10.1.7. Penalties and Incentives

About this text

  • As published by Municode, current through 2026-05-28
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Failure to obtain a permit for landdisturbing activity. If any person commences any land-disturbing activity requiring a land-disturbing permit as

prescribed in this section without first obtaining said permit, the person shall be subject to double permit fees at the time the permit is obtained and/or revocation of his business license, work permit, or other authorization for the conduct of

a business and associated work activities within the jurisdictional boundaries of the local issuing authority. It is the responsibility of the property owner to ensure that the proper permit is obtained.

B. Stop-work orders.

1. For the first and second violations of the provisions of this section, the Director or the local issuing authority shall issue a written warning to the violator. The violator shall have

five days to correct the violation. If the violation is not corrected within five days, the Director or local issuing authority shall issue a stopwork order requiring that landdisturbing activities be stopped until necessary corrective action or mitigation has occurred; provided, however, that, if the violation presents an

imminent threat to public health or waters of the state, the Director or local issuing authority shall issue an immediate stop-work order in lieu of a warning;

2. For a third and each subsequent violation, the Director or local issuing authority shall issue an immediate stop-work order; and

3. All stop-work orders shall be effective immediately upon issuance and shall be in effect until the necessary

corrective action or mitigation has occurred.

4. When a violation in the form of taking action without a permit, failure to maintain a stream buffer, or significant amounts of sediment, as determined by the local issuing authority or by the Director or their designee, have been or are being discharged into state waters and where best management practices have not been properly designed, installed, and maintained, a stopwork order shall be issued by the local issuing authority or by the

Director or their designee. All such stop-work orders shall be effective immediately upon issuance and shall be in effect until the necessary corrective action or mitigation has occurred. All such stop-work orders

shall apply to all land-disturbing activity on the site with the exception of the installation and maintenance of temporary or

permanent erosion and sediment controls.

5. While a stop-work order is in effect, the Building Inspection Department shall conduct no inspection on the property except for soil erosion

inspections, and all work on the site, except that work necessary to achieve compliance with this section, shall cease until compliance is achieved.

C. Bond forfeiture. If, through inspection, it is determined that a person engaged in land-disturbing activities has failed to comply with the approved plan, a written notice to comply shall be served upon that person. The notice shall set forth the measures necessary to achieve compliance with the plan and shall state the time within which such measures must

be completed. If the person engaged in the land-disturbing activity fails to comply within the time specified, he or she shall be deemed in violation of this section and, in addition to other penalties, shall be deemed to have forfeited his or her performance bond, if required to post one under the provisions Sec. 10.1.4.C.2.g.

The local issuing authority may call the bond or any part thereof to be forfeited and may use the proceeds to hire a contractor to stabilize the site of the land-disturbing activity and bring it into compliance.

D. Civil penalties. Any person who violates any provisions of this section, the rules and regulations adopted pursuant to this section, or any permit condition or limitation established pursuant to this section, or who negligently or intentionally fails

or refuses to comply with any final or emergency order of the county issued as provided in this section shall be liable for a civil penalty not to exceed $2,500.00 per day. For the purpose of enforcing the provisions of this section, notwithstanding any provisions of the Official Code of Hall County, the Magistrate Court of

Hall County shall be authorized to impose a penalty not to exceed $2,500.00 for each violation. Notwithstanding any limitation of law as to penalties which can be assessed for violations of county ordinances, any other court of competent jurisdiction trying cases brought as violations of this section likewise shall be authorized to impose penalties for such

violations not to exceed $2,500.00 for each violation. Each day during which a violation or failure or refusal to comply continues shall be a separate violation.

E. Penalty. Any person, firm, corporation, association or partnership violating any provision of this section as the same exists or as it may hereinafter be amended, or shall fail to do anything required by this section as the same exists or as it may hereafter be amended, shall be guilty of a misdemeanor, amenable to the process of the Magistrate or State Court of Hall County, and upon conviction, shall be punished as provided in the Official Code of Hall County, Georgia for each violation in the discretion of the Court.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/10.1.7@2026-05-28-bd0204e011

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.