(a) Providing adequate coverage of disturbed soils to prevent erosion and sediment build up is the intent of this section.
(b) Grassing shall meet the requirements found in the Manual for Erosion and Sediment Control in Georgia.
(c) The extent of grassing consists of those areas which are disturbed by operations and are not covered over by improvements except where specifically noted otherwise together with any additional areas shown on the drawings or designated by the manager of development services.
(d) Grassing operations include, but are not limited to, the following:
(1) Ground preparation;
(2) Seeding;
(3) Liming;
(4) Fertilizing;
(5) Mulching;
(6) Watering; and
(7) Maintenance of grassed areas.
(e) Specified work is minimum required, and any and all necessary materials and operation including reworking shall be performed to obtain specified results.
(f) Grassed areas will be considered acceptable when a viable stand of grass covers at least 90 percent of the total area with no bare spots exceeding one square foot and the ground surface is fully stabilized against erosion.
(g) Maintenance. Maintain grassed areas until the required grass coverage is achieved.
(h) Final inspection and acceptance.
(1) When the grassing work is completed, including maintenance, the county will, upon request, make an inspection to determine acceptability.
(2) Where inspected work does not comply with the requirements the contractor shall replace rejected work and continue specified maintenance until reinspected by the county and found to be acceptable.
(i) Trench grassing.
(1) All disturbed areas adjacent to the work shall be grassed and an appropriate grass coverage is achieved.
(2) Maintain as required to obtain grass coverage within 90 days, regrass after 90 days if desirable stand [not] obtained.
(3) No bahaia grass will be permitted on county right-of-way or easements. Care shall be taken to match existing materials in developed areas.
(4) Apply straw or hay mulch, spread uniformly with 24 hours after seeding and/or planting.