(1) Application and exemptions. These dam regulations shall apply to all new, rebuilt, or modified stormwater impoundment's including appurtenant works whose height exceeds ten feet as measured from the natural bed of the stream or watercourse at the downstream toe of the barrier, or the lowest elevation of the outside limit of the barrier, if the barrier is not across a stream channel or watercourse, to the maximum water storage elevation, with the exception of: a. Any category I dam requiring permitting under the control of the Georgia Safe Dams Program. b. Any dam owned and operated by any department or agency of the United States Government. c. Any newly constructed dam financially assisted by the United States Soil Conservation Service or any other department or agency of the United States government when such department or agency designed or approved plans and supervised construction and maintains a regular program of inspection of the dam. d. Any dam licensed by the Federal Energy Regulatory commission, or for which a license application is pending with the Federal Energy Regulatory Commission. (2) Existing dams. Any dam currently constructed and operating and not subject to regulation under the Georgia Safe Dams Act of 1978 or located on a site for which a development permit is requested is hereby grandfathered in its present state with the owner thereof assuming all rights, responsibilities, and liabilities thereof, subject to the provisions of subsection (3) of this section. Upon any modification to the dam it shall become subject to these regulations. Dams that are located on a project site for which a development permit is being requested shall be brought up to the minimum design standards contained in these regulations regardless of whether any modifications are proposed to the dam or appurtenant structures. If the dam and structures are not wholly contained within the project boundaries the director may waive any or all of these requirements when satisfied that all reasonable efforts have been unsuccessful to obtain the approval from adjacent land owners for any work necessary to comply with these regulations. (3) Emergency draining of a lake. Upon obtaining, evidence which indicates that a potentially hazardous condition may exist (regardless of dam height), such as, but not limited to: a. Excessive leakage transporting soil from the dam interior (i.e. piping). b. Slope failure, excessive scouring or other apparent soil instability. c. Longitudinal cracks, bulging, or shifts in alignment. d. Excessive sloughing or seepage. e. Failure of the spillways and/or outlet devices to function properly (due to clog age, damage or other deficiency). The director has the authority to order the immediate and complete draining of the lake in whatever manner deemed necessary at the time and to require the owner to keep the pool down until remedial work, as is deemed most appropriate to create a safe dam condition, is completed and approved by the director. (4) New category I and category II dams.Any new or modified dams classified as category I or category II as defined by the Georgia Safe Dams Act of 1978, O.C.G.A. ยง 12-5-375 shall be subject to the following: These dams are generally defined as any artificial barrier which impounds or diverts water and either of the following is true: The barrier is more than 25 feet in height as measured from the natural bed of the stream or watercourse at the downstream toe of the barrier, or from the lowest elevation of the outside limit of the barrier, if the barrier is not across a stream channel or watercourse to the maximum water storage elevation; or It has an impounding capacity of 100 acre-feet or more. a. The developer of any new dam classified as a category I dam under the rules of the Georgia Safe Dams Act of 1978 shall be subject to the requirements of the Georgia Safe Dams Act of 1978 and Rules for Dam Safety adopted by the Georgia Department of Natural Resources. The developer shall obtain necessary approvals and permits from the environmental protection division of the Georgia Department of Natural Resources for the project and the dam prior to securing a land disturbance permit from the department. b. The developer of any new dam classified as category II under the rules of the Georgia Safe Dams Act of 1978 shall submit construction plans to the city for review of the project and the dam prior to securing a land disturbance permit from the department subject to the following: 1. If the developer elects to construct the new category II dam in accordance with the design standards for new dams as contained in the rules for dam safety, i.e. category I standards, then new development shall be permitted within the dam breach zone. 2. If the developer elects not to construct the new category II dam to the design standards for new dams as contained in the rules for dam safety, then the following information shall be submitted along with the construction plans for review prior to securing a development permit from the department: i. A dam breach analysis for the dam shall be submitted. The design engineer shall utilize the computer model entitled "DAMBRK" for the dam breach analysis. The breech analysis shall be based on a full pool, sunny day breach; and, ii. The dam shall be required to meet the minimum city