a. In order to obtain a Development Permit, a hydrology report shall be prepared that includes appropriate calculations for the two (2) year, ten (10) year, twenty-five (25) year, and one hundred (100) year design frequency storms. The report shall show detailed calculations indicating the formula used, along with the co-efficient of run-off, the time of concentration, the rainfall intensity, the discharged velocity, and the source of all data used. b. The hydrology report shall include a map outlining the areas and showing the acreage of all on-site and off-site drainage basins contributing flow through the project. c. The hydrology report shall include calculations for the runoff peak rate of discharge to determine the configurations and sizes of pipes, channels and other routing or flow control structures; and the runoff volume to determine the necessity for and sizing of stormwater detention facilities. d. Runoff peak rate of discharge for drainage areas up to three hundred (300) acres in size shall be calculated using the Rational Method, with a minimum time of concentration of ten (10) minutes. Flows from drainage areas larger than three hundred (300) acres in size shall be calculated using the SCS Method. e. Runoff coefficients used for pre- and post-development activity conditions for the Rational Method shall be consistent with local conditions. For the SCS Method, the runoff curve numbers found in the Manual for Erosion and Sediment Control in Georgia shall be used. f. Runoff volume for drainage areas up to five (5) acres in size shall be calculated using the Rational Method triangular hydrography approximation. Flows from drainage areas larger than five (5) acres in size shall be calculated using the SCS Method. g. Hydraulic capacity for open channel or closed conduit flow shall be determined using the Manning Equation. h. The stormwater flow velocity at the site's downstream property line shall not exceed the pre-development activity velocity.