Sec. 38-123. Permit submission and approval process.

About this text

  • As published by Municode, current through 2026-06-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) The applicant shall submit the required number of copies of the application and all supporting plans and documentation to the manager of development services. The presence of an engineer's or surveyor's seal and signature on the plans shall certify that the submitted plans meet or exceed the standards and specifications of the county.

(b) Such permit and required documentation and plans will be distributed by the manager of development services to the reviewing departments. The reviewing departments and the manager of development services shall review all submitted documentation for compliance with this chapter and other county ordinances and standards.

(c) If the plans conform to all requirements, and all payments for plan processing or any traffic control signage and/or any other required moneys or documentation has been received, the manager of development services shall issue a permit authorizing construction.

(d) Permits shall be issued or denied as soon as practical but in any event not later than 45 days after receipt by the manager of development services of a completed application, providing variances and bonding are obtained, where necessary.

(e) If it is determined by the manager of development services during review that additional information is required, a new 45-day review period begins after the submittal of the requested information.

(f) If a permit is denied the reasons for denial shall be stated in writing to the applicant who may then take corrective action or submit additional information to meet county requirements.

(g) Subdivision development requirements are as follows:

(1) If the manager of development services through the permit review process requires changes in the construction plans which require a substantial material change in the approved preliminary plat or if between the approval of the preliminary plat and the land development permit application submittal, the developer makes a substantial material change in the approved preliminary plat, an amended preliminary plat shall be provided by the developer and submitted to the planning commission for their review and approval. If the amended preliminary plat is approved by the planning commission the manager of development services shall approve or deny the permit application.

(2) Substantial material change is considered to be on the order of:

a. Roadway alignment changed to outside the original right-of-way limits;

b. Addition of a new roadway;

c. Any expansion outside the boundaries of the original preliminary plat limits;

and

d. Any change the planning director deems as a substantial material change.

History

The history line the source prints at the end of the section.

(Ord. of 9-18-2000(2), § 38-123)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:lee-county/zoning/38-123@2026-06-23-9299d5610c

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Lee County Zoning Ordinance, Sec. 38-123. Permit submission and approval process | Georgia Commons