on but in proximity to the ROW should be brought to the attention of the transmission line company for assessment of potential impacts to the integrity of

the ROW and transmission line facilities (See Blasting).

This activity limits access for transmission line emergency response.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Railroads Yes, but consent is required Railroad crossings are permitted, provided the railroad company agrees to pay the cost to upgrade or protect the

transmission line. Clearances must be provided as required in Cuts and Fills.

Transmission line cover must be adequate to support the load from the railroad crossing to ensure the transmission line does not incur damage;

vibrations need to be properly evaluated for cyclic fatigue to ensure the integrity of the transmission line is

not compromised, leading to leaks.

Review by the transmission line operator's engineering group is required for all proposed railroad crossings to

ensure the transmission line cover is adequate to support the load from the crossing. Additional cover, concrete, or other forms of mechanical protection may be required to ensure the transmission line does not incur damage as a result of this use and traffic loads.

Recreation Areas Yes, but consent is required ROW may be used for general recreation that does not require the use of any permanent structures or facilities.

Use must not interfere with transmission line maintenance and inspection activities. This use may define the

area as a HCA, thus imposing additional integrity management requirements for the transmission line operator. In addition, no permanent structures are to be placed on the

ROW.

Retaining Walls Yes, but consent is required Provided adequate access to facilities is maintained and Cuts and Fills criteria is maintained. All retaining walls on the ROW must be approved

by transmission line operator's operations or engineering department.

Transmission line cover must be maintained to protect the transmission line, and the use would have to allow for transmission line maintenance and emergency response activities to be completed.

Rifle Ranges No Limited use may be allowed to access rifle range area across the ROW but no permanent facilities may be located on the ROW.

Transmission line systems include above ground facilities that may incur damage from rifle range fire.

Road - Parallel Yes, but consent is required Plans must be approved by the transmission line company's operations or engineering groups. Road easement is

subordinate to the transmission line company's easement. In addition, road and transmission line should be separated by adequate distance to allow for potential future repairs.

Use must allow for transmission line maintenance, inspection, and emergency response activities.

Road Crossings - Private Yes, but consent is required Consent usually will be granted for private roads across the ROW provided: 1) Assurance is given the road will remain a private road. It must be

so marked and signs must be maintained. 2) Road must not be given a hard surface. 3) Cut and Fill requirements must be maintained. 4) Road owner must agree to pay cost of protecting or upgrading the transmission line if the road should be paved or

status is changed to a public road.

Review by the transmission line operator's engineering group required for all proposed streets, roads, and driveways to ensure transmission line cover is adequate to support the load

from the road crossing. Additional cover, concrete, or other forms of mechanical protection may be required to ensure the transmission line does not

incur damage as a result of this use and traffic loads.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Road Crossings - Public Yes, but consent is required Consent generally will be granted for a public road or street across the ROW provided: 1) Developer pays for cost of protecting, upgrading or relocating the transmission line. 2) Transmission line company retains prior rights on roads dedicated to the state,

county or city.

Review by the transmission line operator's engineering group required for all proposed streets, roads, and driveways to ensure transmission line cover is adequate to support the load

from the road crossing. Additional cover, concrete, or other forms of mechanical protection may be required to ensure the transmission line does not

incur damage as a result of this use and traffic loads.

Septic Tanks No Access for transmission line repair activities preclude this use.

Service Stations No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities.

Signs No Signs, except pipeline markers, are not permitted on the ROW.

Foundation or embedded footings could damage the transmission line coating, leading to integrity and corrosion issues.

Sprinkler Systems (underground) Yes, but consent is required Crossings of transmission line must be kept to a minimum. Sprinkler heads should be set outside of the ROW. Due consideration must be given to cathodic protection interference.

There is concern that water can cause corrosion and lead to failures (transmission line operator's operator engineering department review and field monitoring is necessary to ensure no

corrosion issues are identified). There is concern that third-party damage will result and sprinkler systems will interfere with transmission line maintenance and vegetation management activities.

Stock Piles - Storage of Earth Yes, but consent is required See Cuts and Fills.

This material storage can't interfere with transmission line maintenance, inspection, repair, or emergency response activities. In addition, stock piles must not lead to erosion issues.

Storage No The ROW cannot be designated as storage area. However, small amounts of non-combustible materials or equipment may be stored on the ROW by the property owner provided it does

not interfere with access to the transmission line.

This material storage can't interfere with transmission line maintenance, inspection, repair, or emergency response activities. In addition, storage must not lead to erosion issues.

Structures No Permanent structures (i.e., any facility or structure, the foundation or any other portion of which lies below the

ground surface, or is otherwise not readily moveable) are not allowed.

Small outbuildings (e.g., sheds, playhouses) on blocks or without foundations may be permitted on a case by case basis.

No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection, and repair activities.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Subdivisions Yes, but consent is required The area over the transmission line ROW may be subdivided provided: 1) No permanent structures may be located on the ROW. 2) Streets or roads are laid out to cross the transmission

line at a right angle. Parallel encroachments are not acceptable. 3) The requirements for Road Crossings,

either private or public, are met. 4) The ROW is not used for a utility corridor. 5) Developer or person subdividing the property submits approved subdivision plans. 6) Necessary consents are issued by the transmission line operator.

Transmission line operators can work with planners and developers to minimize risks to transmission lines and communities within green spaces;

early communication between all stakeholders is critical to ensure all factors are considered.

Swimming Pools (built-in and above ground) No Small, plastic "kiddy" type pools would be allowed. These types of portable pools are considered temporary and can be easily moved for transmission line activities if necessary.

No permanent structures are allowed because they interfere with transmission line emergency response, maintenance, inspection, and repair activities.

Tanks No Above or underground.

Access for transmission line maintenance, inspection, emergency response, and repair activities preclude this use

Temporary Material Storage Non-earth Material Yes, but consent is required This material storage can't interfere with transmission line maintenance, inspection, emergency response, or repair activities. In addition, storage must not lead to erosion issues.

Tennis Courts No Access for transmission line maintenance, inspection, and repair activities preclude this use.

Trails Yes, but consent is required Adequate precautions should be taken to prevent erosion. See Cuts and Fills.

Trails must be placed to allow transmission line maintenance, inspection and repair activities to be conducted.

