management. (a) All stormwater detention facilities shall be designed to detain the 1-year storm runoff, for the area draining to the pond, for 24 hours. For the project, this volume, called the channel protection volume, shall be equal to or greater than the 1-year storm runoff volume from the project. In addition, these facilities shall control the peak flow rates associated with storms having 2-year, 5-year, 10-year, and 25-year return frequencies so that flows from the developed site do not exceed those associated with predevelopment conditions at the project boundary nor increase the peak flows downstream from the project to the point in the drainage basin where the project area is 10% of the total basin. Where adverse impacts occur during the 100-year storm, the 100-year storm shall also be regulated. (b) To eliminate detention facilities for stormwater, a registered design professional shall evaluate the basin utilizing the ten percent rule as defined in the current edition of the "Georgia Stormwater Management Manual." The design professional shall demonstrate that post-developed peak flows at the ten percent point of analysis are not increased for all storm events up to and including the 25-year storm. Where adverse effects occur for the 100-year storm, the 100-year storm shall also be regulated. (c) Non-detained, post development runoff shall leave the project site as sheet flow and will not have an adverse impact on downstream properties. (d) As part of the hydrological study, the design professional shall complete a downstream analysis in accordance with the current edition of the "Georgia Stormwater Management Manual." Consideration shall be given to the flow capacity of downstream drainage structures from the property line up to and including the 10% point of analysis. If the downstream system is inadequate, the developer is required to either improve the downstream drainage structure or provide additional storage in the detention facility. (e) In approved cases, damming a natural basin with minimal clearing may provide the detention. In such cases: (1) The required discharge structure opening must be large enough to prevent stoppage from leaves and other debris naturally occurring. Also, the volume should be adequate to account for natural growth of vegetation. (2) Documentation shall be provided for the natural drainage way that it is not jurisdictional state waters or for an approved Georgia EPD Buffer Variance Application. (3) Documentation shall also be provided showing compliance with the Clean Water Act Section 404, permitting requirements. (4) Fencing of natural ponds shall be considered by the Public Works Director on a case-by-case basis.