Hogansville · Zoning Ordinance
Part II - CODE OF ORDINANCES / Chapter 102 - UNIFIED DEVELOPMENT ORDINANCE / Article IX - SUBDIVISIONS
Sec. 102-C-9-53. Required improvements for public and private streets.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) Specifications not covered herein shall be performed in accordance with the latest Georgia Department of Transportation and AASHTO standard specifications.
(2) A maintenance bond or other surety shall be furnished which shall name the city as a principal equally with the owner and shall be worded to include in its coverage a one-year maintenance warranty period following acceptance of the improvements by the city.
(3) The arrangement, character, extent, width, grade and location of all streets shall conform to the comprehensive plan. New streets shall be considered in their relation to existing and planned streets, topographic conditions, public convenience and safety, and in their appropriate relation to the proposed uses of the land to be served by such streets.
(4) When such is not shown in the comprehensive plan, the arrangement of streets in a subdivision shall:
(a) Extend existing streets or their projections at the same or greater width, but in no case less than the minimum required width, unless variations are deemed necessary by the zoning administrator for reasons of topography or design;
(b) Connect to existing streets if required by the city to create connectivity and traffic circulation; and
(c) Provide traffic management features for traffic calming if required at the discretion of the zoning administrator.
(5) Where a subdivision abuts or contains an existing or proposed through street with a speed limit greater than 30 mph, access shall be limited to ensure adequate protection of residential properties and maintain public safety. The following measures may be required by the zoning administrator:
(a) Deceleration stacking lane with taper.
(b) Acceleration lane with taper.
(c) Left turn stacking lanes with tapers.
(d) Reverse frontage lots with screen planting strip along the rear property line or such other treatment as may be required to afford adequate separation from through street.
(e) The Georgia Department of Transportation Driveway Manual "Regulations for Driveway and Encroachment Control" shall be used as a design guide.
(f) A subdivision plat involving new or existing streets crossing railroad tracks shall provide adequate right-of-way, including approach right-of-way and slope easements for construction of underpass or overpass unless otherwise determined by the zoning administrator.
(6) Privately owned reserve strips controlling access to streets shall be prohibited.
(7) Street jogs with centerline offsets of less than 125 feet shall be prohibited.
(8) Street intersections should be as nearly at right angles as practical.
(9) Street right-of-way width and curb and gutter requirements shall be provided as regulated in the Street Thoroughfares Table of Sec. 102-C-9-52.
(10) Curb and gutter shall be required on all streets and shall be furnished and installed by the subdivider or his agent in conformance with the latest thoroughfare design standards.
Distance from back of curb to back of curb must not be less than 26 feet.
(11) Base and paving. Minimum road width of 26 feet from back of curb to back of curb shall be furnished and paid for by the subdivider or their agent. Installation shall conform to the Street Thoroughfares Table of Sec. 102-C-9-52. The minimum acceptable paving cross section, unless otherwise modified by the zoning administrator for proposed city streets shall be:
(a) One and one-half inch, twelve and one-half mm asphalt wearing course. (Two inch, nine and one-half mm wearing course optional with approval of the zoning administrator.)
(b) Three inch, 19 mm binder.
(c) Eight inch G.A.B. (graded aggregate base) compacted to 100 percent. STD density per ASTM D698. The asphalt-wearing course must be laid before a period of one year after the streets have passed final inspection and the final plat has been recorded.
(12) Testing thickness and compaction. The zoning administrator or their designee shall make as many tests as necessary to determine the average thickness and compaction of the base course prior to placing of surface course. Tests shall also be made on the finished courses if necessary. When the subdivider or their agent or contractor disagrees with the administrator's tests and prefers a consulting firm to be employed, said consulting firm shall be employed at the subdivider or their agent's expense.
(a) Compaction. Fill shall be placed in uniform, horizontal layers not more than six inches thick (loose measurement). Moisture content shall be adjusted as necessary to compact material to 98 percent maximum laboratory dry density as determined by
ASTM D698.
(b) Utility installation. After the earthwork has been completed, all storm drainage, water, and sanitary sewer utilities have been installed within the right-of-way as appropriate, and the backfill in all such ditches thoroughly compacted, the sub-grade shall be brought to the lines, grades, and typical roadway section shown on the approved plans.
(c) Compaction testing. Utility trenches cut in the sub-grade shall be backfilled as specified herein. Compaction tests at the rate of one per 150 feet of trench may be required to verify compaction.
(d) Proof-roll. Test 1 Sub-grade must pass roll testing with a fully loaded tandem axle dump truck prior to placement of the base material. With the approval of the zoning administrator, a geo-textile or grid may be used to stabilize a sub-grade that does not pass proof rolling.
(e) Subgrade and base inspection. The owner/developer/ contractor shall notify the zoning administrator a minimum of 48 hours in advance to schedule required inspections.
(f) Test 2. Base must pass roll testing with a fully loaded tandem axle dump truck prior to placement of the base material.