Trash Burners No For safety reasons, no flame, fire or flammable material is allowed.

Tree Farms No Must provide access to transmission line facilities. In addition, shrubs should not interfere with transmission line patrolling or inspection activities.

Trees have root structure that may damage transmission line coating or transmission line integrity; tree canopy may interfere with aerial leak patrol activities.

Underground Structure No Other than "other" pipelines and related facilities (See Pipelines).

Access for transmission line repair activities precludes this use.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Utilities - Crossing Perpendicular Yes, but consent is required Consent to common use generally will be granted for crossings of overhead or underground utilities provided: 1) Overhead lines must provide adequate clearance for working on the transmission line. Poles, anchors or supports may not be located on the ROW.

2) All underground lines must be installed with minimum one foot of clearance between the transmission

line and the utility if crossing is above the transmission line and two feet of clearance if crossing is below the transmission line and must be at same depth completely across the ROW. Crossings above the transmission line are strongly discouraged.

Underground electric lines of less than 600 volts and all buried telephone lines, must be encased in plastic conduit across the entire width of the ROW. Underground electric lines

of over 600 volts must be encased in rigid steel pipe across the entire width of the ROW. 3) The crossing utility operator must pay for any protection or upgrading of the transmission line facilities, and a temporary relocation clause may be used to allow

construction or maintenance of the transmission line. 4) Utility crossings must be designed to meet all applicable federal, state and local codes and requirements, and assurance provided

that due consideration has been given to the effect of the project on the surrounding area. 5) Buried electric cables, splices should be discouraged within the ROW.

Adequate separation and interference protection with other utility activities and the transmission line must be performed. Interference protection that is not effective may lead to transmission line corrosion and integrity issues. Activity must allow transmission line maintenance, inspection, emergency response, and repair activities to be conducted.

Utilities - Running Parallel No Parallel encroachment of any utilities, either overhead or underground may be allowed in some cases for short distances. In general, parallel encroachments are to be strongly discouraged.

Easement agreements may not allow absolute prohibition of such encroachments.

Interference protection that is not effective may lead to transmission line corrosion and integrity issues.

Use/Activity Acceptable Use?

Additional Restrictions or Comments Origin/Rationale for Determining Acceptable Activity Utilities - Crossing in Operator Easement Yes, but consent is required The transmission line company generally will grant rights of way for utilities across company-owned lands provided: 1) Easement will not interfere with present or future use of land by

the pipeline company. 2) The pipeline company retains the right to have the crossing utility relocate at its own expense at a future date, if such relocation becomes necessary to permit utilization of the land by the pipeline company. 3) Crossing utilities must be

installed and maintained in accordance with all applicable codes and requirements. 4) Adequate consideration must have been given to the effects of the crossing utility on the environment of the area. 5) Buried electric cables, splices should be discouraged within the ROW.

Adequate separation and interference protection with other utility activities and the transmission line must be performed. Interference protection that is not effective may lead to transmission line corrosion and integrity issues. Activity must allow transmission line maintenance, inspection, emergency response, and repair activities to be conducted.

Utilities - Crossing Outside of Operator Easement Yes, but consent is required Where a utility crosses the transmission line on a public road, the utility normally has equal rights with the

pipeline facility. However, every effort should be made for the pipeline company and the utility company to work together to provide a minimum of one

foot of clearance between the utility and the transmission line if the utility crosses above the transmission line or two feet if the utility crosses below the transmission line, and that the same depth be maintained completely across what would normally be the transmission line ROW. The same criteria for underground electric lines as set forth in "Utilities - Crossing"

should also be requested. Engineering review by the transmission line company is required even if no consent is issued.

Adequate separation and interference protection with other utilities and transmission lines must be performed.

Interference protection that is not effective may lead to transmission line corrosion and integrity issues. Activity

must allow transmission line maintenance, inspection, emergency response, and repair activities to be conducted.

Vaults No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities.

Wading Pools No Small, plastic "kiddy" type pools would be allowed. These types of portable pools are considered temporary and can be easily moved for transmission line activities if necessary.

No permanent structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities.

Weighing Stations No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities.

Wells No Drilling activity could damage transmission lines and lead to integrity issues.

Wrecking Yards No No structures are allowed because they interfere with transmission line emergency response, maintenance, inspection and repair activities.

34.5.11. Burying of construction material. No person shall bury unused, scrap, waste, excess or discarded construction material without the approval of a use permit for an inert waste landfill in accordance with article XIX. Any person who

violates this provision shall be deemed guilty of a misdemeanor and subject to the provisions of article XXIX, Violation and Penalty. (Added 12/1/ 99)

34.5.12. Wastewater pump and lift stations. A minimum 50-foot buffer and 10-foot improvement setback shall be provided along all property lines adjacent to residentially and/or agriculturally zoned properties used for residential or public recreational purposes. (Added 09/01/04)

34.5.13. South Fulton Greenway Trail Master Plan. At the time of application for a land disturbance permit or building permit, development projects with frontage adjacent to roads identified

on the South Fulton Greenway Trail Master Plan Map shall incorporate a multi-use path subject to the approval of the director of the environment and community development. (Amd. No. 10-0379, 4-7-10)

34.5.14. Reserved.

34.5.15. Reserved.

34.5.16. Cluster mailboxes.

A. Applicable districts:

1. All residential districts or districts with residential components when developed with residential units.

2. Non-residential districts and interior building cluster mailboxes are exempt from the design and location

standards of this section.

APPENDIX B—ZONING RESOLUTION 34.5

T ~ ./---1-'-4_0,L-· .~ - ,~ - -~ I PIPELINE PIPELINE EASEMENT

(VARIES) .

RESTRICTED

PIPELINE

AREA

PLANNING AREA

( 300')

CONSULTATION ZONE

( 500')

3. Procedural standards are applicable to all cluster mailbox installations.

B. Procedural standards:

1. Prior to the submission of the preliminary plat, approval of the United States Postal Service (USPS) must

be obtained and attached with the plat.

2. Where a final plat is recorded with a performance bond, the surety shall cover the cluster-style mailbox kiosk and the installation shall occur prior to any certificate of occupancy being issued for a residential structure shown on the plat.

3. Cluster-style mailbox kiosks shall be installed prior to the issuance of a certificate of occupancy for any residential structure that will be served by a cluster-style mailbox.

