Lamar County · Zoning Ordinance
Appendix 1 - ZONING / Article 12 - P-M PLANNED DEVELOPMENT—MIXED USE
Sec. 1205. Plan review and approval procedures.
About this text
- As published by Municode, current through 2024-12-17
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Pre-application conference: Prior to filing a formal application for a P-M development, the applicant is encouraged to confer with the administrative officer and the planning commission in order to review the general character of the plan (on the basis of a tentative land use
sketch if available), and to obtain information on development standards and ordinances affecting the proposed project.
(b) Submission of application for P-M approval:
(1) The applicant must file a petition with the administrative officer for approval of the proposed P-M development. This application must be supported by a development plan and a written summary of intent. The relationship between the proposed development and the surrounding area, both existing and proposed, must be shown. The following information must be presented with the application:
a. A general location map.
b. Existing topographic conditions, including contour intervals of no more than five (5) feet based on field surveys or photogrammetric methods; showing the location or non-existence of any special flood hazard areas (SFHA) with the base flood elevations (BFE).
c. The existing and proposed land uses and the approximate location of all buildings and structures.
d. The approximate location of existing and proposed streets.
e. The approximate location of all existing and proposed utilities, including a preliminary utility and drainage plan.
f. The present zoning pattern in the area.
g. A legal description of the subject property.
h. The location and use of existing and proposed public, semi-public, and community facilities such as schools, parks and open areas on the site.
This includes areas proposed to be dedicated or reserved for community or public use.
i. Perspective drawings of representative building types; however, this is not required for single-family detached dwellings.
(2) If a proposed development creates special problems or involves unusual circumstances, additional information may be required in order to properly evaluate the
proposal as follows:
a. An off-street parking and loading plan.
b. An economic feasibility report or market analysis.
c. A traffic study of the area, and a circulation plan within the proposed development as well as to and from existing streets adjacent to the site.
(3) The written summary of intent submitted with the development plan must include the following information:
a. A statement of the present ownership of all land within the proposed development.
b. An explanation of the character of the proposed development; this includes a summary of acres, number and types of dwelling units, and gross
density by type of land use.
c. A general statement of the proposed development schedule.
d. Agreements, provisions, and covenants which govern the use, maintenance and protection of the development and any common or open areas.
(c) Review and approval of P-M application:
(1) An application for approval of a P-M development is treated administratively as an application for an amendment to these
regulations (rezoning). This is because P-M districts are created only upon request of a developer, whose application materials demonstrate a firm commitment to construction of a well-designed P-M development. Upon approval of the
P-M development, existing zoning must be changed to a P-M zone, which is an amendment to the ordinance. The amendment procedures contained in sections 410 and 2302 must be followed in granting the amendment to permit the P-M development.
(2) The administrative officer will forward the application materials to the planning commission for its recommendations. The planning commission will thoroughly study the materials and make written recommendations to the Lamar County Board of Commissioners, stating the reasons for
its recommendations (according to procedures contained in sections 410 and 2302).
(3) The power to approve an amendment creating a P-M district rests with the Lamar County Board of Commissioners. After
conducting the public hearing and considering recommendations from the planning commission (section 410), the Lamar County Board of Commissioners will then
make an official decision on the proposed P-M development. The Lamar County Board of Commissioners may approve, disapprove, or conditionally approve the development plan.
(4) If the development plan is approved as submitted, the official map will be changed to indicate P-M district (section 2302). If the plan is approved with modifications, the applicant must file with the administrative officer the following:
a. Written notice of consent to the modifications.
b. A properly revised site plan.
(5) The official map will then be changed (section 2302). The site plan and supporting information of any approved plan will be properly identified and permanently
filed with the administrative officer.
(6) No building permits will be issued by the administrative officer until the development plan has been approved by the Lamar County Board of Commissioners.
(d) Issuance of building permits: The administrative officer will issue building permits for buildings and structures in the area covered by the approved development plan if the proposed buildings and structures are in conformity with the approved development plan, the development
schedule, and all other applicable regulations.
(See section 404)
(e) Revision of development plan after approval of plan:
(1) Minor extensions, alterations, or modifications of existing buildings or structures may be permitted after review and approval by the planning commission: Such changes must be consistent with the purposes and intent of the development plan.
(2) Any major or substantial change in the approved development plan which affects the intent and character of the development, the density of land use pattern, the location or dimensions of streets, or similar substantial changes must be reviewed and approved by the Lamar County Board
of Commissioners after receipt of recommendations from the planning commission. A request for a revision of the development plan must be supported by a written statement indicating the nature
of the revision and the reasons it is considered necessary or desirable to revise the development.
(f) Approval of P-M revoked if construction not begun: Construction of the planned development must begin within one (1) year of the approval of the P-M. If no construction has begun by then, or if the applicant fails to maintain the approved development schedule, approval of the development plan will lapse. At its discretion and for good cause, the Lamar County Board of Commissioners may extend the period for beginning construction of any phase of the project for one (1) additional year. If approval of the development plan lapses under this provision, the subject P-M district will be removed from the official map (see section 2302) and the zoning districts and regulations which were in effect prior to the approval of the development plan will be reinstated. It is not
necessary to follow section 410 amendatory procedures for this action, since its purpose is to correct an illegal situation caused by the failure of
the applicant to fulfill the conditions upon which the approval of the P-M development was granted.
History
(Ord. No. 2010-16, 11-16-10)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.