Johns Creek · Zoning Ordinance
Part II - CODE OF ORDINANCES / Part A - GENERAL ORDINANCES / Chapter 113 - DEVELOPMENT REGULATIONS / Article VII - PROCEDURES
Sec. 113-72. Initiation of development activities.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) Initial activities required. Following the approval of plans authorizing land disturbance of a site:
a. Pre-construction meeting. A pre-construction meeting shall be scheduled with the land development inspector assigned to the project prior to commencing any construction activities
on the site. The developer shall provide the inspector a minimum of 24-hour
notice to schedule the meeting. A permit for initial erosion and sediment control installation shall be issued if all permit conditions have been met.
b. Installation of initial erosion and sediment control measures.
1. Required erosion and sediment control measures must be installed per plan by the developer and prior to actual grading or removal of vegetation. Only tree removal and grading necessary to install erosion control measures and sediment storage facilities are allowed under the initial erosion and sediment control permit.
2. Sediment storage facilities must be installed and operational prior to major tree removal and grading operations.
3. Areas required to be undisturbed by the zoning ordinance, stream buffer ordinance, floodplain management ordinance, conditions of zoning approval, Metropolitan River Protection Act or other ordinance or regulation shall be designated by tree save fence, silt fence, or other appropriate markings and shall be inspected and approved by the department prior to the commencement of any clearing or grading activities.
c. Land disturbance permit issuance. The developer shall provide an inspection
letter from the registered engineer who prepared the land disturbance permit plans, stating that all initial erosion and sediment control measures have been
installed properly and undisturbed areas have been flagged. The city will then
issue the land disturbance permit.
(2) Tree protection areas. Prior to the initiation of land disturbance activities and throughout the clearing and grading process the following must be accomplished for a designated tree protection area in accordance with any approved buffer and landscape plan or tree
preservation/replacement plan for the property:
a. For those trees which are not to be removed, all protective fencing, staking, and any tree protection area signs shall be in place. These barriers must be
maintained throughout the land disturbance process and should not be removed until landscaping has been completed.
b. The tree protection areas shall not be utilized for storage of any materials
resulting from or equipment used during the development process.
c. Construction site activities such as parking, materials storage, concrete washout, burning, etc. shall be arranged to prevent disturbances within the tree
protection areas.
(3) Land disturbance inspections. It shall be the responsibility of the developer or contractor to notify the city at least 24 hours prior to commencement of activity for each of the following phases as authorized by any permit for site work or development. Inspections shall be made by the department and passed prior to continuation of further activity or proceeding into new phases.
a. Clearing or clearing and grubbing of the site or any portion included under the
permit.
b. Grading. Installation of slope stakes and street grade stakes may be required.
Compaction tests may be required by the city in accordance with the requirements in article XI.
c. Installation of storm drainage pipe, detention, or other stormwater facilities.
d. Installation of sanitary sewer and appurtenances. Notification shall be made by the contractor or developer to the appropriate utility provider. Approval from the utility provider may be required prior to commencement of further
development activities.
e. Curbing of roadways. Inspection should be requested before the forms have been
set (if used). Roadway width will be spot checked by string line between curb
stakes.
f. Water. Notification shall be made by the contractor or developer to the
appropriate utility provider.Approval from the utility provider may be required prior to commencement of further
development activities.
g. Sub-base or sub-grade of streets. After compaction, the sub-grade will be
checked for depth and crown. The sub-grade shall be roll tested and shall pass with no movement, to the
satisfaction of the department.
h. Street base. The base will be checked for depth and crown, and shall pass a
roll test with no movement to the satisfaction of the department.
i. Paving. A department inspector shall be on site during the paving process to
check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material may be spot-checked, and the roadways will be cored after completion to check thickness. Cores shall typically be located every 300 feet on alternating sides of the street and at the center of cul-de-sacs where no landscape island
is present. When landscape islands are present in the cul-de-sac a core will be taken at a location identified by the land development inspector. Core reports
shall be submitted to the land development inspector at the end of paving to determine compliance.
j. Sidewalks. Inspection should be requested after the forms have been set but prior to setting concrete or other materials as may be required.
k. Erosion and sediment control (E&SC).
During all stages of construction erosion and sediment control measures shall be
inspected. The applicant is responsible for continued maintenance of all E&SC measures and may by subject to inspection at any time. All temporary E&SC measures (silt fences, tree save fences, down drains, diversions, etc.)
shall be removed prior to final approval from the city.
l. Additional inspections may be required prior to approval of the final plat or
issuance of a certificate of occupancy as may be deemed necessary to ensure
compliance with the land disturbance permit. Contact the land disturbance inspector to determine additional inspection requirements.
(4) Responsibility for quality and design. The completion of inspections by city officials or employees and authorization for work
continuation shall not transfer responsibility for the quality of the work performed or materials used from the contractor or developer, nor imply or transfer acceptance of responsibility for project design or engineering from the
professional corporation or individual under whose hand or supervision the plans were prepared.
(5) Stabilization for erosion control. If for any reason a land disturbance permit expires after construction activities have commenced, the developer shall be responsible for stabilizing the site for erosion control, under the direction of the department.