4. The cost of installation, including but not limited to box units, architectural elements, landscaping, concrete pad and concrete/masonry or stone sidewalk access, shall be borne

by the developer.

5. Maintenance of the cluster-style mailbox kiosk, landscaping, trash can and surrounding areas shall be borne

by the home owners association (HOA) of the neighborhood/development. Where no HOA exists, maintenance and associated costs shall be the responsibility of the homeowners served by the cluster mailbox kiosk.

6. Cluster-style mailbox kiosks shall be exempt from the setback requirements of the zoning district; however all structures shall require a separate building permit and must

meet or exceed all applicable building code.

C. Design standards:

1. All cluster-style mailbox units shall be incorporated into a cluster-style mailbox kiosk unless the clusterstyle mailbox units are located interior to a building or as may be approved by the director.

2. Cluster-style mailbox kiosks shall be compatible with other streetscape elements and be architecturally enhanced with building materials and details typical of the architectural

style of the neighborhood/development.

a. Cluster-style mailbox kiosks shall be located away from any location where, by reason of the position, shape or color, it may interfere with, or obstruct the view of or be confused with any authorized traffic control device.

b. Provide a four-foot-wide impervious surface parallel to the kiosk and a roof overhang for a

weather free standing location wherever the individual mailboxes are to be accessed.

c. Provide landscaping consistent with the landscape theme of the neighborhood/development.

d. Provide a trash receptacle at each clustered mailbox location.

e. Provide lighting.

3. Cluster-style mailbox kiosks shall have a base of a width not less than the width of the cluster mailbox structure itself.

4. Cluster-style mailbox kiosks shall have a minimum four-foot-wide concrete/masonry or stone access from the street and/or sidewalk.

5. Cluster-style mailbox kiosks shall provide access compliant with the Americans with Disability Act (ADA).

6. Cluster-style mailbox kiosks shall provide a paved area with ingress/ egress to allow vehicles to pull off, park and re-enter the roadway safely while retrieving mail.

7. Cluster-style mailbox kiosks shall be located in areas that will best allow for vehicle parking. Parking layout is to be designed in a manor so as to not create pedestrian safety or vehicle safety issues as determined by the Fulton County Traffic Engineer.

_______________________________________________________________________________________________

8. Minimum required parking shall be required as follows:

Cluster-style Mailbox Kiosk Off-street Parking Requirement Activity Number of Spaces Required

Cluster-style Mailbox Number of Mailboxes Parking Spaces Required 0—20 0 21—60 2 61—80 3 81—100 4 101 or more 4 plus 1 per each additional 50 mailboxes or portion thereof above 100 _______________________________________________________________________________________________

9. Access drives and parking areas shall be constructed to Fulton County road standards or as approved by the director of the department.

D. Location standards:

1. The location of the cluster-style mailbox is to be approved by the county and by the USPS.

2. Cluster-style mailbox kiosks shall be prohibited from being located within the public right-of-way.

3. Clustered mailboxes shall be placed so as to not adversely affect the privacy of residents.

4. Cluster-style mailbox kiosks shall not be installed within a cul-de-sac bulb.

5. Cluster-style mailbox kiosks shall be located away from the intersection of any street and in no case closer than 75 feet measured from

the street centerline in order to prevent obstruction of free and clear vision.

6. Clustered mailboxes shall be centrally located, offering easy pedestrian access to all residents.

Cluster-style mailbox kiosks shall be located no more than one-fourth mile from the property line of those residents served by the cluster-style mailbox kiosk. Distance shall be measure as a radius drawn from the cluster-style mailbox kiosk.

7. No driveway or street access shall be constructed within five feet of a cluster-style mailbox kiosk and vice versa.

E. Address post:

1. Each residential one- or two-family dwelling shall have its address number posted on a mailbox or addressing post located at or near the main entrance or vehicle access point to the property.

2. The address post shall not exceed six inches by six inches in dimension.

3. One-third of the total length of the address post shall be buried in the ground and the address post shall be secured in the ground i.e. surrounded by concrete.

4. Such address numbers shall have a minimum stroke height of three inches and shall be a color that contrasts with the surrounding surface so as to be readily identifiable.

5. Such numbers shall have a minimum one-half inch between numbers.

6. Address numbers shall not be placed within 18 inches of the ground.

7. Address numbers must be clearly visible on both sides of the post, and shall face the direction of traffic.

8. The post shall not be obstructed from view by any means.

9. The property owner shall have the responsibility of ensuring compliance with the requirements of this section, regardless of whether the

premises are leased or owner-occupied.

The following diagram has been provided as reference for acceptable and unacceptable installation, of the address posts and address numbers.

(15-0273, 4-1-15; 16-0363, pt. 1, 5-4-16)

EXAMPLES OF ADDRESSING POSTS

ACCEPTABLE ADDRESS POSTS

ONA POST

3-4" -==1-1/2- 0 9 3-4" 18" Minimum from ground

MOUNTED BOARD

ONA POST

18" Minimum from ground

DECORATIVE

POST

18" Minimum from ground

UNACCEPTABLE ADDRESS POSTS

ONA POST

Too low to the ground foli age can grow and block numbers

NUMBER STAKES

Too low to the ground Not enough contrast Too far away from the beginning of driveway DI •

34.6. Timber harvesting. (Added 3-6-91; Deleted 12-1-99)

34.7. Cemeteries. In a parcel with a cemetery, burial ground, human remains or burial object(s), there shall be no land disturbing activity or timbering unless approved by the Department of Environment and Community Development. The person or entity seeking a permit shall also comply with O.C.G.A. § 36-72-4. If a parcel is adjacent to a cemetery, there shall be no land disturbance in that parcel unless approved by the Department of Environment and Community Development.

The following development standards shall be required as a part of the application process for a land disturbance permit or building permit on any parcel with a cemetery or on any parcel adjacent to a cemetery:

A. A report prepared by an archeologist determining the boundary of the cemetery and stating the number of graves believed to be present and their location as can be determined from the use of minimally invasive investigation techniques, including remote sensing methods and the use of metal probes.

B. A survey of the cemetery prepared by or under the direction of a registered surveyor showing the location of the boundaries of the cemetery or burial ground based on an archeologist's report.

