Skip to content
Georgia Commons
Menu

Gray · Zoning Ordinance

Appendix A - ZONING AND SUBDIVISION REGULATIONS / Article XIV - REQUIRED SUBDIVISION IMPROVEMENTS

144.8. Reserved.

Reserved

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

144.9. Erosion control: Before commencement of any land disturbing activity, a land disturbance permit must be obtained from the planning and zoning office. All erosion and sedimentation control methods shown on the plan approved by the natural resources conservation service will be installed and inspected by the city superintendent or the zoning director prior to any land disturbance. All silt fences will be trenched into the ground a minimum of six inches with a mechanical trencher. All requirements of City of Gray Soil Erosion and Sedimentation Control Ordinance and sections 161, 162, 163 and 171, pages 108-128 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition will be met. All required erosion and sedimentation control methods will be maintained until final stabilization is achieved.

144.10. Clearing and grubbing: Clearing and grubbing shall begin after all erosion control measures are properly installed. The clearing operation will be checked periodically by the city superintendent or the zoning director. All clearing has to be completed and approved by the city superintendent or the zoning director before grading can begin. All clearing and grubbing will be performed in accordance with section 201, pages 129-134 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition.

144.11. Subgrade construction: Grading construction operations will begin after the clearing and grubbing has been approved by the city superintendent or the zoning director. The streets will be graded according to the typical section found in section 145.6 of this ordinance. The city superintendent or the zoning director will do periodic checks during the grading operations and call for compaction tests as needed. 95 percent compaction is required with the last six inches being 100 percent compaction. Any unsuitable material is to be removed and replaced. All subgrade construction will be performed in accordance with section 209, pages 156-159 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition.

144.12. Graded aggregate construction: After the top six inches of subgrade have been completed per the typical section found in section 145.6, have achieved 100 percent compaction and been approved by the city superintendent or the zoning director, the contractor may begin placing graded aggregate base material. The base shall be six inches thick with 100 percent compaction as shown in the typical section. All graded aggregate base construction will be performed in accordance with section 310, pages 226-230 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition.

144.13. Bituminous prime: After the graded aggregate base operations are complete with a 100 percent compaction that conforms to the typical section and has been approved by the city superintendent or zoning director, it shall be primed. After the prime has been applied, a seven day waiting period is needed for curing. All bituminous prime will be applied in accordance with section 412, pages 283-285 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition.

144.14. Hot mix recycled asphaltic concrete: After the curing period is complete on the bituminous prime, the contractor can begin placing the two inches of recycled asphaltic concrete "B" binder. After the binder material has been in place for 21 /2 years, the contractor

will place the one inch of recycled asphaltic concrete "E" mix. Both layers of the recycled asphaltic concrete are to have a compaction of 96 percent of the theoretical density. All recycled asphaltic concrete will be applied in accordance with sections 402 and 828, pages 270-273, 919-924 of the Georgia Department of Transportation Standard Specifications Construction of Roads and Bridges, 1993 Edition.

144.15. Testing: Engineering analysis shall be performed according to the following matrix:

TYPE OF TESTS TO BE PERFORMED

MINIMUM NUMBER OF

TESTS TO BE PERFORMED TESTING STANDARD

Subgrade Compaction (Density - in place) Subgrade Fill Compaction One per 500 Linear Feet of Roadway One per every two to three feet of Vertical Fill 95% Maximum Density

ASTM - 1557, D-1556, D-2992,

& D-2167 100% Maximum Density on the final 6".

Base Compaction (Density-in place) Depth Check One per 500 Linear Feet of Roadway (Same as Compaction) 100% Maximum Density

ASTM - 1557

Modified Proctor Asphaltic Concrete (Density - in place) One per 1,000 Linear Feet of Roadway 92% Laboratory Density

144.16. Required Notification. The developer shall notify the city superintendent, or other authorized city official, a minimum of 24 hours in advance when the roadway is ready to be tested.

144.17. Financial Responsibility. The developer will be financially responsible to the testing agency for all required tests.

144.18. Proofroll. All sub-base base will be load tested with a minimum 18 ton tandem dump, or equal, to cover base thoroughly by lapping the tires on width each pass to assure a minimum tolerance of 1

/2 inch of settling and to insure no cracking or pumping prior to paving. This is to be witnessed by the city superintendent, zoning director, or designated city representative.

History

The history line the source prints at the end of the section.

(Ord. No. 07-O-003, 3-5-2007)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:gray/zoning/144.8@2026-11-11-b578ee5f90

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Gray Zoning Ordinance, 144.8. Reserved | Georgia Commons