standards contained in these development regulations for dam construction; and, iii. For any new dam that is proposed not to meet the design standards for new dams as contained in the rules for dam safety, the developer shall obtain a dam breach easement, recorded with the clerk of superior court, from any offsite property owner where it is proposed for the dam breach zone to extend off the property where the dam is being constructed. The developer shall also cause a dam breach easement to be recorded upon the property being developed. Only the following uses and structures shall be permitted within the dam breach easement: A. Agriculture which requires no structures for human habitation within the dam breach zone including forestry, livestock raising, and agricultural and forestry access roads. B. Fences. C. Outdoor advertising signs provided they are located no closer than 100-feet from any residence or place of business. D. Roads, driveways and parking areas. E. Utility poles, towers, pipelines, water treatment outfalls and facilities, or other similar facilities and structures. c. Prior to recording of a final plat or issuance of a certificate of occupancy, as appropriate, an as-built certification from a registered professional engineer shall be submitted to the department. The certification shall state that the dam is constructed in accordance with the provisions of these regulations as well as the authorized construction plans. If the project is for the development of a subdivision, the developer shall also establish a legal entity, acceptable to the city, such as a mandatory property owners association, prior to approval of the final plat, responsible for the maintenance of the dam and its impoundment. (5) New dams between ten feet and 25 feet in height. Any newly constructed or modified dams that is ten feet or more in height but less than 25 feet in height or having a storage capacity in between 50 acre-feet and 100 acre-feet at the maximum water storage elevation shall be subject to regulation under these development standards. Any dam that meets the height thresholds of this section and which does not meet the design standards contained in the rules for dam safety shall meet the following minimum standards: a. General requirements. 1. Design shall be by a professional engineer registered and licensed to practice engineering in the State of Georgia. 2. Plans shall be submitted to the city for review and comment. 3. Prior to construction of any dam over ten vertical feet or any dam impounding more than 50 acre-feet, the contractor shall provide the city with sufficient documentation of his qualifications to construct dams. 4. A pre-design meeting shall be held with representatives of the engineering division to review any proposed dam or proposed dam changes for any dam over ten vertical feet or impounding more than 50 acre-feet. Depending on the level of downstream risk, and size of impoundment, the city may require a dam breach analysis to be submitted for any proposed or existing dam contained within a proposed development, utilizing the National Weather Service's DAMBREAK program or other methodology approved by the Georgia Safe Dams Program. 5. When a dam breach analysis is required by the city, a sunny day dam breach analysis shall be performed under full pool conditions as a minimum. 6. All impoundments shall have a permanent drain capable of draining the pool to a depth of no more than two feet within 24 hours. 7. No roadways shall be constructed over any permanent water impoundment structure if that roadway provides the only means of egress for any lot of record, without prior approval of the city. 8. No utilities are permitted to pass through any dam, either longitudinally or transversely, without prior approval of the city. 9. In addition to the storm events that are required in these dam regulations, any dam that impounds stormwater to meet the requirements of the city's post development stormwater management ordinance shall also be evaluated based on the storm required in that ordinance. b. Report requirements. Guidelines are available from the State of Georgia Safe Dams program (EPD) to assist the design/construction professional. Dam design documents shall include, but not be limited to: 1. Hydrology/hydraulic report. 2. Geotechnical report (with borrow study, applicable). 3. Drainage basin map with land use and land improvement parameters. 4. Existing topography of site. 5. Plan view of dam. 6. Cross sections at all critical points. 7. Delineated dam breach zone. 8. Complete details. 9. Technical specifications. 10. Names and professional seals of design civil engineer and geotechnical engineer with 24-hour contact. 11. Designated contractor (if available) c. Outlet/spillway requirements. Because of the variables associated with selecting spillway(s), outlet device(s) or appurtenant structure(s) to suit a given site condition, the design consultant is responsible for the selection, subject to the review and approval of the department. The division will include in its consideration the case of maintenance, longevity of the system, blockage potential, and practicality of operations. 1. No orifice shall be less than three inches in diameter unless it is installed to meet a state or local requirement. 