C. A 25-foot natural undisturbed buffer with a 10-foot improvement setback shall be provided around the perimeter of the outermost burials, as determined by an archeologist, if a cemetery is located on the parcel of land to be developed. If a cemetery is adjacent to the parcel to be developed, a 25-foot natural undisturbed buffer with a 10-foot improvement setback shall be provided along common property lines on the parcel where the land disturbance permit or building permit is being sought.

D. A temporary tree protection fence shall be installed on the outer perimeter of the 25-foot undisturbed buffer before any land disturbing activity occurs. If the cemetery is located on an adjacent parcel, the tree protection fence shall be located along common property lines. The temporary tree protection fence shall remain in place until construction is completed.

E. A permanent 6-foot high fence or wall with a gate shall be constructed along the perimeter of a cemetery on a parcel for which land disturbing activity is sought. The fence shall be constructed of a durable metal material. At minimum fence shall be black vinyl clad chain-link.

Uncoated chain-link fence is prohibited.

The location of the fence shall be as determined by an archaeologist. If the cemetery is located on an adjacent parcel, the fence shall be located interior to the required buffer and improvement setback or along the common property line(s) as may be approved by the Fulton County Arborist. The gate shall have a latch and be 4 feet wide if the cemetery is inactive or 10 feet wide if active.

F. Uninhibited daylight access to the cemetery shall be provided via a 20-foot graveled easement to the cemetery from the nearest public road. The easement shall be recorded in the Fulton County Courthouse.

G. A maintenance plan for a cemetery located on the parcel for which a land disturbance permit or building permit is sought shall be developed and implemented.

H. The location of a cemetery, as identified by the surveyor, shall be included on the recorded plat.

I. A small plaque/marker with the name of the cemetery, range of burials and any other historical information may be placed on the cemetery fence. (Added 2-1-06)

APPENDIX A (INACTIVE)

ARTICLE XIII. A-1 APARTMENT

DWELLING DISTRICT REGULATIONS

(11-2-66)

1. [Article applicable to A-1 district.]

The regulations set forth in this article, or set forth elsewhere in this resolution when referred to in this article, are the regulations in the A-1 District. (See article XIX)

2. Use regulations.

A building or premises shall be used only for the following purposes:

A. Any use permitted in the R-1 Single Family Dwelling District.

B. Two family dwelling.

C. Multiple dwelling.

D. Rooming house and boardinghouse.

E. Institutions of a religious, educational, eleemosynary or philanthropic nature, but not penal or mental institutions. (These uses are contingent upon compliance with article XIX — Additional Use Regulations.)

F. Hospital, except a criminal, mental or animal hospital, (These uses are contingent upon compliance with article XIX — Additional Use Regulations.)

G. Private club, fraternities, sororities and lodge, excepting those the chief activity of which is a service customarily carried on as a business. (These uses are contingent upon compliance with article XIX — Additional Use Regulations.)

H. Accessory use or building and uses customarily incidental to any of the above uses, including as follows:

(1) Single family and two family dwellings: Accessory buildings that are not a part of the main structure

shall be located in the rear yard not less than ten feet from the main building nor less than five feet from any side or rear yard.

(2) Multiple family dwellings and other uses: All accessory buildings shall be located in the rear yard and not nearer to any lot line than the distance prescribed for side and rear yards.

(3) Deleted - 37, Regular Meeting 2/3/ 88.

(4) Swimming pools may be located within the buildable area of any tract or parcel of land used for multiple family dwelling purposes, provided that when located on property adjacent to single family or two family dwelling districts, such pools, including their enclosed areas, shall not be located within 150 feet thereof. Provided, however, when swimming pools are located so as to be screened from

such districts by a multiple family dwelling greater in length by a minimum of 20 feet on each end of the enclosed area of such pools, said distance of 150 feet shall not be required.

3. Off-street parking regulations. (Superseded by article XVIII)

1. Location of parking spaces and driveways on the lot:

(a) Off-street parking shall be provided in the rear yard or within that portion of the side yard lies between a main building and the side lot line.

(b) Except at points where they provide ingress and egress to a property, development, or parcel of land, driveways may not be located nearer than ten feet to any lot line which abuts a

single family or two family dwelling district nor nearer than four feet to any other lot line.

2. Parking space requirements: Parking spaces on the lot with adequate access to a public street and with adequate circulation space shall be constructed of a material which will assure a surface resistant to erosion and maintained permanently

follows:

(a) Multiple dwellings: One and onehalf tenant parking spaces for each dwelling unit, plus one visitor parking space for ever four units, rounded to the next highest whole number of

spaces.

(b) Single family and two family dwellings: Two parking spaces for each dwelling unit.

(c) Fraternities or sororities: One parking space for every three beds contained in the structure.

(d) Rooming house and boardinghouse:

One parking space for every two guest rooms contained in the structure.

(e) Private club or lodge: One parking space for every five active members.

(f) Hospitals or institutions: One space for ever four beds, plus one space for each staff or visiting doctor (based on the average number), plus one space for every two employees, including nurses.

(g) Professional office or studio of a physician, dentist, artist, musician, lawyer, architect or teacher in his place of abode: Parking space with adequate ingress and egress from a public way, place or street equal to twice that area within the structure which

is devoted to such office or studio, but in no instance less than two parking spaces.

(h) Schools and public buildings: One parking space for every ten seats in the auditorium or similar places of public assembly.

(i) Government buildings: One parking space for every 200 square feet of floor area (excluding storage area) plus one space for every two persons employed in an accessory use.

4. Height regulations.

No building shall exceed three stories or 45 feet.

5. Area regulations.

1. Front yard:

(a) Single family and two family dwellings: There shall be a front yard having a depth of not less than 40

feet.

(b) Multiple dwellings and other uses:

There shall be front yard having a depth of not less than 40 feet.

2. Side yard:

(a) Single family and two family dwellings: There shall be two side yards, one on each side of the building,

having a combined width of not less than 15 feet; provided, however, that no side yard shall be less than seven feet in width.

(b) Multiple dwelling and other uses:

(1) Where multiple dwelling districts abut single family and two family districts, there shall

be two side yards, one on each side of the building each having a width of not less than 25 feet.

(2) Where multiple dwelling districts do not abut single family and two family districts, there

shall be two side yards, one on each side of the building, having a combined width of not less than 25 feet provided, however, that no side yard shall be less than ten feet in width.

