Sec. 38-83. Activities that require permits.

About this text

  • As published by Municode, current through 2026-06-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) A land development permit shall be required prior to the commencement of any construction for the purpose of residential, commercial, industrial or institutional uses or for major subdivisions, as defined in chapter 58, article I, section 58-8, that have been granted preliminary approval by the planning commission.

All persons proposing development and/or construction in the county for a major subdivision, as part of a larger plan of development or sale shall submit a storm water plan to the county for approval. The storm water plan may consist of a combination of storage and/or controlled release of storm water runoff in accordance with article VII of this chapter. On site detention or retention shall be required when the proposed development will increase the peak rate of runoff by more than one cubic foot per second (CFS) for a ten-year frequency storm. A proposed development shall include any and all phases of a plan or general development plan under the same name or ownership.

(b) An individual site development permit shall be acquired prior to the beginning of any construction for the purpose of commercial, industrial, institutional or residential developments requiring site construction improvements on already subdivided parcels of property.

(c) An erosion and sedimentation control permit shall be acquired prior to the beginning of any land-disturbing activities that are not exempt under this chapter. This permit is included in subsections (a) and (b) of this section.

(d) A right-of-way/easement permit shall be required for the use [of] county rights-of-way or easements for the construction, installation, or maintenance of any public or private utility, any other facility approved by the board of commissioners, any structure, driveway, culvert, pavement or object in the right-of-way or easements other than those constructed or maintained by the board of commissioners.

(1) Exemptions. No right-of-way/easement permits shall be required for the following:

a. Construction of water, sewer, power, telephone or other utilities in subdivisions in accordance with plans approved by the planning and development department where such construction will be completed prior to the acceptance of the rights-of-way and easements by the board of commissioners and done as part of the permitted subdivision site improvement.

b. Repairs of previously permitted utilities in the right-of-way; provided, however, such repairs do not require cutting of any pavement, including curbs and sidewalks.

History

The history line the source prints at the end of the section.

(Ord. of 9-18-2000(2), § 38-83; Ord. of 12-6-2004(3))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:lee-county/zoning/38-83@2026-06-23-b08ed16488