Subject to the applicability criteria in Sec. 10.5.6 and exemptions in Sec. 10.5.7, the following stormwater management standards apply.
Additional details for each standard can be found in the GSMM Section 2.2.2.2:
A. Design of stormwater management system. The design of the stormwater management system shall be in accordance with the applicable sections of the GSMM as directed by the administrator. Any design which proposes a dam shall comply with the Georgia Safe Dams Act and Rules for Dam Safety as applicable.
B. Natural resources inventory. Site reconnaissance and surveying techniques shall be used to complete a thorough assessment of existing natural resources, both terrestrial and aquatic, found on
the site. Resources to be identified, mapped, and shown on the stormwater management plan, shall include, at a minimum (as applicable):
1. Topography (minimum of two-foot contours) and steep slopes (i.e., areas with slopes greater than 15 percent),
2. Natural drainage divides and patterns,
3. Natural drainage features (e.g., swales, basins, depressional areas),
4. Natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers, drinking water wellhead protection areas and river corridors,
5. Predominant soils (including erodible soils and karst areas), and
6. Existing predominant vegetation including trees, high quality habitat and other existing vegetation.
C. Better site design practices for stormwater management. Stormwater management plans shall preserve the
natural drainage and natural treatment systems and reduce the generation of additional stormwater runoff and pollutants to the maximum extent practicable.
Additional details can be found in the GSMM Section 2.3.
D. Stormwater runoff quality/reduction. Stormwater runoff quality/reduction shall be provided by using the following:
1. For development with a stormwater management plan submitted before December 1, 2020, the applicant may choose either a. runoff reduction or b. water quality [below].
2. For development with a stormwater management plan submitted on or after December 1, 2020, the applicant shall choose (a) runoff reduction and additional water quality shall not be required. To the extent a.
runoff reduction has been determined to be infeasible for all or a portion of the site using the practicability policy, then b. water quality shall apply for the remaining runoff from a 1.2 inch rainfall event and must be treated to remove
at least 80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM.
a. Runoff reduction—The stormwater management system shall be designed to retain the
first one inch of rainfall on the site using runoff reduction methods, to the maximum extent practicable.
b. Water quality—The stormwater management system shall be designed to remove at least
80 percent of the calculated average annual post-development total suspended solids (TSS) load or equivalent as
defined in the GSMM for runoff from a 1.2 inch rainfall event.
3. If a site is determined to be a hotspot as detailed in Sec. 10.5.6, the county may require the use of specific
or additional components for the stormwater management system to address pollutants of concern generated by that site.
E. Stream channel protection. Stream channel protection shall be provided by using all of the following three approaches:
1. 24-hour extended detention storage of the one-year, 24-hour return frequency storm event;
2. Erosion prevention measures, such as energy dissipation and velocity control; and
3. Preservation of any applicable stream buffer.
F. Overbank flood protection.
Downstream overbank flood protection shall be provided by controlling the postdevelopment peak discharge rate to the pre-development rate for the 25-year,
24-hour storm event. If control of the one-year, 24-hour storm is exempted, then peak discharge rate attenuation of the
two-year through the 25-year return frequency storm event must be provided.
G. Extreme flood protection. Extreme flood protection shall be provided by controlling the 100-year, 24-hour storm event such that flooding is not exacerbated.
H. Downstream analysis. Due to peak flow timing and runoff volume effects, some structural components of the stormwater management system fail to reduce discharge peaks to pre-development levels downstream from the site. A downstream
peak flow analysis shall be provided to the point in the watershed downstream of the site or the stormwater management system where the area of the site comprises ten percent of the total drainage area in accordance with Section 3.1.9 of the GSMM. This is to help ensure that
there are minimal downstream impacts from development on the site. The downstream analysis may result in the need to resize structural components of the stormwater management system.
I. Stormwater management system inspection and maintenance. The components of the stormwater management system that will not be dedicated to and accepted by the county, including all drainage facilities, best management
practices, credited conservation spaces, and conveyance systems, shall have an inspection and maintenance agreement to ensure that they continue to function as designed. All new development and redevelopment sites are to prepare a comprehensive inspection and maintenance agreement for the on-site stormwater management system. This plan shall be written in accordance with the requirements in Sec. 10.5.19.
J. Stormwater management system drainage and access easements. Drainage and access easement(s) will be in favor of Hall County, Georgia to allow
Hall County, Georgia to inspect and maintain (on publicly maintained systems) the system, as necessary. No obstruction
shall be built, constructed, or planted that would inhibit proper function of the system, associated drainage systems, or
the easement(s).
