A. Purpose. This section is enacted to more efficiently provide for the safety of persons and vehicles traveling on the County roads of Gordon County, as allowed under
O.C.G.A. § 32-4-42(6).
B. Basis for ordering removal, relocation of facilities; failure to comply, removal by County
1. When the Board of Commissioners reasonably determines that any pipe, main, conduit, cable, wire, pole, tower or other signal and equipment, facilities or appliances of any utility in, on, along, over or under the public roads of the County should be removed or relocated because it has become an obstruction or interference with the use and safe operation of a County road, or will become an obstruction or interference with the use and safe operation of a contemplated
County road, a written notice shall be directed to the utility company, giving at least sixty (60) days' notice in which to make such change as is necessary for removal or relocation as may be necessary.
2. If the utility does not thereafter begin removal within a reasonable time sufficient to allow for engineering and other procedures reasonably necessary to the removal and relocation of the utility facility, the Board of Commissioners may give the utility a final notice directing that such removal shall commence not later than ten
(10) days from receipt of such final notice.
3. If such removal has not begun, or if such removal has begun and the relocation has not been completed within a reasonable time, the County may remove or relocate the same with its own employees, or by contracted labor, tools, equipment, supervision or other necessary services or materials and whatever else is necessary to accomplish the removal or relocation, and the expense thereof shall be charged to the utility.
4. Such expense shall be certified to the County Attorney, who shall have the authority to proceed with suit against the utility for same if payment or arrangements to make payment are not made within sixty (60) days.
C. Compensation of utility upon relocation. Nothing in this section shall be construed so as to deprive any utility, relocated from a location in which it owned a property interest, of compensation for such property interest.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.