Sec. 25C-30-2. Plan generally, criteria.
About this text
- As published by Municode, retrieved 2026-11-14
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Stormwater design manual. The department of community development will utilize the policy, criteria and information including technical specifications and standards in the latest edition of the Georgia Stormwater Management Manual (GSMM) and any relevant local addenda to provide primary guidance for the proper implementation of the requirements of this chapter.
The stormwater management committee may grant approval of alternative methods of stormwater detention based on appropriate engineering studies that would provide for better performance in accordance with city stormwater management practices.
(b) Stormwater concept plan and consultation meeting. Before any stormwater management permit application is submitted, the land owner or developer shall meet with community development for a consultation meeting on a concept plan for the post-development stormwater management system to be utilized in the proposed land development project. This consultation meeting shall take place at the time of the preliminary plan of the development or other early step in the planning process. The purpose of this meeting is to discuss the post-development stormwater management measures necessary for the proposed project, as well as to discuss and assess constraints, opportunities and potential ideas for stormwater management designs before the formal site design engineering is commenced.
To accomplish this goal the following information should be included in the concept plan which shall be submitted in advance of the meeting:
(1) Existing conditions/proposed site plans. Existing conditions and proposed site layout sketch plans, which illustrate at a minimum: Existing and proposed topography; perennial and intermittent streams; mapping of predominant soils from soil surveys (when available); boundaries of existing predominant vegetation and proposed limits of clearing and grading; and location of existing and proposed roads, buildings, parking areas and other impervious surfaces.
(2) Natural resources inventory. A written or graphic inventory of the natural resources at the site and surrounding area as it exists prior to the commencement of the project. This description should include a discussion of soil conditions, forest cover, topography, wetlands, and other native vegetative areas on the site, as well as the location and boundaries of other natural feature protection and conservation areas such as wetlands, lakes, ponds, floodplains, stream buffers and other setbacks (e.g., drinking water well setbacks, septic setbacks, etc.). Particular attention should be paid to environmentally sensitive features that provide particular opportunities or constraints for development.
(3) Stormwater management system concept plan. A written or graphic concept plan of the proposed post-development stormwater management system including: Preliminary selection and location of proposed structural stormwater controls; location of existing and proposed conveyance systems such as grass channels, swales, and storm drains; flow paths; location of floodplain/floodway limits; relationship of site to upstream and downstream properties and drainages; and preliminary location of proposed stream channel modifications, such as bridge or culvert crossings.
(c) Review and approval authority.
(1) A stormwater management plan or application for a variance or waiver under this chapter shall be submitted to the department of community development by the developer for review and approval for any proposed development or redevelopment, unless otherwise exempted. The stormwater management plan shall contain supporting computations, drawings, and sufficient information describing the manner, location, and type of measures which will be employed to conduct stormwater runoff from the site. The department of community development will review the plan to determine the compliance with the requirements of this chapter prior to approval. The plan shall serve the basis for all subsequent construction and maintenance activities.
(2) Notification of approval or reasons for the disapproval or modification shall be issued within ten (10) regular business days after submission of the completed stormwater plan. The stormwater management plan shall not be considered authorized for implementation without the inclusion of a dated approval stamp by the department of community development.
(d) Stormwater management plan; minimum requirements. The stormwater management plan shall be prepared under the supervision of, and certified by, a Georgia registered professional engineer or landscape architect, who must verify that the design of all stormwater management facilities and practices meet the minimum stormwater management standards and requirements outlined in the Georgia Stormwater Management Manual. The plan shall include sufficient information to evaluate the environmental characteristics of the affected areas, the potential impacts of the proposed development or redevelopment on water resources, and the effectiveness and acceptability of measures proposed for stormwater runoff. The plan shall consist of maps, narrative, and supporting design calculations (hydrologic and hydraulic) for the proposed stormwater management system. The developer shall certify on the drawings that all clearing, grading, drainage, construction and development shall be conducted in strict accordance with the plan. The plan shall include all of the information required in the stormwater management site plan checklist found in the stormwater design manual. This includes:
(1) Common address and legal description of site.