2. All risers (standpipes) shall be equipped with a debris deflector (trash rack) and an anti-vortex device. To facilitate outlet operation, curved or inclined a-ash racks designed to allow debris to rise with the water level are preferred. In all cases, trash racks shall be either hinged or removable to facilitate maintenance operations. corrugated metal pipe is not permitted for standpipes. 3. Spillways: Every dam shall be provided with a principal spillway, fully capable of passing at least the 50-year flood, with excess spillway capacity provided by the emergency spillway(s) capable of handling excess flows up to the design storm. The principal spillway can be sized for floods of less magnitude than the 50-year flood only if the emergency spillway is appropriately armored against scour with concrete or other suitable lining as protection against more frequent usage. 4. Principal spillway: All spillways shall be analyzed (hydraulically rated) for both inlet and outlet control conditions using appropriate tail-water ratings. If a control-box or weir-box is affixed, then the coral system (inlet control box and outlet conduit) shall be hydraulically rated to determine the stage-discharge relationship. 5. Emergency spillway(s): For every type of water impounding facility a planned safe flow path must be provided for conveyance of flows of water in an emergency. In many instances, this function can be provided through installation of an emergency spillway. Emergency spillways may be excavated open channels, either vegetated or paved with reinforced concrete or weir sections of concrete walls, or, appropriately designed conduit. Any portion of an open channel spillway excavated into a dam embankment or other fill section must be paved with reinforced concrete equipped with appropriate seepage controls, under-drainage and cut-off walls. 6. Any portion of any spillway excavated into undisturbed residual soil shall be vegetated in accordance with the practices described in the "Manual for Erosion and Sediment Control in Georgia" or protected against scour and erosion by other suitable measures if vegetation does not provide adequate stabilization. The spillway is activated by storms smaller than the 50-year frequency, and then vegetation alone will not be considered sufficient protection against scour according to these standards. d. Permanent impoundments. The following requirements shall apply to lakes and ponds that maintain a permanent pool of water: 1. Earthen dam. i. Design storm shall be at least 25 percent of the probable maximum precipitation storm event (1 /4 PMP). ii. Principal spillway shall be adequate to handle at least the 50-year flood. iii. Emergency spillway(s) as a minimum shall be adequate to handle flows in excess of the 50-year flood, up to the 1/4 PMP. Front and back slopes, each, shall not be steeper than 3:1 unless design includes a slope stability analysis that confirms and documents a steeper slope will be stable. In no condition, however, will a slope steeper than 2:1 be permitted. iv. All organics and topsoil shall be removed from the entire footprint of the dam and the foundation certified by a geotechnical engineer (PE). v. Earthen fill shall be CL or ML material approved for use by geotechnical engineer (PE) and placed and compacted to not less than 95 percent standard proctor under said engineer's direction. vi. Compaction records accompanied by a geotechnical engineer's certification that soil compaction meets this specification shall be forwarded to the city. vii. The low level outlet (lake drain) shall be concrete pressure pipe or ductile iron pressure pipe, cradled in concrete. Bedding shall be in concrete poured the full width of the exposed trench and as a minimum, up to the spring line of the pipe. Pipe and joints shall be rated for internal pressures exceeding that of the design storm and shall meet or exceed ASTM 361 or AWWA C-301. Corrugated metal pipe is not allowed. viii. A lake drain may also be comprised of a valve-operated siphon system designed by a registered civil engineer licensed in the State of Georgia. Piping for a siphon system shall be ductile iron with mechanical joints or PV joints with adequate strength and anchoring to sustain the water forces incumbent with operation. ix. Freeboard of dam above the design storm maximum pool shall be three feet in lieu of fetch calculations of wave height justifying a lesser freeboard. The city reserves the right to require additional freeboard above the nominal three-feet requirement if supported by fetch calculations. x. Crest width shall be not less than eight feet. xi. Embankments shall be protected from erosion by appropriate vegetation, rip rap, paving or some other type of protective surface and maintained in a safe condition. In appropriate vegetation such as trees or shrubs and hedges that may obscure inspection of the dam shall not be allowed or shall be removed. A qualified professional shall be consulted prior to the removal of trees over four-inch dbh or where the removal of any trees may endanger the function or stability of the dam. 2. Gravity dam (reinforced concrete or masonry). i. Design, construction supervision, and certification of completion according to plans and specifications to be by design civil engineer and a geotechnical engineer both licensed to practice in the State of