(3) Where a lot is located at the intersection of two or more streets, the width of the yard along the side street shall be not less than 25 feet.

3. Side yard:

(a) Single family and two family dwellings: There shall be a rear yard having a depth of not less than 25

feet.

(b) Multiple dwellings and other uses:

There shall be a rear yard having a depth of not less than 25 feet, provided, that when a rear yard abuts a single family district and is used for

multiple dwelling purposes, the rear yard shall be not less than 75 feet.

4. Lot area per family: Every dwelling shall be located upon a lot having the following minimum size:

(a) Single family dwelling: Every lot shall have a frontage of not less than 85 feet and an area of not less than 12,000 square feet, however, in no case shall lot frontages and lot areas be required which are larger than those required by zoning standards established in the nearest single family dwelling district.

(b) Two family dwellings: Every two family dwelling shall be located upon a Lot having a frontage of not less

than 85 feet and an area of not less than 10,000 square feet, however, in no case shall lot frontages and lot areas be required which are larger than those required by the zoning standards established in the nearest single family dwelling district.

(c) Multiple dwellings: Multiple dwellings shall be located upon a lot having a frontage of not less than 100 feet and an area of not less than

2,250 square feet per family.

(d) Where a lot has less area or width than herein required and was of record at the time of the effective date of this resolution, that lot may be

used for a single family dwelling, for a two family dwelling, or for the other nondwelling uses permitted in this article.

6. Residential floor area resolutions.

1. Each efficiency or studio apartment shall have a floor area of not less than 450 square feet.

2. Each multiple dwelling other than efficiency or studio apartments shall have a floor area of not less than 600 square feet

per dwelling unit.

3. Each two family dwelling shall have a minimum floor area of 1,000 square feet per dwelling unit.

4. Each single family dwelling shall have a minimum floor area of 1,100 square feet.

7. Lot coverage.

Maximum coverage of the lot by buildings, including accessory buildings, shall be 30 percent of the gross lot area.

8. Buffer screen.

The developer shall provide a buffer screen beginning at the building line and extending along any side or rear property line which abuts a single family or two family district when an A-1 District is used for any purpose other than one or two family dwellings.

Definition:

Buffer screen: Superseded by article III, Definitions. A permanent fence, wall, or evergreen planting screen which will interrupt vision

between adjacent properties. A buffer screen shall be at least six feet high except that initially an evergreen planting screen may be less than six feet if plants are provided which will ultimately attain a height of six feet or more. (Note: If grouped in proximity, such plants as Pinus Strobus (White Pine); Prunus Caroliniana (Cherry Laurel); ligustrum Licidum (Ligustrum); Elaeagnus Pungens (Elaeagnus);

and Ilex Crenta Burfordi (Burfordi Holly) will grow to form a hardy screen thick enough and high enough to interrupt vision and to effectively reduce the transmission of sound.)

ARTICLE XIII-A. (Sept. 6, 1961) (Repealed 5/2/68)

A-O APARTMENT-OFFICE DISTRICT

REGULATIONS

1. [Article applicable to A-O District.]

The regulations set forth in this article, or set forth elsewhere in this resolution when referred to in this article, are the regulations in the A-O District Regulations (See article XIX).

(a) Intent: These regulations are designed to apply to land so located that it is readily adaptable to commercial development but where proximity to residential, public, or other land uses, and its relationship to existing and projected traffic patterns, make it desirable to limit the extent of commercial and residential operations.

2. Use regulations.

A building or premises shall be used only for the following purposes:

1. Any use permitted in the A-1 Apartment Dwelling District but not including single family dwelling, two family dwelling, agriculture, horticulture and general farming as provided in article VII, section 2, paragraph 7, and fraternities or sororities

containing sleeping accommodations.

2. Apothecary shop as an accessory retail use within a building without exterior advertising display, provided that only drugs, prescription medicines, medicinal supplies and pharmaceutical products shall be sold.

3. Assembly halls, gymnasiums, stadiums, and similar structures operated on a nonprofit basis.

4. Automobile parking garages and lots (commercial) provided that portions of open parking lots abutting dwelling districts

are separated therefrom by a planted area 25 feet or more in width measured from the property line.

5. Churches and temples.

6. Clinics, medical, dental, chiropractic, osteopathic and similar operations, but not including a practice of veterinary medicine.

7. Colleges, universities, business colleges, music conservatories, dancing schools and similar institutions, public or private, all without students in residence.

8. Community center buildings, and other similar facilities operated on a nonprofit basis.

9. Financial establishments, such as banks, loan companies, insurance companies.

10. Government buildings: buildings used exclusively by the federal, state, county, or city governments for public purposes but

not including repair garages, repair or storage yards for material, vehicles or equipment, warehouses, buildings and other facilities having commercial or industrial characteristics, and buildings used or intended to be used as correctional or

penal institutions.

11. Incidental accessory retail uses such as cafeterias, gift shoos, flower shops, snack bars, barber shop, beauty shop, tailor shoo, radio-TV shop, and repair shoe shop, conducted for the convenience of the employees, patients, patrons, or visitors on the premises wholly within the principal buildings and without exterior advertising display.

12. Libraries, museums, and art galleries.

13. Office buildings: governmental and private office buildings, including professional offices in which no retail trade activity is carried on with the general

public and no stock of goods is maintained for sale to the general public, except as permitted in an accessory use.

14. Signs:

(a) Professional or announcement sign, illuminated indirectly, not more than 20 square feet in area mounted flat to the wall on the main building freestanding but situated no nearer to the street line than one-half the distance between the street line and the building line on the main building on the lot;

(b) A temporary, unilluminated real estate sign not over 12 square feet in area pertaining only to the sale, lease,

or rent of the property upon which the sign is located, provided the sign shall be mounted or displayed behind the building set-back line of the lot;

(c) A church or institutional bulletin board or sign, not more than 12 square feet in area, illuminated indirectly, used to display the name and/or activities of the church or

institution, situated no nearer to the street line than one-half the distance between the street line and the building line of the main building on the lot;

(d) Lettering, illuminated indirectly, attached to or built into the front wall of the main building or assembly

halls, churches, colleges and universities, community centers, government buildings, hospitals, libraries, museums, office buildings and schools,

for the purpose of displaying the name and/or address of the facility upon which such lettering is affixed.

