Gray · Zoning Ordinance

Appendix A - ZONING AND SUBDIVISION REGULATIONS / Article XIV - REQUIRED SUBDIVISION IMPROVEMENTS

Section 148. Administrative procedures.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The administrative procedures for installing the subdivision improvements required herein shall be as follows:

148.1. When construction may begin. Construction and installation of any required public improvements as described herein shall not begin until the commission has given preliminary approval of the new subdivision. The subdivider shall then confer with the zoning enforcement officer to determine the method and estimated cost of the construction and installation of the required improvements.

148.2. Inspections and approval by the council. During the construction and installation of the required public improvements, the zoning enforcement officer shall from time-to-time make field inspections and supervise said work as predetermined and agreed upon by the zoning enforcement officer and the subdivider. After completion of all the construction and installation of the required public improvements and if the said work has met the specifications as described herein, as determined by the zoning enforcement officer, the zoning enforcement officer shall notify the subdivider in writing of the approval of said work.

148.3. Official acceptance by the council. The council shall officially accept the completed work on the construction and installation of required public improvements one year from the date of the written acceptance by the zoning enforcement officer.

148.4. Performance bond. If the subdivider does not wish to construct and install any required public improvements as described herein prior to submitting the subdivision plat to the commission for final approval, a performance bond shall be required, such bond being equal to the estimated cost of construction. When the work has been completed satisfactorily, the council shall release 90 percent of the funds in escrow with a letter of approval to the subdivider. The remaining ten percent shall remain in escrow for maintenance purposes.

148.5. Maintenance of completed work. The subdivider shall maintain his completed work until the official acceptance by the council as described in section 148.4 above. The subdivider shall be required to sign a maintenance bond agreement with the council. If a maintenance bond is posted by the subdivider, a bond equaling ten percent of the construction cost shall be required. During the maintenance period, the zoning enforcement officer shall make final inspection and notify the subdivider and the bonding company, or in cases where funds are being held in escrow, the cost of making such corrections shall be deducted from these funds, and the subdivider charged with any costs above the amount of escrow funds. If the work is acceptable at this time, the remaining ten percent of the escrow funds shall be released to the subdivider.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:gray/zoning/148@2026-11-11-eb4769aa67

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Gray Zoning Ordinance, Section 148. Administrative procedures | Georgia Commons