Appendix A - UNIFIED DEVELOPMENT CODE / 9.7 - Required Improvements
9.7.3. Delay of Installation of Paving
About this text
- As published by Municode, current through 2026-05-28
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Paving must be completed under one of the following two options:
A. Application of the bituminous plant mix surface may be completed before the filing of a final plat.
B. Application of the bituminous plant mix surface may be delayed because of unsuitable weather until no later than June 1 of the year following the filing of the final
plat if the final plat is submitted for approval after October 1 of the first year;
provided that all other required improvements, including grassing, must be completed prior to approval of the final
plat. In such case, the subdivider must present to the County Engineer an improvement guarantee in the form of a signed contract with a known contractor for paving and a surety or escrow agreement payable to the county for the cost of the paving, not less in amount than the
average county contract price for the paving established by the Georgia Depart- ment of Transportation or the contract price, whichever is greater. The County Engineer may approve the amount and may increase the amount for increases due to normal inflation. The County Engineer may require that paving be completed at the first instance of suitable weather and availability of paving materials.