15. Accessory building and uses customarily incident to the above listed uses. Any building used primarily for any of the above enumerated uses may have not more than 25 percent of the floor area devoted to storage purposes incidental to such primary use.

3. Off-street parking and loading area regulations. (Superseded by article XVIII)

1. Location of parking and loading areas on the lot:

(a) The required off-street parking and loading area shall be provided in the rear yard or within that portion of the side yard which lies between the main building and the side lot line.

(b) No off-street parking space shall be provided within 25 feet of any lot which abuts a dwelling district.

2. Provision of required parking area on remote lots: The required parking area may be located on the lot with the principal

use or on a lot separated therefrom by not more than 300 feet along a directly accessible walkway.

3. Joint use of off-street parking areas: Onehalf of the off-street parking area required for any permitted use in this district, not including multiple dwellings, may be counted toward the parking requirements or the following uses, provided the uses sharing such parking areas are not normally open, used or operated

during the principal operation hours of these uses:

(a) Auditorium.

(b) Assembly halls.

(c) Churches.

(d) Gymnasiums.

4. Minimum requirements for off-street parking and loading:

(a) Rooming house, boardinghouse, and professional office in place of abode;

same as those in A-1 Apartment Dwelling District.

(b) Multiple dwelling; 11 /2 spaces for every dwelling unit.

(c) Hospitals or institutions: one space for every four beds, plus one space for each staff or visiting doctor (based on the average number), plus one space for every two employees, including nurses.

(d) Clinics and offices of doctors, dentists, osteopaths and similar offices;

five spaces for ever doctor plus one for every two employees.

(e) Auditoriums, assembly halls, churches, gymnasiums, stadiums, libraries, museums, art galleries, private club or lodge, one space for each four fixed seats in the largest assemble room or facility or for each 35 square feet of enclosed floor area

used for accommodation of movable seats in the largest assembly room, whichever is greater, plus one space for each 100 square feet of ground area used for assembly.

(f) Government buildings, financial establishments, and office buildings other than clinics and offices for doctors, dentists, etc., one space for every 200 square feet of floor area (excluding storage area) plus one

space for every two persons employed in an accessory use.

(g) Schools.

(1) Public or private elementary, and special schools without students in residence; two spaces for every classroom.

(2) Public or private high; four spaces for every classroom.

(3) Public or private colleges, music conservatories, dancing schools, universities, business

colleges, one space for ever 200 square feet of floor area.

(4) School auditorium assembly halls, stadiums, gymnasiums, same as subsection (e) above.

(h) Accessory retail uses; one space for every two employees

(i) One loading space on the lot shall be provided for each 15,000 square feet of area, or fraction thereof in excess or 5,000 square feet, devoted to uses requiring the receipt of distribution of material or merchandise by auto vehicle.

(j) No lot shall have more than two curb breaks per 100 feet of frontage. No curb break shall exceed 30 feet in width. Curb breaks shall be not less than 25 feet from the intersection of two or more curb lines, as measured along one of the said curb lines.

4. Height regulations. (7/5/67)

1. Buildings intended for multiple dwelling use shall not exceed three stories or 45 feet.

2. Buildings intended for nondwelling use shall not exceed four stories or 60 feet in height except as or may be provided in this resolution. This limitation may be exceeded by special permit as provided in article XIX in specific building and site plans are reviewed and approved by the commissioners of roads and revenues subsequent to public hearing and recommendation of the Atlanta-Fulton County Joint Planning Board. Such approval shall follow investigation and finding that the proposed building:

(a) Will provide adequate open space and off-street parking facilities, and

(b) Will not adversely affect the privacy of adjoining uses and that screened buffer areas will provide separation from any adjoining single family residences.

5. Area regulations.

1. Multiple dwellings shall conform to the following requirements:

(a) Front yard: The front yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(b) Side yard: The side yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(c) Rear yard: The rear yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(d) Lot area per family: The lot area per family shall be the same as those in the A-1 Apartment Dwelling District.

(e) Lot coverage: Maximum coverage of the lot by buildings including accessory buildings) shall be 35 percent of the gross lot area.

2. Nondwelling uses shall conform to the following requirements:

(a) Front yard: The front yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(b) Side yard: The side yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(c) Rear yard: The rear yard regulations shall be the same as those in the A-1 Apartment Dwelling District.

(d) Lot area per family: Lot area per family shall be the same as those in the C-1 Commercial District.

(e) Lot coverage: Maximum coverage of the lot by buildings (including accessory buildings) shall be 40 percent of the gross lot.

6. Residential floor area regulations.

The residential floor area regulations for multiple dwellings shall be the same as those in the A-1 Apartment Dwelling District.

ARTICLE XII-A

TR TOWNHOUSE RESIDENTIAL DISTRICT

(Adopted August 6, 1969)

(Z-68-161 FC)

1. Intent of the district.

A. This district encompasses lands devoted to residential uses having both single and multifamily characteristics. The intent of this district is to provide standards for low density dwellings which

will:

1. Encourage the provisions of usable open and recreation areas and desirable living environment;

2. Be located primarily in areas near or adjacent to single family use areas;

3. Be located so as to provide transition between single family use areas and higher density dwelling areas and/or commercial areas;

4. Be located near such services as retail shopping and major thoroughfares and collector streets; and

5. Encourage home ownership.

B. The regulations set forth in this article, or set forth elsewhere in this resolution when referred to in this article, are the regulations of the TR Townhouse Residential District (see articles

XIX, XX and XXI).

C. An application for rezoning to TR Townhouse Residential District shall be supported by a site plan for the proposed development. (Amended

6/6/73 — Z-73-75 FC)

D. Approval of plans for drainage, sewerage, driveways, and parking areas by the department of planning and community development shall be required prior to the issuance of building permits.

E. Construction shall conform to the overall site plan and detailed engineering plans as approved by planning and community development.

2. Use regulations.

A building or premises shall be used only for the following purposes.

1. Single family dwelling.

2. Two family dwelling.

3. Townhouses: As defined in article III, section 1, 56(b).

4. Accessory uses or buildings customarily incidental to any of the above uses as follows:

(a) Single family and two family dwellings: Accessory uses and buildings that are not a part of the main

structure shall be located in the rear yard or in the side yard, and shall not be less than ten feet from any side or rear lot line.