(2) Vicinity map showing the site location relative to surrounding landmarks, highway intersections, rivers and streams; delineation of property lines and deed record names of adjacent property owners.
(3) Existing conditions hydrologic analysis. The existing condition hydrologic analysis for stormwater runoff rates, volumes, and velocities, which shall include: A topographic map (scale not less than one (1) inch equals fifty (50) feet) of existing site conditions with the drainage basin boundaries indicated; acreage, soil types and land cover of areas for each subbasin affected by the project; all perennial and intermittent streams and other surface water features; all existing stormwater conveyances and structural control facilities; direction of flow and exits from the site; analysis of runoff provided by off-site areas upstream of the project site; and methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology. For redevelopment sites, predevelopment conditions shall be modeled using the established guidelines for the portion of the site undergoing land development activities.
Post-development hydrologic analysis. The post-development hydrologic analysis for stormwater runoff rates, volumes, and velocities, which shall include: A topographic map of developed site conditions with the post-development drainage basin boundaries indicated; total area of post-development impervious surfaces and other land cover areas for each subbasin affected by the project; calculations for determining the runoff volumes that should be addressed for each subbasin for the development project to meet the post-development stormwater management performance criteria in section 25C-30-3(2); location and boundaries of proposed natural feature protection and conservation areas; documentation and calculations for any applicable site design credits that are being utilized; methodologies, assumptions, site parameters and supporting design calculations used in analyzing the existing conditions site hydrology. If the land development activity on a redevelopment site constitutes more than fifty (50) percent of the site area for the entire site, then the performance criteria in section 25C-30-3 must be met for the stormwater runoff from the entire site.
(4) Stormwater management system. The description, scaled drawings and design calculations for the pre- and proposed post-development stormwater management system, which shall include: A map and/or drawing or sketch of the stormwater management facilities, including the location of nonstructural site design features and the placement of existing and proposed structural stormwater controls, including design water surface elevations, storage volumes available from zero to maximum head, location of inlet and outlets, location of bypass and discharge systems, and all orifice/restrictor sizes; a narrative describing how the selected structural stormwater controls will be appropriate and effective; cross-section and profile drawings and design details for each of the structural stormwater controls in the system, including supporting calculations to show that the facility is designed according to the applicable design criteria; a hydrologic and hydraulic analysis of the stormwater management system for all applicable design storms (including stage-storage or outlet rating curves, and inflow and outflow hydrographs); documentation and supporting calculations to show that the stormwater management system adequately meets the post-development stormwater management performance criteria in section 25C-30-3(2); drawings, design calculations, elevations and hydraulic grade lines for all existing and proposed stormwater conveyance elements including stormwater drains, pipes, culverts, catch basins, channels, swales and areas of overland flow; and where applicable, a narrative describing how the stormwater management system corresponds with any watershed protection plans and/or local greenspace protection plan.
(5) Post-development downstream analysis. A downstream peak flow analysis which includes the assumptions, results and supporting calculations to show safe passage of post-development design flows downstream. The analysis of downstream conditions in the report shall address each and every point or area along the project site's boundaries at which runoff will exit the property. The analysis shall focus on the portion of the drainage channel or watercourse immediately downstream from the project. This area shall extend downstream from the project to a point in the drainage basin where the project area is ten (10) percent of the total basin area. In calculating runoff volumes and discharge rates, consideration may need to be given to any planned future upstream land use changes. The analysis shall be in accordance with the stormwater design manual.
(6) Construction-phase erosion and sedimentation control plan. An erosion and sedimentation control plan in accordance with the Georgia Erosion and Sedimentation Control Act, the "LaGrange Soil Erosion, Sedimentation and Pollution Control Ordinance" or NPDES permit for construction activities. The plan shall also include information on the sequence/phasing of construction and temporary stabilization measures and temporary structures that will be converted into permanent stormwater controls.
