6.20.05. Inspection

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Time for Inspection. The Utility shall make the Construction site available to the Director and to all others as authorized by law for inspection at all reasonable times during the execution and upon completion of the Construction.

B. Stop Work Order. At any time, including the time of inspection, the Director may order the immediate cessation of any work which poses a serious threat to the health, safety, or welfare of the public, violates any law, or which violates the terms and conditions of the Utility Permit and/or this Ordinance or issue an order to correct work which does not conform to the Utility Permit and/or applicable standards, conditions or codes.

C. Notice of Completion. When the Construction under any Utility Permit is completed, the Utility shall notify the Director in writing.

History

The history line the source prints at the end of the section.

(Ord. No. 2018-08, § 1, 4-2-18)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:kennesaw/zoning/6.20.05@2026-11-11-4f25182d44

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Kennesaw Zoning Ordinance, 6.20.05. Inspection | Georgia Commons