A. General Requirements Applicants must locate all utility facilities underground throughout the subdivision unless topographical challenges necessitate aerial utilities, as approved by the Director. All existing and proposed utility easements outside of road rightsof-way must be shown on the preliminary and final plats.

B. Location All utilities must be located in accordance with the standard detail drawing for

utility location within the right-of-way of subdivisions as shown on Plates 4, 4A,

4B, and 4C of the Hall County Standard Details and must be shown on the typical roadway section of the preliminary plans.

Hall County strongly encourages the utilization of a joint trench for the power, telephone, fiber optic, and cable lines.

C. Width of Easements Along Rear or Side Lot Lines Utility easements for sewage lines, water lines, or other such utilities located along rear lot lines or side lot lines or passing through a lot must be at least 20 feet

wide, ten feet on each lot, and more if necessary. Easements for storm sewers must be the width as indicated in Table 9.3.4.

Table 9.3.4 Easement Width for Stormwater Infrastructure Pipe Size

(Inches) Maximum Pipe Invert Depth (Ft) — 4 5 6 7 8 9 10 11 12 13 14 15 16 15 20 20 20 20 20 25 25 30 30 30 35 35 40 18 20 20 20 20 20 25 25 30 30 30 35 35 40 24 20 20 20 20 20 25 25 30 30 30 35 35 40 30 20 20 20 20 25 25 25 30 30 35 35 35 40 36 20 20 20 20 25 25 25 30 30 35 35 35 40 42 20 20 20 25 25 30 30 30 35 35 40 40

48 20 20 20 25 25 30 30 30 35 35 40 40 54 20 25 25 25 30 30 35 35 35 40 40 60 20 25 25 25 30 30 35 35 35 40 40 66 25 30 30 30 35 35 40 40 40 72 25 30 30 30 35 35 40 40 40

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hall-county/zoning/9.3.22@2026-05-28-816a6b4eec

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hall County Zoning Ordinance, 9.3.22. Utilities | Georgia Commons