Utilities placed underground shall be placed within the right-of-way as follows (see Typical Street Section C at the end of this article):

a. Sanitary sewer following generally the center line of the street, no less than six (6) feet below the street surface and providing a minimum slope of laterals to abutting properties of one percent.

b. Other utilities, when placed underground along the roadway, shall be located in the shoulder of the road and shall be placed at the following distances measured from the back of curb or edge of pavement, and placed at or below the depths indicated as follows:

Type of Utility by Side of Street Back from curb or pavement Minimum depth

NORTH OR WEST SIDE

TV Cable 0.5 feet 1.5 feet Telephone Cable 2.5 feet 2.0 feet Water Main 5.0 feet 3.0 feet Power 9.5 feet 3.0 feet

SOUTH OR EAST SIDE

TV Cable 0.5 feet 1.5 feet Telephone Cable 2.5 feet 2.0 feet Gas Main 7.0 feet 2.5 feet Power 9.5 feet 3.0 feet (Ord. of 5-10-96)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:hawkinsville/zoning/4.5.6@2026-11-11-2c9e8b80d3

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Hawkinsville Zoning Ordinance, Sec. 4.5.6. Location of utilities | Georgia Commons