Periodic inspections of the stormwater management system during construction shall be conducted by the staff of the county or conducted

and certified by a professional engineer who has been approved by the county. Inspections shall use the approved stormwater management plan for establishing compliance. All inspections shall be documented with written reports that contain the following information:

A. The date and location of the inspection;

B. Whether the stormwater management system is in compliance with the approved stormwater management plan;

C. Variations from the approved stormwater management plan; and

D. Any other variations or violations of the conditions of the approved stormwater management plan.

10.5.14. Final Inspection; As-Built Drawings; Delivery of Inspection and Maintenance Agreement

Upon completion of the development, the applicant is responsible for:

A. Certifying that the stormwater management system is functioning properly and was constructed in conformance with the

approved stormwater management plan and associated hydrologic analysis,

B. Submitting as-built drawings showing the final design specifications for all components of the stormwater management system as certified by a professional engineer,

C. Certifying that the landscaping is established and installed in conformance with the BMP landscaping plan, and

D. Delivering to the county a signed inspection and maintenance agreement that has been recorded by the owner in the

property record for all parcels that make up the site.

The required certification under part A shall include a certification of volume, or other performance test applicable to the type of stormwater management system component, to ensure each component is functioning as designed and

built according to the design specifications in the approved stormwater management plan. This certification and the required performance tests shall be performed by a qualified person and submitted to the county with the request for a final inspection. Hall County shall perform a final inspection with applicant to confirm applicant has fulfilled these responsibilities.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/10.5.13@2026-05-28-1f978a1217

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.