(7) Landscaping and open space plan. A detailed landscaping and vegetation plan describing the woody and herbaceous vegetation that will be used within and adjacent to stormwater management facilities and practices. The landscaping plan must also include: Tree saving plan; the arrangement of planted areas, natural and greenspace areas and other landscaped features on the site plan; information necessary to construct the landscaping elements shown on the plan drawings; descriptions and standards for the methods, materials and vegetation that are to be used in the construction; density of plantings; descriptions of the stabilization and management techniques used to establish vegetation; and a description of who will be responsible for ongoing maintenance of vegetation for the stormwater management facility and what practices will be employed to ensure that adequate vegetative cover is preserved.
(8) Operations and maintenance plan. Detailed description of ongoing operations and maintenance procedures for stormwater management facilities and practices to ensure their continued function as designed and constructed or preserved. These plans will identify the parts or components of a stormwater management facility or practice that need to be regularly or periodically inspected and maintained, and the equipment and skills or training necessary. The plan shall include an inspection and maintenance schedule, maintenance tasks, responsible parties for maintenance, funding, access and safety issues. Provisions for the periodic review and evaluation of the effectiveness of the maintenance program and the need for revisions or additional maintenance procedures shall be included in the plan.
(9) Maintenance access easements. The applicant must ensure access from public right-of-way to stormwater management facilities and practices requiring regular maintenance at the site for the purpose of inspection and repair by securing all the maintenance access easements needed on a permanent basis. Such access shall be sufficient for all necessary equipment for maintenance activities. Upon final inspection and approval, a plat or document indicating that such easements exist shall be recorded and shall remain in effect even with the transfer of title of the property.
(10) Inspection and maintenance agreements. The applicant must execute an easement and an inspection and maintenance agreement binding on all subsequent owners of land served by an on-site stormwater management facility or practice in accordance section 25C-30-2(4).
(11) Evidence of acquisition of applicable local and non-local permits. The applicant shall certify and provide documentation to the department of community development that all other applicable environmental permits have been acquired for the site prior to approval of the stormwater management plan.
(e) Stormwater management inspection and maintenance agreements. Prior to the issuance of any permit of occupancy for a land development activity requiring a stormwater management facility, the applicant or owner of the site must execute an inspection and maintenance agreement, and/or a conservation easement, if applicable, that shall be binding on all subsequent owners of the site. A preliminary inspection and maintenance agreement, if applicable, must be approved by the city prior to plan approval. The final approved and executed stormwater facility maintenance agreement must be recorded in the deed records before a permit of occupancy will be issued. Responsibility for the operation and maintenance of the stormwater management facility or practice shall remain with the property owner and shall pass to any successor owner. If portions of the land are sold or otherwise transferred, legally binding arrangements shall be made to pass the inspection and maintenance responsibility to the appropriate successors in title. Multi-phased projects that are to be permitted by individual phases that utilize stormwater facilities from the previous phase and/or add new stormwater facilities for the subsequent phase may amend, upon approval by the city, the original approved stormwater management inspection and maintenance agreement to reflect the new phase being permitted. The city may also seek bonds or other securities to guarantee construction or maintenance obligations for the subsequent phases being permitted. A copy of the stormwater facility maintenance agreement is available from the department of community development. The inspection and maintenance agreement shall consist of the following:
(1) Responsible person(s). The inspection and maintenance agreement shall identify by name or official title the person(s) responsible for carrying out the inspection and maintenance. These arrangements shall designate for each portion of the site, the person to be permanently responsible for its inspection and maintenance.
(2) Schedule. As part of the inspection and maintenance agreement, a schedule shall be developed for routine inspection and maintenance to ensure proper function of the stormwater management facility or practice.
(3) Plans for annual inspections. The agreement shall also include plans for annual inspections to ensure proper performance of the facility between scheduled maintenance events and shall also include remedies for the default thereof.
In addition to enforcing the terms of the inspection and maintenance agreement, the department of community development may also enforce all of the provisions for ongoing inspection and maintenance in section 25C-30-6 of this article.
(f) Performance and maintenance bonds. The posting of bonds or other security to guarantee performance of construction and/or maintenance obligations hereunder shall be required for all above ground stormwater retention facilities.
History
(Ord. No. 21-10, § 1, 6-22-21)