Haralson County · Zoning Ordinance
Part - CODE OF ORDINANCES / Chapter 50 - ZONING TABLE OF CONTENTS / Article VIII - ADMINISTRATION, ENFORCEMENT AND PENALTIES
Sec. 50-230. Construction progress.
About this text
- As published by Municode, current through 2023-06-06
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Any building permit issued shall become invalid unless the work authorized by it shall have been commenced within six months of the date of issue or if the work authorized by the permit is suspended or abandoned for an aggregate period of six months. Any building permit issued shall be valid for a maximum of 18 months but may be renewed by Haralson County. Anyone that does not comply with the ordinance by obtaining a building permit before work is commenced will be sent a letter and fined double the amount the original permit would have cost. If this is not paid to the permit office within 15 [days] of the date of the letter, the county marshal will issue a court citation.
History
(Ord. of 12-7-2004, art. XII, § 12.4; Ord. of 11-3-2009(7))