(b) Townhouses:

(1) All accessory buildings shall be located not nearer to any perimeter lot line than the distance prescribed for side and rear

yards.

(2) Deleted — 37, 2/3/88.

(3) Unenclosed recreational facilities, except swimming pools, may be placed within any required side or rear yard, provided that any such use shall not be permitted nearer to any

perimeter lot line than 30 feet.

(4) Swimming pools: Provided that no swimming pool may be placed nearer than 30 feet to any rear or side lot line, nor nearer than 50 feet to any public street line.

Provided further that when located adjacent to a single family residential district, such pools shall not be located within 150

feet thereof, except in cases when located so as to be screened from single family dwelling district by a townhouse dwelling, or an accessory structure greater in length by a

minimum of 20 feet on each side of such pool(s), the distance of 150 feet shall not be required. A fence of minimum

height of five feet shall be provided around the perimeter of all swimming pools.

(5) Stacked flats, (Deleted) with approval of special use permit, pursuant to article XIX, Additional Use Regulations (Z83-33 FC, April 6, 1983).

3. Off-street parking regulations. (Superseded by article XVIII)

1. Location of parking and driveways:

(a) No off-street parking shall be permitted in any front yard. On a corner property, no off-street parking shall

be permitted within the side yard between the buildings and the adjacent street frontage.

(b) No off-street parking or driveways shall be located within ten feet of any perimeter lot line.

(c) Driveways serving more than two parking spaces shall provide an adequate turn-around space.

2. Parking space requirements:

(a) Single family and two family dwellings: Two off-street parking spaces for each dwelling unit.

(b) Townhouse dwellings: Two off-street parking spaces for each dwelling unit, plus one visitor parking space for every four units or fraction thereof.

Each visitor parking space shall be located in the proximity of the units it serves.

4. Building regulations.

1. For single family, two family and townhouse dwellings: No building or structure shall exceed 35 feet in height.

2. For townhouse residential development:

(a) Deleted 6/6/73 — Z-73-75 FC

(b) No more than 20 townhouse dwelling units shall be permitted to form a single building.

(c) No more than three contiguous townhouse dwellings which form a part of a single building shall have the same

front setback or roof line. Said setback and roof line shall be varied by a minimum of two feet.

(d) Sidewalks shall be provided for each townhouse pedestrian access throughout the entire development.

(e) Driveways serving more than six units shall be paved to a minimum width of 30 feet.

5. Area regulations.

1. For single family and two family dwellings:

(a) Front yard: There shall be a front yard having a depth of not less than 40 feet.

(b) Side yard: There shall be two side yards, one on each side of the building of not less than ten feet. where a lot is located at the intersection of

two or more streets, the width of the yard along the side street shall not be less than 20 feet. No accessory building or portion thereof shall be located within the required yard area along any street.

(c) Rear yard: There shall be a rear yard having a depth of 25 feet.

(d) Lot area per family: Every dwelling shall be located on a lot having a frontage of 90 feet at the building setback line and containing the following areas:

1. Eleven thousand square feet for a single family dwelling (90′ × 122′).

2. Fifty-five hundred square feet per family for a two family dwelling (99′ × 112′).

2. For townhouse residential developments:

(a) Density: A Townhouse Residential Development shall not exceed nine dwellings units per gross acre (4,480 square feet per family unit).

(b) Size of development site: The minimum size of the site to be developed for townhouse residential use shall

be two acres, with 100 feet of frontage. (Z-80-38 FC — App. 4-2-80).

(c) Yard requirements:

1. Front yard: There shall be a front yard of not less than 40 feet.

2. Side yard: There shall be two side yards of not less than 30 feet on each side provided, however, where a side yard abuts a single family dwelling district,

the side yard shall not be less than 40 feet.

3. Corner setback: Where a lot, tract, or parcel of land is located at the intersection of two streets, the width of the yard

along the side street side shall not be less than 40 feet provided, however, that when such property lies adjacent to a single family dwelling district, the yard requirement along the side

street shall be the same as prescribed or established for the front yard of the adjacent single family dwelling district. In no case shall such yard be less

than 40 feet.

4. Rear yard: There shall be a rear yard along the rear lot line of not less than 35 feet provided, however, when a rear yard abuts a single family dwelling district and is used for townhouse dwellings, the rear yard

(d) Buffers: In addition to the above setback requirements, a buffer zone may be required along any perimeter lot

line, or portion thereof, in order to provide privacy and separation between adjoining properties. Property with such buffer areas may be included within the lot area for density and lot coverage purposes.

6. Residential floor area regulations.

1. Each single family dwelling shall have a minimum ground floor area of 1,200 square feet if less than two stories.

2. Each single family dwelling of two stories in height shall have a minimum ground floor area of 900 square feet, and a total minimum floor area of 1,320 square feet.

3. Each two family dwelling shall have a minimum floor area of 900 square feet and a minimum ground floor area of 900 square feet if two stories in height.

4. Each townhouse dwelling unit shall have a minimum floor area of not less than 1,100 square feet.

(a) Each townhouse unit shall have a minimum width of 20 feet.

(b) Private, usable open space, such as balconies, sundecks, patios, etc. shall be provided contiguous to each dwelling unit. The area of such open space provided for each unit shall not be

less than ten percent of the floor area of the unit served. The location and number of square feet shall be clearly indicated on the site plan.

7. Screening garbage and storage areas. (Superseded by article IV) All exterior garbage, incinerators, or other outside storage areas shall be screened by a solid enclosure of not less than four feet in height.

8. Townhouse Residential open space requirements.

1. Open space requirements for Townhouse Residential buildings shall be as follows:

(a) The minimum distances between buildings, when so arranged shall be as follows:

Front to Front 50 feet Front to Rear 60 feet Rear to Rear 50 feet Front or Rear to Side 40 feet Side to Side 40 feet

(b) Where unusual and uncommon conditions of topography or configuration of the property exist, the planning board may permit a departure from the above prescribed distances

between buildings, provided such departure shall not diminish the required distances by more than 50 percent.

