Chapter 10 - ADMINISTRATIVE PROCEDURES

10.00.03. Expiration of Approvals

About this text

  • As published by Municode, current through 2024-03-19
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Any building permit or other permit shall become void if the work authorized by the permit has not begun within six (6) months after the date of issuance of the permit.

B. If construction described in a building permit or other permit is suspended or abandoned after work has commenced, the permit shall expire twelve (12) months after the date that work ceased.

C. The time period for which a permit is valid may be extended for one (1) or more periods of not more than ninety (90) days each where an application for such extension is filed and such extension has been granted in writing by the County Administrator.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:gordon-county/zoning/10.00.03@2024-03-19-ee9735a0ff

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Gordon County Zoning Ordinance, 10.00.03. Expiration of Approvals | Georgia Commons