Modifications after Approval A. Administrative Modifications The following modifications to an approved development plan are allowed when the applicant notifies the Planning & Zoning Department before submitting a modified building permit development plan and as long as no modification violates the requirements of this Zoning Ordinance without securing an appropriate variance or administrative variance. 1. Reduction of the area of the building footprint. 2. Multi-family or mixed use building: Increase in the size of a proposed building footprint a maximum of 5%, provided the required number of parking spaces is met, the increase does not change stormwater drainage or exceed site coverage requirements, and the building locations and number of stories shown on the approved development plan do not change; 3. Reduction in the number of parking spaces in exchange for additional green space or in order to save trees, provided the number of required parking spaces provided does not fall below the minimum required. 4. Elimination of particular on-site sidewalks in conjunction with the reduction in building footprint area. The applicant must provide written notice to the Planning & Zoning Department if any of the above modifications have been made to an approved development plan. B. Non-Administrative Modification 1. Development plan modifications to an approved development plan, other than those listed in Sec. 8.7.4.A above, may be submitted to the Planning & Zoning Department for approval by the Planning Commission during the validity period of the development plan and during the construction period after obtaining a valid building permit. 2. Approval of such modifications will not extend the validity period of the development plan. 3. Modifications that affect the original intent of the approved development plan as determined by the Planning & Zoning Department must be processed as a new application and require the appropriate fees. C. Development Plan Validity 1. A development plan approved by the Planning Commission is only valid for 24 months from the date of approval, unless within such period a building permit is obtained and construction has commenced on the site. Land disturbance alone is not considered to be the start of construction. When a development plan approval expires due to construction not being commenced, any and all building permits issued consistent with that development plan also expire. D. Penalties A Certificate of Occupancy will be withheld from all projects not meeting the requirements of the approved development plan.