2. Common open space and facilities: Deleted 6/6/73 — Z-73-75 FC

APPENDIX A (INACTIVE)

SUB A SUBURBAN A SINGLE FAMILY

DWELLING DISTRICT

1. SUB A District intent and scope.

Regulations set forth in this article are the SUB A District regulations. Article XIX should be consulted to determine uses and minimum standards for uses allowed by administrative or use permit. The SUB A District encompasses lands

devoted to residential use areas of one or fewer dwellings per acre and closely related uses.

2. Use regulations.

2.1 Permitted uses. A building or property may be used for only the following purposes:

A. Single family dwelling.

B. Agriculture, general and specialized farming, initiated prior to March 7, 1990, including: horticulture, plant nursery, greenhouse, dairy farming, and truck gardening, provided that buildings used for agricultural purposes shall not be located nearer than 200 feet to any side or rear lot line

and provided that produce is not offered for sale on the premises.

2.2 Accessory uses. A building or lot may be used for uses customarily incidental to any permitted use and a dwelling may be used for a home occupation.

3. Development regulations.

3.1 Height regulations. Buildings shall be no higher than 35 feet or 21 /2 stories, whichever is higher.

3.2 Area regulations.

A. Minimum front yard: 60 feet.

B. Minimum side yard:

— 15 feet adjacent to interior lines.

— 30 feet adjacent to streets.

C. Minimum rear yard: 40 feet

D. Minimum lot area: one acre

E. Minimum lot width: 150 feet

F. Minimum lot frontage: 35 feet

G. Minimum heated floor area: 1,200 s.f. for less than two story.

1,320 s.f. for two story or more than two story with 900 s.f. on ground floor

I. Minimum accessory structure requirements: Accessory structures may be located in rear or side yards, but shall not be located within a minimum yard.

4. Other regulations.

The headings below contain provisions applicable to uses allowed in the SUB A District.

Development regulations. Article XXXIV Exceptions. Section 4.3 Floodplain management. Section 4.24 Off-street parking and loading. Article XVIII Outside storage. Section 4.2 Landscape area and buffer regulations. Section 4.23 River protection. Metropolitan River Protection Act Signs. Article XXXIII

APPENDIX A (INACTIVE)

SUB B

SUBURBAN B SINGLE FAMILY DWELLING

DISTRICT

1. SUB B District scope and intent.

Regulations set forth in this article are the SUB B District regulations. Article XIX should be consulted to determine uses and minimum standards for uses allowed by administrative or use permit. The SUB B District encompasses lands

devoted to residential use areas of one or fewer dwellings per acre and closely related uses.

2. Use regulations.

2.1 Permitted uses. A building or property may be used for only the following purposes:

A. Single family dwelling.

B. Agriculture, general and specialized farming, initiated prior to March 7, 1990, including: horticulture, plant nursery, greenhouse, dairy farming, and truck gardening, provided that buildings used for agricultural purposes shall not be located nearer than 200 feet to any side or rear lot line

and provided that produce is not offered for sale on the premises.

2.2 Accessory uses. A building or lot may be used for uses customarily incidental to any permitted use and a dwelling may be used for a home occupation.

3. Development regulations.

3.1 Height regulations. Buildings shall be no higher than 35 feet or 21 /2 stories, whichever is higher.

3.2 Area regulations.

A. Minimum front yard: 60 feet.

B. Minimum side yard:

— 15 feet adjacent to interior lines.

— 30 feet adjacent to streets.

C. Minimum rear yard: 40 feet.

D. Minimum lot area:

One acre.

Ten acres for poultry.

Five acres for kennel.

E. Minimum lot width: 150 feet.

F. Minimum lot frontage: 35 feet.

G. Minimum heated floor area: 850 s.f. on ground floor.

H. Minimum accessory structure requirements:

Accessory structures may be located in rear or side yards, but shall not be located within a minimum yard.

4. Other regulations.

The headings below contain provisions applicable to uses allowed in the SUB B District.

Development regulations. Article XXXIV Exceptions. Section 4.3 Floodplain management. Section 4.24 Off-street parking and loading. Article XVIII Outside storage. Section 4.2 Landscape area and buffer regulations. Section River protection. Metropolitan River Protection Act Signs. Article XXXIII

APPENDIX A (INACTIVE)

SUB C

SUBURBAN C SINGLE FAMILY DWELLING

DISTRICT

1. SUB C District scope and intent.

Regulations set forth in this article are the SUB A District regulations. Article XIX should be consulted to determine uses and minimum standards for uses allowed by administrative or use permit. The SUB C District encompasses lands

devoted to residential use areas of two or fewer dwellings per acre and closely related uses.

2. Use regulations.

2.1 Permitted uses. A building or property may be used for only the following purposes:

A. Single family dwelling.

B. Agriculture, general and specialized farming, initiated prior to March 7, 1990, including: horticulture, plant nursery, greenhouse, dairy farming, and truck gardening, provided that buildings used for agricultural purposes shall not be located nearer than 200 feet to any side or rear lot line

and provided that produce is not offered for sale on the premises.

2.2 Accessory uses. A building or lot may be used for uses customarily incidental to any permitted use and a dwelling may be used for a home occupation.

3. Development regulations.

3.1 Height regulations. Buildings shall be no higher than 35 feet or 21 /2 stories, whichever is higher.

3.2 Area regulations.

A. Minimum front yard: 50 feet.

B. Minimum side yard:

Ten feet adjacent to interior lines.

20 feet adjacent to streets.

C. Minimum rear yard: 35 feet.

D. Minimum lot area: 18,000 s.f.

E. Minimum lot width: 100 feet.

F. Minimum lot frontage: 35 feet.

G. Minimum heated floor area: 1,000 s.f. on ground level for less than two story.

1,100 s.f. for two story or more than two story dwelling with 850 s.f. on ground floor.

H. Minimum accessory structure requirements: Accessory structures may be located in rear or side yards, but shall not be located within a minimum yard.

4. Other regulations.

The headings below contain provisions applicable to uses allowed in the SUB C District.

Development regulations. Article XXXIV Exceptions. Section 4.3 Floodplain management. Section 4.24 Off-street parking and loading. Article XVIII Outside storage. Section 4.2 Landscape area and buffer regulations. Section 4.23 River protection. Metropolitan River Protection Act Signs. Article XXXIII

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:fulton-county/zoning/whole@2026-08-05-965468960a

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.