(g) Use of roads as construction roads. When the street is to be used for construction traffic before the paving work is completed, a layer of stone (except crusher run) shall be laid as a traffic surface. This material shall not be used as a part of the base material. It may be worked into the sub-grade, or it shall be removed before the base course is set up for paving.
(h) Temporary drainage. Provisions shall be made to drain low points in the road construction when the final paving is delayed. A break in the berm section is required when the curbing has not been constructed. After installation, drainage under the curb to side slopes is required, using minimum four inch diameter pipe sections.
(13) Manhole covers and valve boxes projecting above the intermediate course shall have temporary ramps of cold mix asphalt placed at a five foot radius. Prior to application of the surface course, the cold mix asphalt shall be removed. The elevation of the top-of-structure shall be inspected by the director of public services or his designee and any needed adjustment to match the final pavement elevation shall be made. The intermediate asphalt course shall be inspected by the city to determine surface uniformity and integrity. Any settlement or other deficiencies found shall be repaired to the city's satisfaction before placement of the surface course.
(14) Curb and gutter standards.
(a) Twenty-four inch curb and gutter similar to GDOT STD. 9032B Type 2.
(i) Curb and gutter material shall be Portland cement concrete, class "A" as defined by GDOT, and shall have a minimum break strength of 3,000 psi at 28 days. All construction shall be in conformance with section 430, GDOT Standard Specifications Construction of Transportation Systems, most current edition, with supplements and revisions.
(ii) Base roadway aggregate base six inches thick shall extend under the curb and gutter for a distance of six inches beyond the back-of-curb.
(iii) Joints one-half inch asphalt-impregnated expansion joints shall be provided at all structures and radius points, and at intervals not to exceed 100 feet in the remainder. Contraction joints shall be provided at intervals not to exceed ten feet. Curb and gutter shall be set true to the line and grade of the street and finished to the section shown on the plans. Line and grade shall be field staked and set by the developer's engineer or surveyor. All gutters shall drain positively with no areas of ponding.
(iv) Damage to curb and gutter caused by construction or development activity shall be repaired from joint to joint at no cost to the City of Hogansville within 30 days or prior to the issuance of a certificate of occupancy, whichever is earlier.
(v) Workmanship. Inferior workmanship or unprofessional construction methods resulting in unacceptable curb and gutter will be cause for rejection of the finished work. Unacceptable construction shall be removed and replaced from joint to joint. Disturbed areas along all curbing shall be backfilled, stabilized, and grassed.
(b) Roll back curbs and header curbs are prohibited.
(15) Culs-de-sac, if approved, shall have a minimum radius of 60 feet to the right-of-way, and a minimum radius of 48 feet to the face of curb.
(16) Access to subdivisions shall be provided over a public street. Where subdivisions abut a public street that has a right-of-way width of less than 50 feet (larger right-of-way widths are required for some streets), the subdivider or their agent shall dedicate additional land to provide a width of 25 feet (or half the total width required) on the subdivider's side of the centerline. Where public streets less than 50 feet in width (larger right-of-way widths may be required for certain roads) traverse subdivisions, the subdivider or his agent shall dedicate additional land to provide a width of 25 feet (or half the total width required) on both sides of the centerline. Nothing herein shall be construed to obligate the City of Hogansville or subdivider or his agent to improve such road or street frontage.
(17) Approval may be denied of a proposed subdivision if the zoning administrator deems a public street to the subdivision as being inadequate due to right-of-way width or construction until such time as the road has been modified to meet city standards.
(18) Driveways within the right-of-way shall be constructed according to the latest Georgia Department of Transportation and AASHTO Standard Specifications.
(19) The developer or their agent shall furnish and install required striping and all regulatory signage (stop signs, yield signs, etc.) at proposed street intersections during construction of the streets. The city will install the street name signs and speed limit signs once the streets have been accepted. Subdivision entrance markers are not permitted within the existing or proposed public right-of-way.
(20) Inspection. The zoning administrator shall be notified prior to each phase of construction. Each developer/contractor shall notify the zoning administrator a minimum of 48 hours in advance of each requested inspection.
(21) Sewer.
(a) Where a public sanitary sewer is within 400 feet of the subdivision at its nearest point and connection by gravity flow is feasible, the subdivider shall connect with such sanitary sewer and provide a connection for each lot. The size of the mains shall be at least eight inches. The subdivider shall be responsible for the costs to existing facilities. Where sanitary sewers are not available, oxidation pond, septic tank, or other disposal device designed and installed according to the health department may be permitted.
(b) Where a public water main is within 400 feet of the subdivision at its nearest point, the subdivider shall connect with such water main. In such cases, mains of at least six inches shall be required. The subdivider shall be responsible for the costs of all taps and extensions to existing facilities. Where an adequate public water supply is not reasonably accessible as determined by the planning commission, the subdivider shall provide evidence of an individual water supply to be approved by the health department.
(22) Standard details and illustrations.
History
(Ord. No. 23-0605, § 1(Exh. A), 6-5-2023; Ord. No. 25-0505, § 36, 5-5-2025)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.