(a) Purpose and intent. By requiring traffic impact studies for proposed developments meeting certain thresholds, the city will be better able to determine the transportation demands of development proposals and provide for reduction of adverse impacts on the transportation system.
(b) Objectives. The city finds that requiring a traffic impact study for proposed developments that meet certain thresholds will help to achieve the following objectives:
(1) Forecast additional traffic associated with new development, based on accepted practices.
(2) Determine the improvements that are necessary to accommodate the new development.
(3) Allow the local government to assess the impacts that a proposed development may have and assist the local government in making decisions regarding development proposals.
(4) Help to ensure safe and reasonable traffic conditions on streets after the development is complete.
(5) Reduce the negative impacts created by developments by helping to ensure that the transportation network can accommodate the development.
(6) Provide information relevant to comprehensive planning, transportation planning, transit planning and the provision of programs and facilities for traffic safety, road improvements, transportation demand management, pedestrian access and other transportation system considerations.
(c) Thresholds of applicability.
(1) All applications for development that meet or exceeds the following thresholds shall require a traffic impact study. For developments requesting a rezoning, the study shall be conducted and submitted with the rezoning request.
Table 94-125C - Thresholds of Applicability Development Type Thresholds Office Greater than 50,000 gross square feet Commercial Greater than 50,000 gross square feet Warehouse Greater than 100,000 gross square feet Hotel Greater than 75 rooms Assembly spaces Greater than 500 seats Residential, single-family detached or attached Greater than 50 units Residential, multifamily Greater than 75 units General Any use that generates more than 100 peak hour trips
(2) The zoning official may determine that a traffic impact analysis is necessary for developments that do not meet or exceed the aforementioned thresholds based on a finding of any one or more of the following conditions:
a. There is a drive-thru proposed.
b. There is gate or any access point design requiring stacking or vehicular queuing;
c. There is modification to any existing access point.
d. There is a need to remove or add access points.
e. There will be a changing of the type of traffic control at the location.
f. There will be a roundabout, left turn lane, or other traffic calming feature proposed or required.
g. There are site visibility, roadway level of service, or emergency access concerns expressed by fire chief or city engineer during the development review process.
h. The project requires annexation, rezoning, variance, or special use permit, or any combination thereof. Or in cases where an application has been filed to amend a past condition of approval for an annexation, rezoning, variance, or special use permit.
i. Any other condition or special circumstance, for any project which generates 100 vehicle trips or more at peak hour onto city or county roadways abutting the property, as determined by the zoning official,
(d) Exemptions. Any development of regional impact that complies with rules of the Georgia Regional Transportation Authority (GRTA) shall be exempt from this article.
(e) Required contents of a traffic impact study. The traffic impact study shall be prepared following and meeting the standards of the GRTA Development of Regional Impact technical guidelines, dated March 1, 2014, as may be amended from time to time. In addition, the following components shall be included:
(1) Existing, proposed, and needed multi-modal transportation (walking, bicycling, transit, etc.) options.
(2) References. A listing of all technical documents and resources cited or consulted in preparing the traffic impact study.
(3) Technical appendix. Relevant technical information, including, but not limited to: copies of raw traffic count data used in the analysis, calculation sheets and/or computer software output for all LOS and V/C calculations in the analysis, and warrant worksheets for signals, turn lanes, signal phasing, etc. used in the analysis.
(4) Mitigation measures and costs. Listing of all intersections and road segments that are forecasted to be level of service "E" and "F" in the horizon year, or if phased, in the years that each phase is planned to be complete, and an identification and description of specific mitigation measures including signal, turn lane, or other warrant analyses as appropriate and necessary to bring these intersections and road segments into compliance with a level of service "D" or other city-adopted level of service for said road segment or intersection.
(5) If roadway improvements are needed, the study shall show a drawing at an engineering scale of one inch equals 20 feet for all recommended lane configurations.
(6) If signalization is warranted by the traffic signal warrants outlined in the Manual on Uniform Traffic Control Devices (MUTCD), a warrant analysis shall also be conducted as a part of the traffic impact study. If a traffic signal is warranted, the warrant package in the study shall show a drawing at an engineering scale of one inch equals 20 feet, detailing the signal design and phasing plans.
(7) The estimated cost associated with implementing all such mitigation measures shall be provided in the traffic impact study. The traffic impact study may take into account any city/county/state-approved roadway, traffic signalization and other improvements in determining mitigation measures and providing recommendations.
(f) Additional technical specifications. Staff is further authorized to promulgate and require the use of additional technical specifications for conducting traffic impact studies, which shall be consistent with analysis methods included in the most recent Highway Capacity Manual, Manual on Uniform Traffic Control Devices, "Trip Generation" published by the Institute of Transportation Engineers (ITE), and/or Traffic Access and Impact Studies for Site Development: A Recommended Practice (Washington, DC: Institute of Transportation Engineers, 1991), as may be amended or republished from time to time.
(g) Recommendations for mitigation of impacts. As part of its application review, staff shall complete review of the study and submit to the applicant all recommendations for mitigation measures as stated in the traffic impact study and include any interpretations or recommended conditions of approving the discretionary development proposal that will mitigate traffic impacts of the proposed development.
(h) Determination of project and system improvements. Planning and development department staff shall determine which mitigation measures constitute "project" improvements and which mitigation measures constitute "system" improvements within the context of the Georgia Development Impact Fee Act of 1990.
(i) In the event that a particular improvement is called for in the traffic impact study or recommended by staff, if staff is unable to uniquely attribute the recommendation as a project or system improvement or finds that such improve-ment has characteristics of both a project improvement and a system improvement, staff shall determine the proportion of the cost of such improvement that can reasonably be attributed to the development as a project improvement, and the portion of such improvement that can reasonably be considered a system improvement.
(j) Conditions of development. Upon the determination of project improvements needed to mitigate the traffic impacts of the discretionary development proposal as provided in this article, staff shall recommend that the project improvements be completed by the developer as conditions of approval of the discretionary development proposal.