Georgia. ii. Design shall address and account for overturning, uplift, and seepage with adequate safety factory and adequate freeboard. iii. All slab on grade concrete, including concrete footings, shall be designed and constructed to control seepage and piping of foundation soil along the underside of the slab in incorporating cutoff walls, or other appropriate measures. iv. Design storm shall be at least 25 percent of the probable maximum precipitation (1/4 PMP). v. Principal spillway shall be adequate to handle at least the 50-year flood unless the emergency spillway is appropriately armored against scouring. vi. Emergency spillway shall be adequate to handle flows in excess of the 50-year flood, up to the 1 /4 PMP. vii. Freeboard of dam above the design storm maximum pool shall be three feet in lieu of fetch calculations of wave height justifying a lesser freeboard. Additional freeboard above the nominal three-feet required if supported by fetch calculations. viii. All organics and topsoil shall be removed from the entire footprint of the dam and the foundation certified by a geotechnical engineer (PE). ix. Earthen fill (if any) shall be subject to the criteria specified above for earthen embankments. e. Temporary/dry impoundments. The following requirements shall apply to those stormwater facilities that are normally dry, i.e. dry detention ponds: 1. Design criteria. i. Design storm shall be at least the 100-year, 24 hour storm. ii. Multi-frequency outflow control shall be provided in accordance with the Georgia Stormwater Manual. Storm frequencies may include: 24-hour extended detention for the one-year event and peak flow attenuation for the 25-year and 100-year events. iii. Principal spillway shall be adequate to handle at least the 25-year flood. iv. Emergency spillway(s) shall be provided to handle flows in excess of the 25-year flood, up to the 100-year flood. v. Where fencing is required by subsection 113-166(9) the fence shall not extend across the emergency spillway in such a manner as to create a possible clogging hazard. 2. Earthen dam. i. Front slope shall not be steeper than 2.5:1 unless design includes a slope stability analysis that confirms and documents a steeper slope will be stable. In no condition, however, can any slope be steeper than 2: 1. ii. All organics and topsoil shall be removed from the entire footprint of the dam and the foundation inspected and approved by the city prior to fill placement. iii. Earthen fill shall be CL or ML material approved for use by geotechnical engineer (PE) and placed and compacted to not less than 95 percent standard proctor under said engineer's direction. iv. Freeboard of dam above the 100-year design storm maximum pool shall be two feet in lieu of fetch calculations of wave height justifying a lesser freeboard. The city reserves the right to require additional freeboard above the nominal two-feet requirement if supported by fetch calculations. v. Crest width shall be not less than eight feet, unless approved by the department. vi. Embankments shall be protected from erosion by appropriate vegetation, rip rap, paving or some other type of protective surface and maintained in a safe condition. In appropriate vegetation such as trees or shrubs and hedges that may obscure inspection of the dam shall not be allowed or shall be removed. A qualified professional shall be consulted prior to the removal of trees over four-inch dbh or where the removal of any trees may endanger the function or stability of the dam. 3. Gravity dam (reinforced concrete or masonry). i. Design shall address and account for overturning uplift, and seepage with adequate safety factor, and adequate freeboard. ii. All slab on grade concrete, including concrete footings, shall be designed and constructed to incorporate appropriate cutoff walls. iii. Under no condition, can any fill slope (if any) be steeper than 2:1. iv. All organics and top soil shall be removed from the entire footprint of the dam and the foundation inspected and approved by the city prior to gravity dam concrete or masonry placement. v. Earthen fill (if required) shall be approved for use by geotechnical engineer (PE) and placed and compacted to not less than 95 percent standard proctor under said engineer's direction. vi. Freeboard of dam above the 100-year design storm maximum pool shall be two feet along any earth fill sections of the dam, in lieu of fetch calculations of wave height justifying a lesser freeboard. The city reserves the right to require additional freeboard above the nominal two-feet requirement if supported by fetch calculations. (6) Existing category II dams. When an existing category II dam may be reclassified to a category I dam because of a proposed development downstream of the dam, the following shall be provided by the developer for review by the Georgia Safe Dams Program. a. Location of the category II dam and the proposed development; b. A surveyed cross-section of the stream valley at the location of the proposed development including finished floor elevations; and c. A dam breach analysis using the dam break computer model to establish the height of the flood wave in the downstream floodplain. The dam break modeling shall be completed in accordance with the safe dams program quality assurance program by a qualified registered engineer.