1. Stormwater management system easements, residential. The developer shall execute 20-foot easements in favor of Hall County, Georgia to include the following:
a. An easement encompassing the entire perimeter of any stormwater management facilities that shall be measured from
the 100-year stormwater ponding limits or six inches above the elevation of the overflow.
Easement shall encompass entirety of the stormwater management system as well.
The entire dam structure shall be included as well, and easement should extend 20 feet beyond the dam toe of slope.
b. A 20-foot drainage easement measured ten feet in both directions from the appropriate centerline of all associated piping, channels, ditches, streams or
other areas that are designed for stormwater to flow to and from the stormwater management facility;
c. A 20-foot access easement connecting the facility to the nearest public road;
d. Access easements can be combined with drainage easements where a pipe exists with a width of 30 feet provided
easement is off center with the pipe such that there is 20 feet clear on one side for access.
e. No portion of the easement(s) to and from the Hall County, Georgia road and around the perimeter of the facility will be steeper than a grade of 3:1.
The access easement must be clearly staked at the time of final platting.
2. Stormwater management system easements, nonresidential. The property owner shall execute a 20-foot drainage easement surrounding the entire perimeter of the facility in favor of Hall County, Georgia to allow Hall County, Georgia to
inspect and observe the facility, as necessary. The easement boundary shall be measured from the 100- year stormwater ponding limit or six inches above the elevation of the overflow. The entire dam structure shall be included as well. Easement shall encompass entirety of the stormwater management system as well. The property owner shall additionally grant permission to Hall County, Georgia, its authorized agents and employees, to enter upon the property and to inspect the facilities whenever Hall County, Georgia deems necessary. Hall County,
Georgia maintains the right to make emergency repairs to the facility as deemed necessary. No obstruction shall be built, constructed or planted that would inhibit proper function of the facility, associated drainage systems, or the easement(s).
K. Hall County specific design requirements.
1. Fencing. Fences and warning signs will be required on all detention facilities, constructed wetlands, retention ponds or similar devices where the sides of the device adjacent to the water are steeper than a 3:1 grade and the depth of the water in the pond is greater than three feet during a 25-year storm event. Fences shall be five feet tall with a 14-footwide gate. Fences may be chain link or other approved material. The
gate shall be locked with a Master Number One lock that is keyed as per the Hall County Engineer.
Residential fences shall be located on the outside edge of the 20-foot perimeter easement and must allow complete access to facility and dam.
Commercial fencing should be located on the outside edge of the 20-foot perimeter easement when possible but may be located elsewhere with the Hall County Engineering Department's approval.
2. Survey marker. A concrete survey marker shall be placed in the near vicinity of the stormwater management facility. The marker shall be a minimum of five inches by five inches
in width and be embedded one foot into the ground. The marker shall have a "PK" nail embedded in the top. The marker must be placed above the high water elevation of the facility and within the drainage easement area. Alternate survey markers are allowed with prior approval from the Hall County Engineer.
3. Outlet structure and piping construction. Outlet structures and piping for residential above-ground detention facilities must be constructed of concrete to be eligible for
acceptance into the Hall County, Georgia maintenance system.
4. Residential underground stormwater management facilities.
Residential underground stormwater management facilities must be constructed of materials with a
service life of greater than 50 years, and must be designed to allow for proper inspection and maintenance.
Residential underground facilities will not be accepted into the Hall County, Georgia maintenance system until the subdivision has reached a point of 85 percent build-out, or greater. Until such acceptance time, the underground facilities must be bonded for 100 percent of entire cost of facility.
5. Residential stormwater management facilities with retaining walls or water. Retaining walls, micro
pools, permanent pools, ground water present, holding water, or any facility which is constructed to provide 80 percent removal of Total
Suspended Solids for water quality as part of stormwater management facilities will not be accepted into the county maintenance system. An appropriate private maintenance agreement for these facilities must be in place prior to final plat.
6. Individual lot residential BMPs.
Individual lot residential BMPs, including, but not limited to, downspout disconnects, individual rain gardens, or other BMPs designed to treat a single residential lot, are not eligible for acceptance into the county maintenance system.
An appropriate private maintenance agreement for these facilities will need to be in place prior to final plat.
7. Stormwater management facility dams. Dams for stormwater management facilities need to be at least 20 feet from the nearest property line
as measured from the toe of slope for an earthen dam or edge of footer for a concrete structure.
8. Proprietary devices. Proprietary devices or facilities may be allowed with proper third party testing data that follows the testing protocol as set forth by the Metropolitan North Georgia Water Planning District.
Such devices or facilities are not eligible for acceptance into the county maintenance system. An appropriate private maintenance agreement for such devices or facilities must be
in place prior to final plat.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.