Requests for inspections shall be made by the owner or contractor to the Building Inspector at least twenty-four (24) hours prior to when the inspection is needed. Inspections shall be made and passed prior to continuation of further activity or proceeding into new phases. Inspections are required of each of the following phases, as applicable to the actual work to be performed under the development permit: a. Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, inspection of erosion and sedimentation control measures and protective devices for undisturbed areas. b. Upon completion of street grading, inspection and approval shall be required prior to trenching or continuation with subgrade preparation. c. Upon installation of storm drainage pipe, detention, or other stormwater facilities. d. Street curbing and gutter. Inspection shall be requested after the forms or string line have been set. Street width and vertical and horizontal alignment may be spot checked. e. Sub-grade of streets. After compaction and receipt of test reports by the Building Inspector the sub-grade may be roll tested with an 18-ton tandem dump truck and shall pass to the satisfaction of the Public Works Director. f. Street base. After receipt of test reports by the Building Inspector, the base may be string-lined for depth and crown. The street base may be roll-tested with an 18-ton tandem dump truck and shall pass to the satisfaction of the Public Works Director. g. Paving. The Public Works Director shall be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored and the street will be cored after completion to check thickness and density. Satisfactory test results of the cores shall be delivered to the Building Inspector prior approval of a final subdivision plat or certificate of occupancy.