Sec. 336. Solar collection systems.

About this text

  • As published by Municode, current through 2023-12-05
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

Solar collection systems shall be considered an accessory use where allowed, in accordance with Table 2-2 in Article 2 (Use of Land and Structures) and shall meet the following requirements:

(a) Special use approval required. This use requires special approval in accordance

with applicable procedures set forth in Article 11 (Procedures and Permits) of this Development Code.

(b) Minimum standards.

(1) Minimum lot size required to install solar collection systems (i.e., solar

farms) shall be 50 acres. This does not apply to individual roof-mounted solar panels.

(2) A solar panel site located in a resort zoning district, and not on an

individual residential property within the district, shall require the submittal of an addendum to the resort master plan for review and approval by the Planning Commission and Board of Commissioners.

(3) Freestanding solar panels located on the ground or attached to a framework located on the ground shall not exceed 20 feet in height above the ground.

(4) Freestanding solar panels shall meet the required setback for principal

structures in the district in which they are located.

(5) The total coverage of a lot with freestanding solar panels shall not exceed 50% of the total lot coverage or the maximum allowable coverage for the district in which they are located, whichever is greater.

(6) A 50-foot undisturbed, vegetative buffer is required along the perimeter of the installation area where the solar panels are located and must provide sufficient screening from adjacent properties and/or the public right-of-way. The buffer shall be installed so that it remains opaque at all times (i.e., evergreen species).

(c) Roof-mounted solar panels.

(1) Roof-mounted solar panels installed on a building or structure with a sloped roof shall not exceed the height requirements for the district in which they are located.

(2) Systems located on the roof shall provide, as part of their permit application,

evidence of design review and structural certification if the slope of the panel

differs from the roof pitch. All panels on commercial roofs shall provide this

information regardless of slopes, as well as any residential roof with greater than 50 percent coverage.

(d) A solar energy system shall not be used to display advertising, including signage, streamers, pennants, spinners, reflectors, ribbons, tinsel, balloons, flags, banners or similar materials.

(e) The identification of the manufacturer(s) or installer and appropriate warning signage shall be posted on or near the panels in a clearly visible manner.

(f) No solar energy system shall be installed until evidence has been presented to the Community Development Department

that the electric utility company has been informed of the customer's intent to install an interconnected customer-owned generator. Off-grid systems shall be

exempt from this requirement.

(g) Decommissioning requirements: The following requirements shall be met for decommissioning solar collection systems:

(1) Freestanding solar collection systems that have not been active and in

continuous service for a period of one year shall be removed at the expense of the owner or operator.

(2) The site shall be restored to as natural condition as possible within six months of the removal.

(h) Permitting requirements: The following requirements shall be met for building/

development permit applications for a solar collection system:

(1) A descriptive plot plan including setbacks, panel sizes, locations of property lines, buildings, and road rights-of-ways for freestanding solar panels.

(2) A map and list indicating the location of existing solar collection facilities or substations within a twomile radius

(3) Any other relevant studies, reports, certificates and approvals as may

be reasonably requested by the Community Development Department, including, but not limited to, design

review.

(4) Any panels installed to be used by someone other than the owner of the property shall provide an affidavit or evidence of agreement between the lot owner and facility's owner or operator confirming the facility owner or operator has permission of the property owner to install and utilize solar panels.

(5) Any additional documents needed to indicate compliance with the standards set forth in this Section or as required by the Community Development Department.

(6) Fees shall be submitted to the Community Development Department according to the fee schedule

approved by the Board of Commissioners.

(i) Reclamation bond.

(1) A reclamation bond shall be posted by the property owner to ensure that the County has sufficient funds to reclaim the site in the case the permittee fails to complete the approved reclamation plan.

(2) The bond shall meet requirements set forth by the Community Development Department.

(3) Prior to acceptance, any surety shall be approved by the Board of Commissioners.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:harris-county/zoning/336@2023-12-05-81fd02d28e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Harris County Zoning Ordinance, Sec. 336. Solar collection systems | Georgia Commons